High wheel space Temperature issues
• Contact Information
http://frame-6-users-group.org
High wheel space Temperature issues
Saudi Aramco is one of the largest companies in the
world.
Integrated energy and chemicals company.
The Company is engaged in:
Exploration
production
Refining
Distribution
Shipping
Marketing
l
http://frame-6-users-group.org
High wheel space Temperature issues
Abqaiq Plants is the largest oil production facility in
the world.
Comprises in three major plants:
Oil
NGL
Utility
http://frame-6-users-group.org
High wheel space Temperature issues
• Abqaiq Plants:
Power Plant Details:
Three GE units of
Frame- 6581B
Date Commissioned: 2003
Duty: Power generation (Combined Cycle)
Fuel: Dry Gas
http://frame-6-users-group.org
High wheel space Temperature issues
• Frame 6B units at Abqaiq Plants
http://frame-6-users-group.org
High wheel space Temperature issues
Started the machine after completing the MI and noticed the following:
TTWS2AO-2 above alarm level
TTWS3FO-2 above alarm levels
http://frame-6-users-group.org
High wheel space Temperature issues
• WS TCs locations:
http://frame-6-users-group.org
High wheel space Temperature issues
TP
http://frame-6-users-group.org
High wheel space Temperature issues
http://frame-6-users-group.org
High wheel space Temperature issues
Findings:
• As found thermocouple insertion reading diaphragm temp.
Wrong insertion
http://frame-6-users-group.org
High wheel space Temperature issues
• WS Thermocouple cap before machining
http://frame-6-users-group.org
High wheel space Temperature issues
Corrective Action:
The insertion length as per the casing stamping.
Correct Insertion
http://frame-6-users-group.org
High wheel space Temperature issues
Corrective Action:
• WS thermocouple guide tube cap:
After Machining: Removed the Red color for machined area because this
step inside 3FO-1/2 & 2AO-1/2 right angle prevents TCs from reaching
slight drilling – TCs then installed the end of the cap
smoothly to the correct insertion
length.
High wheel space Temperature issues
Machine Parameters After Modification
• WS TC readings after the correction and at base load:
High wheel space Temperature issues
Lesson Learned
High wheel space temperature is a common problem on
Frame 6B.
During MI and before installing the turbine casing,
ensure the WS TCs are inserted correctly.
Borescope WSTCs guide tubes.
Apply heat on the TC caps and verify with Mark 6.
Great team work leads to solving a chronic issues.
http://frame-6-users-group.org
Thank you