33rd WEEK
Physical Progress of 32nd Week Works Physical Progress of 33rd Week Works
Nov 08 – Nov 14, 2019 Nov 15 – Nov 21, 2019
Percentage Percentage
DESCRIPTION WORK
(%) TOTAL PLAN (%) TOTAL ACTUAL
A. BUILDING A WORK
1 . STRUCTURAL WORK 10,251% 0,151% 0%
f Column Work 1,062% 0,151%
-Form Work (Plywood) 2 times usage 0,36% 0,071%
-Rebar Work 0,48% 0,080% 0,153%
B. BUILDING B WORK -
1 . STRUCTURAL WORK 10,263% 0,530% 0,275%
3 Beam Work 3,528% 0,000%
4 Column Work 1,575% 0,108%
-Rebar Work 0,648% 0,108% 0,108%
-Cast Concrete f'c 25 Mpa (K.300) 0,425% -
-Form Work (Plywood) 1,475% 0,211% 0,167%
-Rebar Work 0,745%
-Cast Concrete f'c 25 Mpa (K.300) 0,634% 0,211%
C . BUILDING C WORK
1 . STRUCTURAL WORK 9,496% 0,530% 0,279%
3 Beam Work 3,528% 0,000%
4 Column Work 1,575% 0,108% 0,108%
-Form Work (Plywood) 2 times usage 0,502%
-Rebar Work 0,648% 0,108% 0,108%
-Cast Concrete f'c 25 Mpa (K.300) 0,425%
-Form Work (Plywood) 1,475% 0,211%
-Rebar Work 0,745% - 0,060%
-Cast Concrete f'c 25 Mpa (K.300) 0,634% 0,211%
D . SKY CROSS WORK 7,972% 0,123% 0,141%
Beam Cast Work 4,204% 0,000% 0,018%
Column Cast Work 0,479% 0,123%
-Form Work (Plywood) 2 times usage 0,15% 0,050% 0,050%
-Rebar Work 0,22% 0,072% 0,072%
-Cast Concrete f'c 25 Mpa (K.300) 0,11%
Floor Slab Cast Work 2,141% 0,000%
Progress Resume of Thirty third (33rd) Week
Working result on thirty second week (33rd) of PLN Administration Building Steam
Coal Power Plant Unit 3 & 4 is PT. Horas Bangun Persada able to do those works as
weekly time schedule planned. Cumulative total work until the end of thirty third
week is 36,284 %.
34th Week Working Plan