Professional Documents
Culture Documents
Automatic Generation Control (AGC)
Automatic Generation Control (AGC)
(AGC)
by
KIRTIMAN GODARA
M.TECH(Power Systems)
Department of Electrical Engineering
DELHI TECHNICAL UNIVERSITY
DELHI
1
Outline
Purpose and Overview of AGC
Automatic Generation Control
(AGC)
System modeling: control block
diagram
AGC for single generator
AGC for 2 generator
AGC for multi generator
Area Control Error (ACE)
2
Purpose of AGC
To maintain power balance in the
system.
Make sure that operating limits
are not exceeded:-
◦ Generators limit
◦ Tie-lines limit
Make sure that system frequency
is constant (not change by load).
3
Overview of AGC
Load is always changing.
To maintain power balance,
generators need to produce more
or less to keep up with the load.
When Gen < Load (Gen > Load),
generator speed and frequency
will drop (rise).
=> We use this generator speed
and frequency as control signals!
4
3 Components of AGC
Primary control
◦ Immediate (automatic) action to sudden change of
load.
◦ For example, reaction to frequency change.
Secondary control
◦ To bring tie-line flows to scheduled.
◦ Corrective actions are done by operators.
Economic dispatch
◦ Make sure that the units are scheduled in the most
economical way.
This
presentation covers only primary and
secondary control of AGC.
5
FUNDAMENTAL OF SPEED
GOVERNING
7
ISOCHRONOUS
GOVERNOR
8
GOVERNOR WITH SPEED
DROP CHARACTERISTIC
9
LOAD SHARING BY PARALLEL
UNITS
Turbine and Generator Load
Model
Turbine Model
YE ( s ) Kt Pg ( s)
1 STt
11
AGC for Single
Generator
closed loop power control system
as below.
1
R PD ( s )
PC - Kg Kt -
Kp
+ 1 sTg 1 sTT +
Pg ( s ) 1 STp F ( s )
12
AGC IN TWO AREA
AGC FOR TWO
AREA
AGC for Multi Generators: Block
Diagram
Change in tie-line
Pi power flow
PCi PMi + - i
GMi s GPi s
+
- -
PLi
1
Ri
1 1
GPi s GMi s
~
M i s Di 1 sTGi 1 sTTi
15
AGC for Multi
Areas
Simplified Control
Model
Area Control Error
(ACE)
16
AGC for Multi Areas
During transient period, sudden change of load
causes each area generation to react according
to its frequency-power characteristics.
This is “called primary control”.
This change also effects steady state frequency
and tie-line flows between areas.
We need to
Restore system frequency,
Restore tie-line capacities to the scheduled value, and,
Make the areas absorb their own load.
This is called “secondary control”.
17
AGC for Multi
Generators
Consider effect of
◦ power flows in transmission lines,
and
◦ loads at each bus
to mechanical power of each
generator.
This analysis assumes that every
bus is a generator bus.
18
Area Control Error (ACE)
Control setting power of each area
needs to be adjusted corresponding
to the change of scheduled tie-line
capacity and change of system
frequency.
ACE measures this balance, and is
given by,
ACE1 P12 B1
ACE2 P21 B2
1
Bi DLi
for two area case. Ri
WhereBi = Frequency bias setting of area i (>0) and
19
ACE: Tie-Line Bias Control
Use ACE to adjust setting controlPCi
power, , of each area.
Goal:
◦ To drive ACE in all area to zero.
◦ To send appropriate signal to setting
control
P power,
Ci
20
Simplified Control Model
Generators are grouped into control areas.
Consider
An area as one generator in single area, and,
Tie-lines between areas as transmission lines
connecting buses in single area.
We can apply the same analysis to multi-
area!!
However, we have to come up with
frequency-power characteristics of each
area.
Actual application of this model is for
power pool operation.
21
Power Pool Operation
Power pool is an interconnection of
the power systems of individual
utilities.
Each company operates
independently, BUT,
They have to maintain
◦ contractual agreement about power
exchange of different utilities, and,
◦ same system frequency.
Basic rules
◦ Maintain scheduled tie-line capacities.
◦ Each area absorbs its own load changes.
22