Professional Documents
Culture Documents
Chapter 1 Concrete
Chapter 1 Concrete
Chapter 1 Concrete
CONSTRUCTION
ESTIMATE
CONCRETE
Chapter 1
Plain and Reinforced Concrete
Plain Concrete – an artificial stone as a
result of mixing cement, fine aggregates,
coarse aggregates and water.
Illustration 1-3
A national highway project as shown specify 25
centimeters thick concrete. Find the number of bags cement,
sand and gravel required using class “A” mixture.
Estimating Concrete Slab By The
Area Method
Table 1-3 Quantity of Cement, Sand and Gravel for Slab
and Walls per Square Meter Area
Mixture Class
Slab
Sand Gravel
Thickne 40 kg. Cement 50 kg. Cement
cu.m. cu.m.
ss cm.
A B C A B C
5.0 .450 .375 .300 .350 .300 .250 .0250 .050
7.5 .675 .563 .450 .525 .450 .375 .0375 .075
10.0 .900 .750 .600 .700 .600 .500 .0500 .100
12.5 1.125 .938 .750 .875 .750 .625 .0630 .125
15.0 1.350 1.125 .900 1.050 .900 .750 .0750 .150
17.5 1.575 1.313 1.050 1.225 1.050 .875 .0880 .175
20.0 1.800 1.500 1.200 1.400 1.200 1.000 .1000 .200
22.5 2.030 1.688 1.350 1.575 1.350 1.125 .1125 .225
25.0 2.250 1.875 1.500 1.750 1.500 1.250 .1250 .250
27.5 2.475 2.063 1.650 1.925 1.650 1.375 .1380 .275
30.0 2.700 2.250 1.800 2.100 1.800 1.500 .1500 .300
Estimating Concrete Slab By The
Area Method
Illustration 1-4
Solve problems of illustration 1-1 and 1-2 by the Area
Method.
Illustration 1-5
A concrete wall, 3 inches thick with general
dimensions of 3.00 meters high by 7.00 meters long specify
class “B” mixture. Find the number of 40 kg. cement, sand
and gravel required.
Square Concrete Column
Estimating the quantity of materials for
concrete post or column can also be done in two
simple ways:
1. By Volume Method
2. By Linear Meter Method
Illustration 1-6
A reinforced concrete square column in 5.00
meters long with a cross sectional dimensions of
16 by 16 inches. Determine the quantity of
cement, sand and gravel using class A concrete.
Square Concrete Column
Illustration 1-7
A concrete column is 7.00 meters high with a
cross sectional dimensions of 20 by 20 inches.
Determine the quantity of cement, sand and gravel
content of the column if there are 8 columns in the
row using class “A” concrete.
Estimating Square Concrete
Column by Linear Meter Method
Table 1-4 Quantity of Cement, Sand and Gravel for Post Beam and
Girder per Meter Length
Mixture Class
Size Sand Gravel
40 kg. Cement 50 kg. Cement
cm. cu.m. cu.m.
A B A B
15 x 20 .270 .225 .210 .180 .015 .030
15 x 25 .338 .281 .263 .225 .019 .038
15 x 30 .405 .338 .315 .270 .023 .045
15 x 35 .473 .394 .369 .315 .026 .053
15 x 40 .540 .450 .420 .360 .030 .060
Plastering
If the post will be plastered by 12 mm
thick with class “A” mortar mixture solution,
determine the materials required.
Rectangular Beam and Girder
A beam is defined as a strong
horizontal piece of reinforced concrete for
spanning and supporting weights. On the
other hand, a beam that is carrying or
supporting another beam is called girder.
Similarly, estimating the materials for these
types of structures is either by the volume
or the linear meter method.
Rectangular Beam and Girder
Illustration 1-10
From the figure, using class “A” concrete, list down
the materials required.
Circular Column
Estimating the materials for circular
column is typically the same as the volume
method for the square and rectangular
columns with the aid of Table 1-2. However,
Table 1-5 was also prepared for circular
column problems to avail of the linear
meter method of estimating.
Circular Column
Table 1-5 Quantity of Cement, Sand and Gravel per Meter Length of
Circular Column
MIXTURE CLASS
Column
Sand Gravel
Diameter 40 kg cement 50 kg cement
cu.m. cu.m.
cm
A B A B
25 .442 .368 .344 .295 .025 .050
30 .636 .530 .495 .424 .035 .070
35 .866 .722 .673 .577 .048 .096
40 1.131 .942 .880 .754 .063 .126
50 1.767 1.473 1.374 1.178 .098 .196
55 2.138 1.782 1.663 1.425 .119 .238
60 2.545 2.121 1.979 1.696 .141 .282
65 2.986 2.488 2.323 1.991 .166 .332
70 3.464 2.886 2.694 2.309 .192 .384
75 3.976 3.313 3.093 2.651 .221 .442
80 4.524 3.770 3.519 3.016 .251 .502
85 5.107 4.256 3.972 3.405 .284 .568
90 5.726 4.771 4.453 3.817 .318 .636
100 7.069 5.890 5.498 4.712 .393 .786
Circular Column
Illustration 1-11
A circular concrete column has a
diameter of 60 cm by 6.00 meters high.
Find the concrete materials required if
there are 5 columns of the same size in a
row.
Concrete Pipe
Concrete pipe is much in
demand for small and medium
drainage construction. The use of
concrete pipe as drainage
structure materially save cost of
forms, time and labor costs as
well.
Concrete Pipe
Procedures in Estimating the Materials
for Concrete Pipe
1. Find the net volume of the concrete
pipe. That is, by subtracting the volume
occupied by the hole from the gross
volume of the pipe.
2. Knowing the net volume of the
concrete, refer to Table 1-2, under 40
kg cement and class of mixture
specified, multiply by the net volume
found for cement, sand and gravel or
3. Use Table 1-6 for final result
Concrete Pipe
Table 1-6 Quantity of Cement, Sand and Gravel per Concrete Pipe.
CEMENT IN BAGS
Diameter in Centimeter Sand Gravel
Class of Mixture
D d A B cu.m. cu.m.
21 15 .152 .127 .009 .018
26 20 .195 .163 .011 .022
33 25 .328 .274 .018 .037
39 30 .436 .363 .025 .050
50 40 .635 .530 .036 .072
60 50 .779 .650 .044 .088
78 60 1.755 1.463 .098 .196
90 70 2.260 1.883 .126 .252
100 80 2.538 2.115 .141 .282
110 90 2.826 2.355 .157 .314
120 100 3.110 2.595 .173 .346
144 120 4.482 3.735 .249 .498