Offload Preparation Party & Debark Team
Offload Preparation Party & Debark Team
SG 1 MPF-11 2
Terminal Learning Objective
SG 1 MPF-11 3
Enabling Learning
Objectives
With the aid of references:
• State the mission of the OPP.
• Derive the organization of the OPP.
• Describe the responsibilities of the OPP.
• Describe the command relationships of
the OPP.
SG 1 4
MPF-11
References
• NTTP 3-02.1M / MCWP 3-31.5, Ship-To-
Shore Movement.
• MCWP 3-32/NTTP 3-02.3, Maritime
Prepositioning Force (MPF) Operations.
• MCWP 3-31.7, Seabasing.
• TM 4790-14/2A, Logistic Support for Maritime
Prepositioning Force (MPF) Program
Maintenance and Material Management.
SG 1 MPF-11 5
Acronyms
• AAA - Arrival and Assembly
• COR - Contracting Officer’s Representative
• CMT - Contract Maintenance Team
• CNSE- Commander Naval Support Element
• DCO - Debark Control Officer
• MHE - Material Handling Equipment
SG 1 MPF-11 6
Overview
• MISSION
• ORGANIZATION
• RESPONSIBILITIES
• COMMAND RELATIONSHIPS
• DISESTABLISHMENT
• PLANNING CONSIDERATIONS
• SUMMARY
SG 1-2 MPF-11 8
Mission
• Prepares equipment on MPS for debarkation
at the Arrival and Assembly Area (AAA)
SG 2 MPF-11 9
Organization
• Temporary task organization of MAGTF
and NSE personnel.
SG 2 MPF-11 10
Organization
OPP OIC
OPP
MOLT
AOIC
OPP det OPP det OPP det OPP det OPP det
OIC OIC OIC OIC OIC
NSE MAGTF NSE MAGTF NSE MAGTF NSE MAGTF NSE MAGTF
SG 2 MPF-11 11
Notional OPP
OPP TM OBREGON OPP TM BOBO
MEB OFF ENL NSE OFF ENL MEB OFF ENL NSE OFF ENL
CE 0 0 BMU 0 3 CE 0 0 BMU 0 1
GCE 0 33 ACU 1 5 GCE 0 37 ACU 0 4
ACE 0 11 ACB 0 5 ACE 0 12 ACB 1 3
LCE 3 36 NMCB 0 0 LCE 3 36 NMCB 0 0
NCHB 1 4 NCHB 1 4
SUB 3 80 SUB 2 17 SUB 3 85 SUB 2 12
12
SG 2
Attachment 11-A
MPF-11
Offload Preparation Party
• Consists of OPP
Officer in Charge
(OIC) and his staff
– OIC designated by
the CNSE
• Overall responsible
for the equipment
preparation efforts
for the MPSRON
SG 2 MPF-11 13
Offload Preparation
Party
• AOIC
– Senior Marine
– Oversees work
– Coordinates support
– Prioritizes efforts as
necessary
– Realigns personnel
as necessary
SG 2 MPF-11 14
OPP Detachment
• Navy or Marine OIC.
• Two elements: NSE &
MAGTF
– NSE
• Lighterage and
Equipment operators
(BMU, ACB, ACU)
• Crane operators &
Cargo handlers (NCHB)
SG 2 MPF-11 15
OPP Detachment
– MAGTF
• Maintenance and
embark personnel
• Equipment operators
SG 2 MPF-11 16
OPP Detachment
• OPP Det OIC:
– Will be the Debark Control Officer (DCO)
for his MPS upon arrival to the AAA.
– Oversees equipment preparation for his
MPS.
SG 2 MPF-11 17
Responsibilities
• Detachment tasks include:
– Preparing ship’s offload systems
• Cranes and winches
• Lighterage
• Slings, container handlers, etc
• Fuel and water discharge systems
SG 2-3 MPF-11 18
Responsibilities
• Tasks include (cont)
– Depreservation and preparation of
embarked equipment
• Normal “Before Operating Services”
• Fueling
• Identification of defects
• Limited organizational maintenance
SG 2-3 MPF-11 19
Priorities for equipment
preparation
• Ships cargo handling systems
MPF-11 21
Command Relationships
• OPP OIC and COMPSRON
– OPP OIC reports to COMPSRON to obtain
specific direction concerning shipboard
activities.
SG 3 MPF-11 24
CMT
• Maintenance responsibilities are provided in
detail in the statement of work
• Statement of Work
– Cyclic inventories and stock surveillance
– Preventative and corrective maintenance
– Exercise and reprocess of all principle end items
IAW specific instructions
– Modification as directed
SG 3 MPF-11 25
CMT
• Statement of work (cont)
– Maintenance of technical libraries
• Provide access to
– Pre-expended bins
– Petroleum, oils and lubricants
(POL)
– Special tools
– Maintenance publications
SG 3 MPF-11 27
Command Relationships
• OPP OIC and Contracting Officer’s
Representative (COR)
– MAGTF commander’s offload priorities are
conveyed to the COR
– Must cooperate and coordinate
– Neither has directive authority over the
other
SG 3 MPF-11 28
Disestablishment
• Occurs upon arrival at
the AAA and/or
completion of off-load
preparations
• OPP will remain aboard
as the nucleus of the
debark teams formed
from MAGTF and NSE
personnel arriving in the
FIE
SG 4 MPF-11 29
Disestablishment
• CNSE and the MAGTF
Landing Force Support
Party (LFSP) will provide
additional personnel to
conduct offload
operations
SG 4 MPF-11 31
MPF-11 33
MPF-11 34
Legacy Causeway MPF-11 35
Planning Considerations
• Tasks to accomplish
– Equipment preparation
– Urgent modification
instructions
– Equipment operators’
licenses
• Billeting limitations
– Female OPP members
• Where and how the
OPP joins the MPSRON
SG 4 MPF-11 36
Planning Considerations
• OPP composition
– Specified in SOP
– Should include cooks, corpsman, etc
– Other units assigned
• MPS internal security
• Naval Embarked Advisory Teams (NEAT)
• Technical Assistance and Advisory Team
(TAAT)
SG 4 MPF-11 37
Review
• What is the mission / purpose of the
OPP and when do they arrive?
SG 13-1 MPF-11 39
Summary
• Mission
• Organization
• Responsibilities
• Command Relationships
• COR
• Disestablishment
• Planning Consideration