Professional Documents
Culture Documents
MRP Management and Lot-Sizing Techniques: Neil G. Tuazon Bsa Iv-B
MRP Management and Lot-Sizing Techniques: Neil G. Tuazon Bsa Iv-B
and
Lot-Sizing Techniques
Neil G. Tuazon
BSA IV-B
MRP Management
System Nervousness
- frequent changes in the
MRP system.
Two tools to reduce MRP System
Nervousness:
1. Time Fences
A way of allowing a segment of the master
schedule to be designated as not to be
rescheduled.
2. Pegging
Tracing upward in the bill of material (BOM)
from the component to the parent item.
MRP and JIT
Material Requirements Planning (MRP)
Is a planning and scheduling technique
with fixed lead times.
Just-in-Time (JIT)
Is a way to move material expeditiously.
Two approaches for integrating the
two systems:
Small Bucket Approach
Steps :
Step 1Reduce MRP “buckets” from weekly to daily
or perhaps hourly.
Buckets – time units in a material
requirements planning (MRP) system.
Bucketless System – time-phased data are
referenced using dated records rather than
defined time periods, or buckets.
Step 2 The planned receipts that are part of a
firm’s planned orders in an MRP
system are communicated to the work areas
for production purposes and used to
sequence production.
Step 3 Inventory is moved through the plant
on a JIT basis.
Step 4 As products are completed, they are
moved into inventory (typically
finished goods inventory) in the normal
way.
Step 5 A system known as back flush is
used to reduce inventory
balances.
Back Flush – a system to reduce
inventory balances by deducting
everything in the bill of material upon
completion of the unit.
Balanced Flow Approach
Lot-Size
- it is the item quantity that is
made or purchased.
- measure or quantity
increment acceptable to or
specified by the party offering to
buy or sell.
Lot-Sizing Techniques
Different mathematical
models are designed to assist
decision making at all level
of plant design and control.
Lot-Sizing Decisions
The process of, or techniques
used in, determining lot size.
Lot-Sizing Techniques
1. Lot-for-lot
2. Economic Order Quantity
(EOQ)
3. Part Period Balancing (PPB)
4. Wagner-Whitin Algorithm
Lot-for-lot
A lot-sizing technique that
generates exactly what was
required to meet the plan.
MRP Lot-Sizing Problem: Lot-for-Lot Technique
1 2 3 4 5 6 7 8 9 10
Gross Requirements 35 30 40 0 10 40 30 0 30 55
Scheduled Receipts
Projected on Hand 35 35 0 0 0 0 0 0 0 0 0
Net Requirements 0 30 40 0 10 40 30 0 30 55
Gross Requirements 35 30 40 0 10 40 30 0 30 55
Scheduled Receipts
Projected on Hand 35 35 0 0 0 0 0 0 0 0 0
Net Requirements 0 0 0 0 0 0 0 0 0 0
Gross Requirements 35 30 40 0 10 40 30 0 30 55
Scheduled Receipts
Projected on Hand 35 35 0 0 0 0 0 0 0 0 0
Net Requirements 0 30 40 0 10 40 30 0 30 55
Gross Requirements 35 30 40 0 10 40 30 0 30 55
Scheduled Receipts
Projected on Hand 35 35 0 0 0 0 0 0 0 0 0
Net Requirements 0 30 40 0 10 40 30 0 30 55
Gross Requirements 35 30 40 0 10 40 30 0 30 55
Scheduled Receipts
Projected on Hand 35 35 0 0 0 0 0 0 0 0 0
Net Requirements 0 30 40 0 10 40 30 0 30 55
Gross Requirements 35 30 40 0 10 40 30 0 30 55
Scheduled Receipts
Projected on Hand 35 35 0 43 3 3 66 26 69 69 39
Net Requirements 0 30 0 0 7 0 4 0 0 16
Ten-week usage equals gross requirement of 270 units; therefore, weekly usage equals
27, and 52 weeks (annual usage) equals 1,404 units.
From Chapter 12. the EOQ model is
Q* = 73 units
Setups = 1,404/73 = 19 per year
Setup Cost = 19 x $100 = $1,900
Holding Cost = (73/2) x ($1 x 52 weeks) = $1, 898
Setup Cost + Holding Cost = $1,900 + $1,898 = $3,798
The EOQ solution yields a computed 10-week cost of $730 [$3,798 x (10 weeks/52 weeks)
= $730]
Notice that actual holding cost will vary from the computed $730, depending upon the
rate of actual usage. From the preceding table, we can see that in our 10-week example,
costs really are $400 for 4 setups, plus a holding cost of 318 units at $1 per week for a total
of $718. Because usage was not constant, the actual computed cost was in fact less than
the theoretical EOQ ($730), but more than the lot-for-lot rule ($700). If any stockouts had
occurred, these costs too would need to be added to our actual EOQ of $718.
MRP Lot-Sizing Problem: EOQ Technique
1 2 3 4 5 6 7 8 9 10
Gross Requirements 35 30 40 0 10 40 30 0 30 55
Scheduled Receipts
Projected on Hand 35 35 0 43 3 3 66 26 69 69 39
Net Requirements 0 30 0 0 7 0 4 0 0 16
Ten-week usage equals gross requirement of 270 units; therefore, weekly usage equals
27, and 52 weeks (annual usage) equals 1,404 units.
Part Period Balancing (PPB)
An inventory ordering
technique that balances setup
and holding costs by changing
the lot-size to reflect
requirements of the next lot-
size in the future.
PPB Calculations
Trial Lost Size
Periods (Cumulative Net Costs
Combined Requirements) Part Periods Setup Holding Total
2 30 0 40 units held for 1 period = $40
2,3 70 40 = 40 x 1 10 units held for 3 periods = $30
2,3,4 70 40
6,7,8 70 30 = 30 x 1 + 0 x 2
6,7,8,9 100 120 = 30x 1 + 30 x 3 100 + 120 = 220
(Therefore, combined periods 6 through 9; 120 is as close to our EPP of 100 as we are going to get.)
10 55 0 100 + 0 = 100
300 + 190 = 490
MRP Lot-Sizing Problem: PPB Technique
1 2 3 4 5 6 7 8 9 10
Gross Requirements 35 30 40 0 10 40 30 0 30 55
Scheduled Receipts
Projected on Hand 35 35 0 50 10 10 0 60 30 30 0
Net Requirements 0 30 0 0 0 40 0 0 0 55