Professional Documents
Culture Documents
Project Case Study Group
Project Case Study Group
Project Case Study Group
Total 40
Chapter Four
4 . Data Analysis
The activity of project committee and the concerned sectors
have been analyzed for the purpose of study.
The reason construction delay of road bridge in Sululta
administrative city can be analyzed by collecting data from
many sector such as, from Sululta administrative office ,
finance and economic office , construction office, education
office, health office, water and mining office and road office.
In addition we have interviewed the local elders for our case
study. Finally the case study presents and interpretations of
data collected through questionnaire from employees of Sululta
City Administration. To collect the data for the case study 40
questionnaires were distributed and all were collected from
respondents for the study.
10 respondents were asked by using
interview method. The data was
analyzed by using quantitative and
qualitative methods. That means by
using tables for quantitative data and
narration method for qualitative data
analyzing.
Table 2 profile of respondents
8 21 11
% 72.5 27.5 0 25 52.5 22.5 0 17.5 52.5 30
20 52.5 27.5
As it is shown on the above table1 (72.5%) of the respondents were
males whereas ( 27.5%) of them were females. This shown that the
numbers of males is much more than number of females Worker.
As indicated in table 1 age distribution is one of the demographic
characteristics that show the proportion of people by dividing in to
different sections. From the given table 25% of the total respondents
were within age range of 24-29 years, 52.5 % of them within 30-35
years, 22.5% of them within above 36 years.
As it is shown on the above table1 (72.5%) of the respondents were
males whereas ( 27.5%) of them were females. This shown that the
numbers of males is much more than number of females Worker.
As indicated in table 1 age distribution is one of the demographic
characteristics that show the proportion of people by dividing in to
different sections. From the given table 25% of the total respondents
were within age range of 24-29 years, 52.5 % of them within 30-35
years, 22.5% of them within above 36 years.
Table 3 performance of project committees
Performance
How was the
performance
Respondents High Medium Low very low
of the project
committee in
No 6 10 20 4
sululta
administrativ
e city
regarding the
completion of
the project ? % 15 25 50 10
As shown on the above table 3 the
respondents indicate that performance
of the project committee is 15% high,
25% is medium, 50% is low and 10%
is very low respectively .as we
understand from the above table the
activities of project committee in
Sululta Administrative city is low .this
clearly indicate the cause delay of the
road bridge project.
Table 4The evaluation and monitoring system
Performance
Total
How the
Respondents High Medium low very low
project
40
committee
and the client No 4 10 20 6
sectors 100
monitor and
evaluate the
project ? % 10 25 50 15
As shown on the above table 4 the
respondents indicate that performance of the
monitoring and their evaluation
activities :- 10% is high, 25% is medium,
50% is low and 15% is very low
respectively. When we analyzed the
monitoring and evaluation activities of
project committee and the client sector in
Sululta Administrative city is weak. for
these reason the Beldaras road bridge
project started in 2011 and have not been
completed up to now.
Table 5 Are the project committee and client sector
effective in case of managing project ?
Are the project
committee and
Number of Respondent %
client sector
effective in case Yes 18 45
of managing No 22 55
project?
Total 40 100
. As we understand on table 5
45% from the total respondent
agreed that the project committee
can perform the project in effective
way but 55% of the respondent from
the total said no, this show that the
project committee and client sector
cannot perform their task in
effective way.
Chapter Five
5. Conclusion And Recommendation
5.1 Conclusion
To study reason construction delay of road bridge project in
Sululta Administrative city, we prepared questioner and distributed
for 40 employers of the stuff. Then we have collected all
questioner from respondents and analyzed it by using tables.
when we have seen the opinion of respondents on table 3 the
activities of project committee are, 15% high, 25% medium, 50
% low and 10% very low respectively . this clearly indicate they
have poor performance . When we analyzed on table 4 65% of the
respondent agreed that the delay problem of project in case of low
evaluation and low controlling system . Generally when we
conclude this finding the performance of the project committee and
the client sector of the Sululta administrative city have poor
performance in case of management such as planning, following
up, controlling contractor, to accomplish road bridge on time and
with quality
5.2 Recommendation
Based on the findings of our case study we recommend
the following points how the project committee, client
sector ,contractor and consultant respectively mitigate
the problem of delay of project construction.
Before execution of the project the client sectors and
project committee should give more attention for
planning and for visibility study.
Problem of civil engineering have been clearly observed
on construction project of sululta administrative city. So
the they should solve this problem. .
Client and contractor should avoid suspension work that lead
for additional time.
The project committee should give great attention to
environmental degradation. Because around the construction
area there is high gorge and valley that may affect the
residential. For that on the area the physical and biological
structure should be done.
In case of monitoring and evaluation the activity of project
committee is weak, so they should be essential for them to
solve problem associated with management .
Referance.
Ahmed, S Azher, S., Castillo, M. and Kappagantula, P. (2002) Construction delays
in Florida; an empirical study, Florida,
2002.http://www.cm.fiu.edu/publication/Delays .pdf, Retrieved on 2 June, 2017
Alaghbari, W., Kadir, M. A., & Salim, A., E. (2007). The significant factors causing
delay of building construction projects in Malaysia. Construction and
Architectural Management, 14(2), 192–206. http://dx.doi.org. Retrieved on 13
April, 2017.
Ethiopian Roads Authority (ERA). 2011. Road Sector Development Program
Performance: Thirteen Years Performance and Phase IV.
Fugar, F. D. K., & Agyakwah, B. A. B. (2010). Delays in Building Construction
Projects in Ghana, Australasian Journal of Construction Economics and Building,
10(1), 103‐116.
Frimpong, Y., Oluwoye, J.and Crawford, L. (2003). Causes of delay and cost
overruns in construction in developing countries‟, International Journal of project
management.
(I J.PMS,2006). Causes and Effects of Delay on Project Construction Delivery time
(on line). Available http://eprints.covenantuniversity.edu.ng. Retrieved on 9 April,
2018
Msafiri Atibu Seboru. An Investigation into Factors
Causing Delays in Birdge Construction Projects in
Kenya. American Journal of Civil Engineering. Vol. 3, No.
3, 2015, pp. 51-63. doi:
Owolabi James (2014). Causes and Effects of Delay on
Project Construction Delivery time (on line). Available
http://eprints.covenantuniversity.edu.ng. Retrieved on 9
April, 2017
Stumpf, G. (2000). Schedule delay analysis.
Construction Engineering Journal. 42(7):32–43 Syed,