Professional Documents
Culture Documents
Project Presentation BY Onyia Chukwuka Obinna Agu Victoria Chinonso ON Project Management
Project Presentation BY Onyia Chukwuka Obinna Agu Victoria Chinonso ON Project Management
BY
ONYIA CHUKWUKA OBINNA
ON
PROJECT MANAGEMENT
USING CPM/PERT METHODS
(A CASE STUDY OF HELICON ASSOCIATES,
OWERRI).
CHAPTER ONE
INTRODUCTION
• Project management is the discipline of planning, organizing and managing
resources to bring about the successful completion of specific project goals and
objectives.
• Project management has been practiced since early civilization. Two fathers of
project management are Henry Gantt, the father of planning and control
techniques, which is famous for his use of Gantt chart as a project management
tool. And Henry Fayol for his creation of a project management function which
forms the foundation of the body of knowledge associated with project and
project control management. The 1950’s marked the beginning of the modern
project management era. At that time, two mathematical project scheduling
models were developed. The Critical Path Method (CPM) developed as a joint
venture between Dupont Corporation and Remington Rand Corporation for
managing plant maintenance projects. And the Program Evaluation and Review
Technique (PERT) developed by Booz-Allen and Hamilton as part of the United
States Navy’s Polaris missile submarine program. These mathematical
techniques quickly spread into many private enterprises.
• Basically, CPM/PERT are project management techniques
which have been created out of the need of western
industrial and military establishment to plan schedules and
control complex projects. Its graphic way of showing and
managing events and activities in a project provides a clear
and efficient method to analyze and allocate resources in
order to meet deadlines in a project.
• In this work, we present a study that describes the method
and models that are applied in estimating the durations
involved in project management. Traditionally, the managers
or experts estimate the durations of each activity in a project
and this is often based on their knowledge, experience or
historic data. This paper presents research that provides
more accurate method to achieve the objectives.
Objective of the Study
Free Float: This is defined as the excess of the time span defined from
the earliest occurrence of event i to the earliest occurrence of event j
over the duration of (i,j) i.e., TFij = j- i - Dij.
By definition, FFij ≤ TFij.
Red-Flagging Rule: For a noncritical activity (i,j)
(a) If FFij = TFij, then the activity can be scheduled anywhere within it’s ( j ,
i
) span without causing schedule conflict.
(b) If FFij ‹ TFij, then the start of the activity can be delayed by at most FF ij
relative to its earliest start time ( i) without causing schedule conflict.
Any delay larger than FFij (but not more than TFij) must be coupled with an
equal delay relative to j in the start time of all the activities leaving
node j.
The implication of the rule is that a non critical activity (i,j) will be red-flagged if
its FFij = TFij. This red flag is important only if we decide to delay the start of the
activity past its earliest start time, i, in which case we must pay attention to the
start times of the activities leaving node j to avoid schedule conflicts.
The critical path is the longest duration path through the network. The
significance of the critical path activities that lie on it cannot be delayed
without delaying the project. Because of its analysis is an important aspect of
project planning.
The critical path can be identified by determining the following four
parameters for each activity;
1. ES – Earliest start time: The earliest time at which the activities must be
completed first. This is represented mathematically as ECij = ESij + Dij, where
ECij is the earliest completion time which are defined for activity(i,j).
2. EF – Earliest finish time: This is equal to the earliest start time for the
activity plus the time required to complete the activity i.e. EFij = ESi + Dij
3. LF – Latest finish time: The latest time at which the activity can be
completed without delaying the project.
4. LS – Latest start time: This is the latest time an event can begin without
delaying the entire project. This is represented mathematically as LSij = LCj – Dij,
where LC is the latest completion and Dij is the duration. Therefore LCn = ESn, as
we observed.
The slack indicates how much delay in reaching n event can be tolerated
without delaying the entire project completion time. Suppose ESi is the earliest
start time of all the activities emanating from event i, then ES i represents the
earliest occurrence time of event i. If i = 0 is the ‘start’ event, then
conventionally for the critical path computation ESo = 0. Let Dij be the duration
of activity (i,j). The forward pass calculation is obtained from the formula;
a m b
Where μ represents the average length of time of the job duration. The value of
m depends on how close the value of ‘a’ and ‘b’ are relative to m. The expected
time to complete an activity is approximated as:
μ = a + 4m + b
6
The variance of the time is given as:
V2 = b – a 2
6
The spread of the distribution is equal to six times the standard deviation σ,
thus;
6σ = b – a or σ = b – a
6
3.2 TABULATION AND ANALYSIS OF CPM.
The table and diagram below shows the various events and calculates the
Forward Pass, Backward Pass, Total Float and Free Float for the CPM method.
2
2 C=
0 a=
2 2
2 9 10 11 14 16 19 21 31 34 39 42 49
2
g=1 h=1 i=3 j=2 k=3 m=2 0=10 p=3 q=5
1 b=2
3
f=5
4 5 6 7 8 9 11 12 13 14 r=3
15 s=7 16
0 4 9 10 11 14 16 19 21 31 34 39 42 49
l=
1
20
C=
u=
4 10
5
l=4
53 n=4
57
60 54
4 62 19 53
y=3 v=4
67
d=
ac=2 21 26
ad=5 17
5
18 W=5 22
23 57
80
62 62 60 53
67
Ae
=1
z=
68
3
24
af=4
X=5
68 72
25
ag=5
77
72
an=1
79
ai=2 27 80
Ah=3
29
77 28
79
ab=2
80
ak=1
9 80
20 al= Aj=
1 30 1
77 80
Am
=1
81
31
81
ACTIVITY 19-28 (z): START TIME = 65, DELAY relative to its EARLIEST START = 8,
FREE FLOAT = 20.
ACTIVITY 20-29 (ab): START TIME = 47, DELAY relative to its EARLIEST START =
38, FREE FLOAT = 68.
ACTIVITY 29-31 (al): START TIME = 80, DELAY relative to its EARLIEST START = 1,
FREE FLOAT = 1.
ACTIVITY 26-31 (an): START TIME = 54, DELAY relative to its EARLIEST START = 0,
FREE FLOAT = 26. FINISH preceding activities (u) must be moved back to time
54 (or earlier if possible).
Once a critical path is identified, the interest shifts to seeing where it is
possible to save time and where schedule can be allowed to slide for a while, if
it will be advantageous. Information that helps in solving this problem is
provided by the slacks or floats of the non-critical activities. In order to
calculate these floats, the earliest start and completion as well as the latest
start and completion must be known for each activity. This can be seen in the
table below.
The list of critical activities for the CPM includes;
Codes Names
1–2 Site clearing
2–3 Bringing of materials
3–4 Setting – out (pegging)
4–5 Excavation (including septic tank)
5–6 Placing of pillars
6–7 Blinding of foundation (including septic tank)
7–8 Forming of block work to DPC level (including septic tank)
8–9 Backfilling and ramering
9 – 11 Casting of German floor to DPC level
11 – 12 Placing of formwork and reinforcement for columns
12 – 13 Block work to lintel stage
13 – 14 Formwork for lintel and slabs (for septic tank)
14 – 15 Casting of columns, lintel and slab (for septic tank)
15 – 16 Leveling with block work
16 – 17 Carpentry work for roofing
17 – 19 Roofing with aluminum sheets
19 – 21 Setting of aluminum frames for windows
21 – 22 Fixing of doors and windows
22 – 23 Fixing of window protectors
23 – 24 Rendering of walls (inside)
24 – 25 Covering of septic tank with slabs
25 – 27 Flooring (with tiles)
27 – 28 Rendering of walls (outside)
27 – 29 Internal furnishing
28 – 31 Landscaping
29 – 30 Disposal of unwanted materials from site
30 – 31 Handover