Professional Documents
Culture Documents
05 PM Imdr C Crashing
05 PM Imdr C Crashing
CRASHING
CPM: Time-Cost
Relationship
Time Cost Relationship in CPM
Crash
Cc Cost Slope = (Cc – Cn) / (Tc – Tn)
Direct cost of Activity
Cn Normal
Tc Tn
Duration of activity
Time Cost Trade off
• Time and Cost are two important items that a Project
Manager deals with . It is necessary to have a
judicious balance between the two. This is called
Time cost trade off
• Some times projects have to be speeded up due to
various reasons.
• This can be done by “crashing” Activities on the
Critical Path. Crashing Activities on Non critical Paths
which have “slack” will only result in extra costs due
to “crashing” without bringing down Project
completion time
Time Cost Trade off
LS LF
0 9 12 17
C 14 19
0 9 2 4
5 F 17 22
A
5
9 D 9 17 6
1 8 9 17
B G
5 17 22
0 8 8 E 5
3
2 10 7 8 15 17 22
10 17
ADG is the Critical Path having no slack.
The Project Duration is 22 wks
Example- Cont’d
Activity Tn Cn Tc Cc Cost Slope
A 9 10 6 16 2
B 8 9 5 18 3
C 5 7 4 8 1
D 8 9 6 19 5
E 7 7 3 15 2
F 5 5 5 5 -
G 5 8 2 23 5
0 6 9 14
LS LF
C 11 16
0 6 2 4
5 F 14 19
A
5
6 D 6 14 6
1 8 6 14
B G
5 14 19
0 8 8 E 5
3
0 8 6 8 14 14 19
8 14
ADG and BEG are the Critical Paths having no slack.
The Project Duration is 19 wks
EXAMPLE- cont’d
6 11 LS LF
0 6 7 12
C 11 16
0 6 2 4 Activity C& F
5 F 12 17 Have slack
A
5 Of 1 week
6
D 6 14 6
1 6 14
B 8 G
0 8 E 3 14 17
8 3 5
0 8 6 8 14 14 17
8 14
ADG and BEG are the Critical Paths having no slack.
Duration of Activity G reduced by 2 weeks. New
Project Duration is 17 wks
Example- Cont’d
• The revised cost of the Project will be: Rs. 63 K
(Cost of Project of duration 19 weeks) + Cost
escalation in Activity G due to speeding up the
Activity by 2 weeks i.e. 2x5K = Rs.73 K
6 11 LS LF
0 6 6 11
C 11 16
0 6 2 4
5 F 11 16
A
6 5
D 6 14
1 6
8 6 14
B G
0 8 E 2 14 16
8 3 5
0 8 6 8 14 14 16
8 14
ADG and BEG are the Critical Paths having no slack.
Duration of Activity G reduced by 3 weeks.
New Project Duration is 16 wks. C& F becomes critical.
Example- Cont’d
6 10 LS LF
0 6 6 10
C 10 15
0 6 2 4
4 F 10 15
A
6 5
D 6 13 6
1 6 13
B 7 G
0 8 E 2 13 15
8 3 5
0 8 5 8 13 13 15
8 13
ADG ,BEG , ACG critical paths.
Duration of Activity C,D &E reduced by 1 week.
New Project Duration is 15 wks.
Example- cont’d
• Cost of Project (duration 15 weeks) = Cost of
Project duration 16 weeks Rs.78K+ Cost
escalation in C for 1 week 1x1K+ Cost
escalation in D for 1 week 1x5K+ Cost
escalation in E for 1 week 1x2 K= Rs.86 K
Indirect costs
Optimum Project duration
Time weeks
Finding out Optimum Project
duration (Least cost duration)
Find the critical path and the Total Direct costs for
optimum Project duration 4 Project at Tn is
C
Rs.3600K
A 7
1 2
9 D
B 4 Indirect expenses is
at the rate of Rs. 250
5 per week
3
Activity D on Critical Path can be reduced by since it has the lowest Cost slope of Rs
200/ week.
Total project cost for 17 weeks = 3600+1x200 + 17x250= Rs 8050
Total Project cost for 16 weeks of duration is = 3800 + 1x200+ 16x250=Rs 8000
Now both paths ABD and AC have become critical with 16 weeks each
Indirect cost
Direct cost
Finding out Optimum Project
duration (Least cost duration)
BOTH ABD & AC are Critical paths
EF=16 LF=16
ES=0 4
EF=9 C
LS=0 LF=9
A 7
1 2 ES=9
9 LS=9 D
B 2
5 EF=14
ES=LS=14
LF=14 3
The cost of crashing A is Rs. 300 per week. Cost of crashing B & C together
is Rs. 400+ 200 = 600. So, we choose crashing A.
(Tc= 4 weeks)
Total Project cost for 15 weeks = 4000+ 1x300+ 15x 250 = 8050
Total Project cost for 14 weeks = 4300+ 1x300+14x250 = 8100
Total Project cost for 13 weeks = 4600+ 1x300 +13x250 = 8150
Direct cost
Indirect cost
Finding out Optimum Project
duration (Least cost duration
Summarizing
18 8100
17 8050
16 8000
15 8050
14 8100
Exh 19.30
Exh 19.31 – normal duration. Crash one-by-one, don’t repeat already crashed
activity
CPM Model
Crashing Illustration
Crashing Illustration