Time Co ST Trade Off Cras Hing
Time Co ST Trade Off Cras Hing
d eo ff c
co st t ra
T im e
Prepared By:
Group 9
Divi Agarwal – 191084
Mahak Khemka – 191094
Sahil Sethi – 191110
Shilpi Jain – 191112
Shrey Gupta – 191114
Basic Concepts:
Each activity is allocated some resources.
- Normal Time and Normal Cost.
2
Crashing increases the direct costs and
decreases the indirect costs.
The goal in evaluating time-cost trade offs is to
identify activities that will reduce the sum of
direct costs and indirect costs.
3
Assumptions:
4
Activity Normal Normal cost Crash Time Crash Cost Immediate
Time (In (In Rs.) (In Weeks) (In Rs.) Predecessors
Weeks)
A 2 50 1 70 -
B 4 80 2 160 A
C 8 70 4 110 A
D 6 60 5 80 A
E 7 100 6 130 B
F 4 40 3 100 D
G 5 100 4 150 E,F
5
Network diagram
E7
B4
A2 D6 F4 G5
START END
i ty
C8 ctiv
y a
mm
Du
6
Critical Path
Path Total Time
A-D-F-G 2+6+4+5 = 17
A-C 2+8 = 10
7
Critical Path
E7
B4
A2 D6 F4 G5
START END
i ty
C8 ctiv
y a
mm
Du
8
So, minimum project completion time is 18
Weeks.
Critical Path is A-B-E-G
And
Normal Cost incurred is Rs. 500.
9
Minimum Total Direct Cost
Activity Normal Normal Crash Crash Available Crash Cost
Time (In cost (In Time Cost (In Days per day
Weeks) Rs.) (In Weeks) Rs.)
A 2 50 1 70 1 20
B 4 80 2 160 2 40
E 7 100 6 130 1 30
G 5 100 4 150 1 50
Total 18 500
17 weeks :
Activity Crash Cost (Per Available Weeks Minimum
week) crash cost
A 20 1
B 40 2
E 30 1
G 50 1
11
After crashing activity ‘A’ by 1 day
Paths Length
A-B-E-G 17
A-D-F-G 16
A-C 9
12
16 weeks
Activity Crash Cost (Per Available Weeks
week) Minimum
A No reduction - crash cost
possible
B 40 2
E 30 1
G 50 1
A-D-F-G A No further
reduction
possible
D 20 1
F 60 1
G 50 1
14
15 weeks:
The option of shortening the least expensive
activity on each path would cost Rs. 40 for ‘B’ and
Rs. 20 for ‘D’ , totaling to Rs. 60.
A-B-E-G 15
A-D-F-G 15
A-C 9
16
Path Activity Crash Cost (Per week) Available
Weeks
A-B-E-G A No further reduction -
possible
B 40 2
E No further reduction -
possible
G No further reduction -
possible
Minimum
crash cost
D 20 1
F 60 1
G No further reduction -
possible
17
14 weeks :
The option of shortening the least expensive activity on
each path would cost Rs. 40 for ‘B’ and Rs. 20 for ‘D’ ,
totaling to Rs. 60.
So, we will crash the activity ‘B’ and ‘D’.
Minimum total direct cost = 600 + 60
= 660
Paths Length
A-B-E-G 14
A-D-F-G 14
A-C 9
18
Path Activity Crash Cost (Per week) Available
Weeks
A-B-E-G A No further reduction -
possible
B 40 1
E No further reduction -
possible
G No further reduction -
possible
19
13 weeks :
The option of shortening the least expensive activity on
each path would cost Rs. 40 for ‘B’ and Rs. 60 for ‘F’ ,
totaling to Rs. 100.
So, we will crash the activity ‘B’ and ‘F’.
Minimum total direct cost = 600 + 100
= 700
Paths Length
A-B-E-G 13
A-D-F-G 13
A-C 9
20
INDIRECT COST
Assumptions:
21
18 weeks
Indirect Cost : 400
Activity Normal Normal Crash Crash Available Crash Cost
Time (In cost (In Time Cost (In Days per day
Weeks) Rs.) (In Weeks) Rs.)
A 2 50 1 70 1 20
B 4 80 2 160 2 40
E 7 100 6 130 1 30
G 5 100 4 150 1 50
Total 18 500
Paths Length
Minimum project cost
A-B-E-G 18
incurred is 500 + 400 = A-D-F-G 17
900. A-C 10
22
17 weeks
Indirect Cost : 350
Activity Crash Cost (Per Available Weeks Minimum
week) crash cost
A 20 1
B 40 2
E 30 1
G 50 1
Since 20 does not exceed the indirect project cost of 350, so we can crash
activity ‘A’.
Paths Length
Minimum direct cost = 500 + 20
= 520 A-B-E-G 17
Total project cost = 520 + 350 A-D-F-G 17
= 870.
A-C 9
23
16 weeks
Indirect Cost : 300
Activity Crash Cost (Per Available Weeks
week)
A No reduction - Minimum
possible crash cost
B 40 2
E 30 1
G 50 1
A-D-F-G A No further
reduction
possible
D 20 1
F 60 1
G 50 1
25
15 weeks:
Indirect Cost : 250.
The option of shortening the least expensive activity on each
path would cost Rs. 40 for ‘B’ and Rs. 20 for ‘D’ , totaling to Rs.
60.
And total crash cost = 60 + 50 =110.
26
Minimum direct cost = 500 + 100 = 600
Total Project Cost = 600 + 250 = 850.
Paths Length
A-B-E-G 15
A-D-F-G 15
A-C 9
27
Path Activity Crash Cost (Per week) Available
Weeks
A-B-E-G A No further reduction -
possible
B 40 2
E No further reduction -
possible
G No further reduction -
possible
Minimum
crash cost
D 20 1
F 60 1
G No further reduction -
possible
28
14 weeks
Indirect Cost : 200
The option of shortening the least expensive activity on each path
would cost Rs. 40 for ‘B’ and Rs. 20 for ‘D’ , totaling to Rs. 60.
Since, total crashing cost till 14th week is Rs 160 which is less than
Rs 200 of indirect cost
So, we will crash the activity ‘B’ and ‘D’.
Minimum total direct cost = 500 + 160
= 660
Paths Length
A-C 9
29
Path Activity Crash Cost (Per week) Available
Weeks
A-B-E-G A No further reduction -
possible
B 40 1
E No further reduction -
possible
G No further reduction -
possible
30
13 weeks
Indirect Cost : 150
The option of shortening the least expensive activity on
each path would cost Rs. 40 for ‘B’ and Rs. 60 for ‘F’ ,
totaling to Rs. 100.
But since total crashing cost till 13th week is Rs 260
which is greater then the total indirect cost of Rs 150
So, we will cannot crash the project further.
31