MAIN MESSAGE
• Overall progress – a further slippage
occurred based on delayed tower crane
installation on site
• Delay against BL 4.2 Month
• PAC has not been shifted beyond
23/07/2021
Schedule risks from critical path Mitigation measure Action owner Due date
Tower Cranes Installation Expedite installation of TC PB End of
(HZI FSPE dept.) Sept.
Steel Structure Quality Supplier is on site and instruct the construction HZI End Sept.
company how to solve quality issues.
Missing bolts, nuts and washers Missing bolts will be purchased asap. Steel structure End Sept.
supplier
List of delayed activities having an Mitigation measure Action owner Due date
impact on the 1st 3 subcritical paths
• Overall progress:
Actual 96.68% vs 100% planned