Professional Documents
Culture Documents
Chapter 17 Lecture Slides
Chapter 17 Lecture Slides
17-1
Learning Objectives
Nature, examples, triple constraints of projects
Project life cycle
Matrix organizations
Work breakdown structures
Gantt chart
Critical path method (CPM)
Project evaluation review method (PERT)
Crashing analysis
Project risk management
Project management software
17-2
Projects
Projects:
Unique
One-time effort to accomplish a specific set of objectives in
a limited time frame
Start and end dates
Reward and penalty
Examples:
The Olympic Games
Producing a movie
Software development
Product development
ERP implementation
MBA Dissertation
17-3
The Triple Constraint
of Project Management
Successful project
management means
meeting all three goals
(scope, time, and cost) –
thus satisfying the
project’s sponsor and
customer(s)!
Quality is fourth
constraint!
17-4
The Nature of Projects
Projects go through a series of stages– a life
cycle
Projects bring together people with a
diversity of knowledge and skills, most of
whom remain associated with the project for
less than its full life
Use their own organizational structure called
Matrix organization
17-5
Project Life Cycle
17-6
Matrix Organization
HR,
Training,
Legal,
Construction …
17-7
Project Management
Decisions
Project success depends upon making key
managerial decisions over a sequence of
steps:
Deciding which projects to implement
Selecting the project manager
Selecting the project team
Planning the project
Managing and controlling project resources
Deciding if and when a project should be
terminated
17-8
Project Management Tools
Work Breakdown Structures (WBS)
Gantt Chart
Critical Path Method (CPM)
Project/program Evaluation Review
Technique (PERT)
Crashing Analysis
Risk Analysis
17-9
Work Breakdown Structure
(WBS)
WBS
A hierarchical listing of what must be done
during a project
Establishes a logical framework for identifying the
required activities for the project
1. Identify the major elements of the project
2. Identify the major supporting activities for each of the major
elements
3. Break down each major supporting activity into a list of the
activities that will be needed to accomplish it
17-10
Example Work Breakdown
Structure
17-11
Example Work Breakdown
Structure
17-11 a
Gantt Chart
17-12
CPM and PERT
CPM (critical path method) and PERT (program evaluation
and review technique) are two techniques used to manage
large-scale projects
CPM and PERT help Project Managers:
1. A graphical display of project activities
2. An estimate of how long the project will take
3. An indication of which activities are most critical to timely project
completion
4. An indication of how long any activity can be delayed without
delaying the project
CPM is deterministic and PERT probabilistic
17-13
Example
Activity Time Preceded By
A 10 --
B 7 --
C 5 A
D 13 A
E 4 B,C
F 12 D
G 14 E
17-14
Network Diagram
2 4
A(10) D(13) F(12)
1 C(5) 6
B(7)
E(4) G(14)
3 5
A-C-E-G 33 2
B-E-G 25 10
17-15
Early Start and Finish Times
17-16
Latest Start and Finish Times
17-17
Activity Slack Time
Activity Slack
17-19
Activity Slack Times
Activity ES EF LS LF Slack
A 0 10 0 10 0
B 0 7 10 17 10
C 10 15 12 17 5
D 10 23 10 23 0
E 15 19 17 21 2
F 23 35 23 35 0
G 19 33 21 35 2
17-20
PERT: Project Planning When
Activity Times are Uncertain
Inputs
optimistic (to), most likely (tm), and pessimistic (tp) time
estimate for each activity
activity precedence relationships
Outputs
graphical representation of project
expected activity and path completion times
variance of activity and path completion times
probability that project completed by specified time
17-21
Expected Activity Time and
Variance of Activity Time
t o 4t m t p
te
6
2
t p to
2
6
17-22
Example
Activity Preceded By to tm tp te 2
A -- 2 6 7 5.50 .694
B -- 5 7 9 7.00 .444
C A 3 5 6 4.83 .250
D A 10 10 10 10.0 0.000
E B,C 3 4 5 4.0 .111
F D 8 12 13 11.5 .913
G E 2 4 8 4.33 1.000
17-23
Network Diagram with Expected
Activity Times and Variances
17-24
Expected Completion Time
and Variance of Path A-D-F
17-25
Path Expected Times and
Variances
Expected Standard
Path Time Variance Deviation
A-D-F 27 1.607 1.27
17-26
Probabilities of Completion
17-27
Probability of Project Being
Completed on or Before Time 25
5.82%
17-29
Project Completion Time
A project is not complete until all project activities are complete
It is risky to only consider the critical path when assessing the
probability of completing a project within a specified time.
To determine the probability of completing the project within a particular time
frame
Calculate the probability that each path in the project will be completed
within the specified time
Multiply these probabilities
The result is the probability that the project will be completed within
the specified time
17-30
Problem 7, Page 819
a. Draw precedence diagram
17-31
Assumption: Independence
Independence
Assumption that path duration times are
independent of each other
Requires that
1. Activity times are independent
2. Each activity is on only one path
The assumption of independence can be considered
to be met if only a few activities in a large project are
on multiple paths
17-32
Time-Cost Trade-Offs
Activity time estimates are made for some given level of
resources
It may be possible to reduce the duration of a project by
injecting additional resources
Motivations:
To avoid late penalties
Monetary incentives
Free resources for use on other projects
17-33
Time-Cost Trade-Offs:
Crashing
Crashing
Shortening activity durations
Typically, involves the use of additional funds to support additional
personnel or more efficient equipment, and the relaxing of some work
specifications
The project duration may be shortened by increasing direct
expenses, thereby realizing savings in indirect project costs
17-34
Crashing Decisions
To make decisions concerning crashing
requires information about:
Regular time and crash time estimates for each
activity
Regular cost and crash cost estimates for each
activity
A list of activities that are on the critical path
Critical path activities are potential candidates for crashing
Crashing non-critical path activities would not have an impact on
overall project duration
17-35
Crashing: Procedure
General procedure:
1. Crash the project one period at a time
2. Crash the least expensive activity that is on the critical path
3. When there are multiple critical paths, find the sum of crashing the
least expensive activity on each critical path
If two or more critical paths share common activities, compare
the least expensive cost of crashing a common activity shared by
critical paths with the sum for the separate critical paths
17-36
Crashing Activities
17-37
Project Risk Management
Risks are an inherent part of project management
Risks relate to occurrence of events that have undesirable
consequences such as
Delays
Increased costs
Inability to meet technical specifications
Good risk management involves
Identifying as many risks as possible
Analyzing and assessing those risks
Working to minimize the probability of their occurrence
Establishing contingency plans and budgets for dealing with any
that do occur
17-40
Project Management Software
such as MSP 2007
Specialized software used to manage projects
Assign resources
Compare project plan versions
Evaluate changes
Track performance
Imposes a methodology and common project management
terminology
Provides a logical planning structure
May enhance communication among team members
Can flag the occurrence of constraint violations
Automatically formats reports
Can generate multiple levels of summary and detail reports
Enables “what if” scenarios
Can generate a variety of chart types
17-38
Reading: Managing Projects the Right
Way: Key Principles for Successful
Projects
17-41
Case: Time Please, pp 825
17-42