33rd Weekly PLN PANGKALAN SUSU

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 15

PLN PANGKALAN SUSU

ADMINISTRATION BUILDING OF COAL


FIRED STEAM POWER PLANT UNIT 3
AND 4 PANGKALAN SUSU
WEEKLY PROGRESS OF ADMINISTRATION
BUILDING PLTU UNIT 3 AND 4

33rd WEEK
Physical Progress of 32nd Week Works Physical Progress of 33rd Week Works
Nov 08 – Nov 14, 2019 Nov 15 – Nov 21, 2019

Total Progress Plan Total Realization Progress


 Preparatory Work 6,006 %
 Preparatory Work 3,850 %
 Foundation Work 18,724 %
 A Building Work 20,993 %  Foundation Work 18,724 %
 B Building Work 23,153 %  A Building Work 2,979 %
 C Building Work 18,149 %
 B Building Work 3,889 %
 Sky Cross Work 8,061 %
 Other Works 0%  C Building Work 3,574 %
Total 100%  Sky Cross Work 3,268 %
 Other Works 0%
 Preparatory Work 3,850 %  Total Realization Progress 36,284%
 Foundation Work 18,724 %
 A Building Work 2,826 %
 B Building Work 3,614 %
 C Building Work 3,295%
 Sky Cross Work 3,127 %
 Other Works 0%
 Total Realization Progress 35,434 %
Progress Resume of Thirty third (33rd) Week
Weekly Plan Realization

 Column Work Building A 0,150 % 0%


 Column Work Building B 0,110% 0,275%
 Column Work Building C 0,110% 0,279%
 Column Work Sky Cross 0,120% 0,141%
Total Weekly Progress Realization 0,490% 0,695%
BREAK DOWN WEEKLY PLANING ADMINISTRATION BUILDING OF
CFSPP PANGKALAN SUSU UNIT 3&4 (2X200 MW)

Percentage Percentage
DESCRIPTION WORK
(%) TOTAL PLAN (%) TOTAL ACTUAL
A. BUILDING A WORK
1 . STRUCTURAL WORK 10,251% 0,151% 0%
f Column Work 1,062% 0,151%
-Form Work (Plywood) 2 times usage 0,36% 0,071%
-Rebar Work 0,48% 0,080% 0,153%
B. BUILDING B WORK -
1 . STRUCTURAL WORK 10,263% 0,530% 0,275%
3 Beam Work 3,528% 0,000%
4 Column Work 1,575% 0,108%
-Rebar Work 0,648% 0,108% 0,108%
-Cast Concrete f'c 25 Mpa (K.300) 0,425% -
-Form Work (Plywood) 1,475% 0,211% 0,167%
-Rebar Work 0,745%
-Cast Concrete f'c 25 Mpa (K.300) 0,634% 0,211%
C . BUILDING C WORK
1 . STRUCTURAL WORK 9,496% 0,530% 0,279%
3 Beam Work 3,528% 0,000%
4 Column Work 1,575% 0,108% 0,108%
-Form Work (Plywood) 2 times usage 0,502%
-Rebar Work 0,648% 0,108% 0,108%
-Cast Concrete f'c 25 Mpa (K.300) 0,425%
-Form Work (Plywood) 1,475% 0,211%
-Rebar Work 0,745% - 0,060%
-Cast Concrete f'c 25 Mpa (K.300) 0,634% 0,211%
D . SKY CROSS WORK 7,972% 0,123% 0,141%
Beam Cast Work 4,204% 0,000% 0,018%
Column Cast Work 0,479% 0,123%
-Form Work (Plywood) 2 times usage 0,15% 0,050% 0,050%
-Rebar Work 0,22% 0,072% 0,072%
-Cast Concrete f'c 25 Mpa (K.300) 0,11%
Floor Slab Cast Work 2,141% 0,000%
Progress Resume of Thirty third (33rd) Week

 Total of 33rd Week Realization Progress 36,255%


 Total of 33rd Week Progress Plan 94,120%
Total Progress Deviation -57,865%

 33rd Weekly Progress Plan 0,490%


 33rd Weekly Progress Realization 0,695%
Weekly Progress Deviation +0,205%
Progress of Thirty third (33rd) Week
Time Schedule Progress Description

Working result on thirty second week (33rd) of PLN Administration Building Steam

Coal Power Plant Unit 3 & 4 is PT. Horas Bangun Persada able to do those works as

weekly time schedule planned. Cumulative total work until the end of thirty third

week is 36,284 %.
34th Week Working Plan

 Pouring Concrete of Column Building C and Sky Cross Area

 Finish Installation of Rebar and Formwork Slab Building A


Work Documentation

Installation of Rebar Beam


Installation of Formwork Wall
Rebar Column Erection
Installation of Rebar Column K3
Installation of Rebar Beam Building A area
THANK YOU