ABOUT NTPC
 NTPC ,the largest power company in India ,was setup in 1975 to accelerate power
development in country.
 NTPC Dadri is a unique power plant of NTPC group which has coal based thermal plant and
gas based thermal plant of 1820 MW ,830 MW and solar based plant 5MW respectively.
 NTPC has installed capacity of 29,397MW.
 It has 15 coal based power station ,7 gas based power stations and 1 solar based power station.
 It plans to be 75,000MW company by 2017.
NTPC DADRI

COAL GAS SOLAR


BASED BASED BASED

1820 830 5
MW MW MW

TOTAL = 2655 MW
INTRODUCTION TO CHP.

 In Thermal power plant coal is used as fuel.


 NTPC is maintaining MGR(merry go round) system
to transport the coal.
 Here wagons are unloaded in two ways:
i. Wagon tippler.
ii. Track hoper.
The coal is unloaded from a box type wagon by tilting
150deg angle.
 In this the wagons are bottom open type.
 To open and to close we use air compressors.
 CRUSHER HOUSE : Crusher house is used
to crush the coal to a size of 20mm.
The house consists of crusher blades.
CONVEYOR PROTECT SYSTEM.

 Pull cord switch : Pull cord switch is


used as a safety switch to stop
the conveyor emergency.

 Belt sway switch : The switch allows smooth running of


conveyor and protects it from overswaying due to uneven
loading of material.
 Chute block switch : Chute block switch is
used to monitor the chute
jamming in hopper & give early
warning of Belt Damage.

 Field & desk emergency push button : Emergency


push button is an electronic switch used to stop the
conveyor.
Interlock systems.
 Magnetic separator :

 Metal detector :
 STACKER RECLAIMER is a large machine
used to handle bulk material.
 Generally it is rated in tonnes per hour
(tph).
 It can usually move in 2 directions:
horizontal and vertical.

LONG TRAVEL DRIVE.


 Bucket wheels are used for digging the coal back and sending it to the boiler
when coal is required.
STACKER RECLAIMER
C
The target of NTPC was to achieve 75,000 MW
O by 2017. Which it did !!
N In CHP most of the induction motors are of
squirrel cage motors.
C
L In CHP fluid coupling of motors employed.