Proposal
Proposal
Proposal
Proposed by:
Judiel Bautista
John Kyle Bando
Arlene Marasigan
Nielmar Dioquino
Samuel Sarmiento
Adriel Hayag
Jim Patrick Geneveo
Jed Bullos
Objectives
• enable people to watch live
performances on the stage.
• Finesse
Efficiency
Convenience
DESCRIPTION OF THE PROJECT
Perspective view
EXTERIOR
First
Floor
Plan
Second
Floor
Plan
Perspective view
INTERIOR
Perspective view
INTERIOR
Arrangement of seats
Arrangement of seats
FIRST FLOOR SEAT PLAN
Seats Per Section
Row Formula Seats
F E U
1 𝐴1 = 28 + 1 − 1 1 28 seats 12 4 12
20 𝐴20 = 28 + 20 − 1 1 47 seats 12 23 12
Arrangement of seats
𝑛
𝑆𝑛 = [2𝑎1 + (𝑛 − 1)𝑑]
2
20
𝑆20 = [2(28) + (20 − 1)1]
2
𝑆20 = 10 (56 + 19)
𝑆20 = 750
The total number of chairs in our first floor
is 750 seats.
Arrangement of seats
SECOND FLOOR SEAT PLAN
Seats Per
Row Formula Seats Section
S C
1 𝐴1 = 15 + 1 − 1 1 30 seats 15 15
7 𝐴7 = 15 + 7 − 1 1 42 seats 21 21
Arrangement of seats
𝑛
𝑆𝑛 = [2𝑎1 + (𝑛 − 1)𝑑]
2
7
𝑆7 = [2(15) + (7 − 1)1]
2
𝑆7 = 3.5(30 + 6)
𝑆7 = 126
Multiplied by 2 because of the 2 sections
of chairs, the total number of chairs in our
second floor is 252 seats.
BUDGET SUMMARY
• MATERIALS - STRUCTURE
Description Quantity Unit Amount per Total
unit
Cement 9,260 Per sack Php 245 Php 2,268,700
(0.027 cubic
m)
Sand 18,520 Per sack Php 350 Php 6,482,000
(0.027 cubic
m)
Gravel 27,780 Per sack Php 350 Php 9,723,000
(0.027 cubic
m)
Deformed Bar 4000 Per piece Php 371 Php 1,484,000
(steel) (16mmx6m)
Wood 500 Per piece Php 258 Php 129,000
(8x4ft)
Glass 1,500 Per piece Php 200 Php 300,000
Nails 20 Per kilogram Php 43 Php 860
• MATERIALS - STRUCTURE
Description Quantity Unit Amount Total
per unit
Paints 600 Per Php 2,000 Php 1,200,000
bucket
(16L)
Standing 26,383 Per Php 450 Php
seam metal piece 11,872,350
Hollow 22,546 Per Php 16 Php 360,736
Blocks piece
(6”)
Php
TOTAL 33,820,646
• MATERIALS - INTERIOR
Description Quantity Unit Amount per Total
unit
Php
TOTAL
5,923,800
• MATERIALS - RESTROOMS
Description Quantity Unit Amount per Total
unit
Php
TOTAL 218,100
• MATERIALS - ELECTRICAL
Description Quantity Unit Amount per unit Total
TOTAL Php
312,198.75
• LABOR
Description Quantity Salary Per Overall Salary
Week (Each)
Engineer 4 Php 7,200 Php 2,073,600
Architect 1 Php 7,920 Php 570,240
Electrician 6 Php 9,000 Php 3,888,000
Plumber 5 Php 3,824.64 Php 1,376,870.4
Contractor 2 Php 10,527.53 Php 1,515,964.32
Foreman 3 Php 4,247.28 Php 917,412.48
Construction 50 Php 3,000 Php 10,800,000
Worker
TOTAL Php
21,142,087.2
Preparation for Land Php 10 000 000
SUMMARY OF BUDGET
Preparation for Land Php 10 000 000
Materials (Structure) Php 33,820,646
Materials (Interior) Php 5,923,800