INTRODUCTION
Raw materials - bauxite, coal, caustic,
furnace oil, C.P coke comes through
railway siding.
4
INTRODUCTION
The overall functioning of Alumina
Tippler can be broadly divided in to 4 major Sections :
( A) Shunting & Weighment
( Railway section )
1 rake = 59 wagons
6
Working of Railway Siding
7
Railway Siding
Placement of Different material Wagons at
process.
BC11AY0002
1
BC11816
Reclaim #1
BC11AY0017
VGF BC11AY0016 BC1007
BC11AY0012
3
BC11AY0015 BC1001
BC11AY0019
BC11AY0051
D/Gate & Chute
BC Belt Conveyor
Cone Crusher
Stock 10
Wagon Tippler Plant Capacity =600 TPH
At Boiler & Cogen plant
requirement of coal is
around 2800 MT/Day.
BMS Impactor
Aprox 10,00,000 MT
VGF
Coal /Annum
3 Way Gate
Screen Screen
Stock Pile
+25mm -75
mm
Stock Pile
- 25 mm & +75 11
mm
Coal Handling Plant & Its Major Equipment
Wagon tippler 82.5 Ton 1 No.
Hopper 150 Ton 2 nos.
13
Working of Wagon Tippler
(B) Unloading & Crushing
• Weighed wagons are placed on WAGON TIPPLER
(This equipment unloads the Box N (open on top)
wagon by tippling to 160 deg rotation) for unloading
of materials
• The Wagon Tippler unloads 8 –9 wagons / Hour into
an underground 150 Ton capacity hopper. The
Bauxite is retrieved from the hopper at @ 550 TPH by
2 nos Apron Feeder, conveyed and Crushed
From (-) 350mm to (-) 75mm size as per customer
requirement.
14
Working of Wagon Tippler
Hydraulic unit
16
Hopper and Apron Feeder
Materials unloaded to hopper
Conical in shape
17
Apron Feeder
Apron Feeders are usually installed under a hopper or bin
18
Apron Feeder
Working principle of Apron Feeder – VFD (variable
frequency drives) where speed of motor is varied
that helps:
To optimize the feed rate
Frequency is set depending upon the size of
bauxite and coal fed.
Size Freq.
Fine 50%
13 inch 80%
19
Belt Conveyor
• Designed according to lump size.
• Made of rubber on nylon.
• Nylon ply provides strengthening and Rubber
gives cushioning effect .
20
Belt Conveyor accessories
Types of pulleys attached to belt conveyor:
Head pulley
Snub pulley
Bend pulley
Tail pulley
Rollers attached:
Transaction roller
Impact roller
Troughing roller
Return roller
Self aligned Roller
Safety attachment
Zero Speed switch
Pull cord switch
21
VGF (Vibrating Grizzly Feeder)
22
Bauxite Crushing Unit
After VGF, oversized materials are passed to crushing
unit.
Feed plate helps distribution of material uniformly before
sending to crushing unit.
Cone crusher breaks the material by squeezing action
provided by eccentrically gyrating spindle.
Reduction of bauxite is from 8-10 inches to 3-4 inches.
23
Cone Crusher
Bauxite crushing
350 mm to -75 mm
24
Impact Crusher (Coal Impactor)
The material to be reduced is feed into hopper from which, it
falls directly in to the center of impactor impeller rotating at
high speed. The material is then uniformly jlug outwards by
centrifugal force. The rotating speed of the impeller assembly
along with the precision speed and angles outwards and
forwards against the stationary. Other flying particles. Each
impact reduces the material further. The plates are position at
sufficient distance from the rotating impeller to allow free
body impacting. The resulting fragmented cubical product is
discharged by gravity. Output gradation within limits can be
controlled by varying these two factors (1) impeller speed (2)
the feed material characteristic. The impactor gives superior
cubical shape product with excellent gradation at reduced
horse power with low maintenance cost.
25
Impact Crusher (Impactor)
26
Vibrating Screen for Coal
Screening is an important operation in
mineral dressing for the preparation of
the feed material to the next process.
29
Line diagram of Bxt stock pile for H Mill Secondary crushing
BC-1002
Hammer Mill
Ball Mill 8 # 7 Reclaim # 4 30
Capacity 20,000 Ton
There are Four Hammer Mill circuits :-
31
#1 #2 #3 #4 #5 #6 #7
Capacity 100 70 110 110 150 150 110
(Running)
TPH
Motor H.P. 150 150 180 150 270 270 150
No. of 27 78 45 27 80 80 21
Hammer
s
No. of 15-17 12- 13 15- 64 64 36
Cage 14 17
Bars
Screen Vibra Fix Vibr Vibr Vibr Vibr Vibr
Type ting ed ating ating ating ating ating
Day Bin 470 610 1200 1200 470 - -
capacity
Tons
Hammer 5 5 14 5 16 16 5
Weight(Kgs
.)
32
Equipments in Hammer Mill
• Reclaim & Emergency feeder
• Hammer Mill Feed Conveyor
• Magnet & Metal detector on Conveyor
• Vibrating Screen
• Hammer Mills
• Hammer Mill discharge Conveyor
• Sump Pumps in Tunnel
• Dust Collector (Bag Filters)
• Weight-o-meter on Hammer mills
Discharge Conveyor
• Air Blasters
33
Hammer mill
Hammers are mounted
on rotating shaft that
swing on the ends of the
cross .
Material fed through
hopper gets impacted
that gets shredded &
expelled through screens
in the drum of a selected
size.
Material finally gets
crushed to 0.5 inch size.
34