Professional Documents
Culture Documents
Capital Budgeting Under Risk and Uncertainty
Capital Budgeting Under Risk and Uncertainty
Capital Budgeting Under Risk and Uncertainty
NPV of NCF
PV of Variable Cost 100%
PV of variable cost
Yrs Variable Cost DCF@10% PV of Variable Contribution
1 80,000 0.909 72,720
2 120,000 0.826 99,120
3 60,000 0.751 45,060
216,900
₱8,450.00
100%
₱216,000
3.9%
PV of variable cost
Yrs Variable Cost DCF@10% PV of Variable
Contribution
1 80,000 0.909 72,720
2 120,000 0.826 99,120
3 60,000 0.751 45,060
216,900
₱ 8,450
₱108,450 100%
= 7.79%
The sales volume of the product should
not be reduced by more than 7.79% every
year for the project to be worthwhile.
(d) Initial outlay:
For the project to be viable, the initial
outlay of the project should not increase
by more than 8.45%.
Expected NPV
This is based on the principle of expected
value. Once probabilities are assigned to
future outcomes of net cash flow for a
period, the expected value would be
calculated and discounted. The expected
NPV arithmetically takes account of the
expected variability of two or more possible
outcomes by averaging possible outcomes
weighted by their respective possibilities.
Example:
For example, a project runs for three years with
the following distribution of returns in each
year, viz;
Year 1 Year 2 Year 3
Return Probability
The project will cost the company P42
million to establish. Calculate the
expected NPV if the discount rate is 10%.
Standard Deviation and Variance
Standard deviation is an absolute measure
of risk. It measure the dispersion of the
cashflow and spread about the mean
value. The Standard Deviation NPV