PSCH - P-3242 Istanbul PPR 2019-08 - Rev.17 - Edh

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 12

P-3242 Istanbul

Overall Progress Curve By PSch

MAIN MESSAGE
• Overall progress – a further slippage
occurred based on delayed tower crane
installation on site
• Delay against BL 4.2 Month
• PAC has not been shifted beyond
23/07/2021

Project Progress Report Aug. 2019_P-3242 Istanbul 1


P-3242 Istanbul
Key Dates Movements By PSch

Project Progress Report Aug. 2019_P-3242 Istanbul 2


P-3242 Istanbul
Project Key Dates (QGR) 1/2 By PSch & PEM

Project Progress Report Aug. 2019_P-3242 Istanbul 3


P-3242 Istanbul
Project Key Dates (QGR) 2/2 By PSch & PEM

Project Progress Report Aug. 2019_P-3242 Istanbul 4


P-3242 Istanbul
Project Main Critical Path By PSch

Schedule risks from critical path Mitigation measure Action owner Due date
Tower Cranes Installation Expedite installation of TC PB End of
(HZI FSPE dept.) Sept.

Steel Structure Quality Supplier is on site and instruct the construction HZI End Sept.
company how to solve quality issues.

Missing bolts, nuts and washers Missing bolts will be purchased asap. Steel structure End Sept.
supplier

Project Progress Report Aug. 2019_P-3242 Istanbul 6


P-3242 Istanbul
On Time Performance By PSch

List of delayed activities having an Mitigation measure Action owner Due date
impact on the 1st 3 subcritical paths

Project Progress Report Aug. 2019_P-3242 Istanbul 8


P-3242 Istanbul
Progress Curve – Engineering Overall By PSch

• Overall actual is 99.55%

Project Progress Report Aug. 2019_P-3242 Istanbul 9


P-3242 Istanbul Back–up Slide
Progress Curve – Engineering CSP (CB+WSC) By PSch

• Overall progress - 100%

Project Progress Report Aug. 2019_P-3242 Istanbul 10


P-3242 Istanbul Back–up Slide
Progress Curve – Engineering FGT By PSch

• Overall progress - 100 %

Project Progress Report Aug. 2019_P-3242 Istanbul 11


P-3242 Istanbul Back–up Slide
Progress Curve – E&IC Engineering By PSch

• Overall progress 99.61%

Project Progress Report Aug. 2019_P-3242 Istanbul 12


P-3242 Istanbul Back–up Slide
Progress Curve – Plant Engineering By PSch

• Overall progress:
Actual 96.68% vs 100% planned

Project Progress Report Aug. 2019_P-3242 Istanbul 13


P-3242 Istanbul
Progress Curve - Procurement By PSch

• Progress Increase 1.5% vs. 1.98%


planned
• Overall progress still 8.04 % under
planned progress
• Trend goes down since last update

Project Progress Report Aug. 2019_P-3242 Istanbul 14

You might also like