Professional Documents
Culture Documents
Penangangan Sedimentasi PLTA Bakaru
Penangangan Sedimentasi PLTA Bakaru
Regulating Pondage
High water level EL. 615.5 m
Reservoir area 2 km2
Gross capacity 6.92 106 m3
Effective capacity 2.0 106 m3
Effective depth 3.5 m
Dam
Type Concrete gravity
Height 16.5 m
Crest length 92.5 m
Discharge capacity 2,850 m3/sec
Spillway gate 4 steel radial gates 10.5 m wide 8.0 m high each
Sand drain gate 2 steel radial gates 10.5 m wide 10.0 m high each
Discharge regulating gate 2 steel roller gates 4.0 m wide 4.0 m high each
High water level (H.W.L.) 615.5 m
Low water level (L.W.L.) 612.0 m
GENERAL LAYOUT BAKARU 2
Powerhouse Bakaru II
2. Present Condition of Bakaru Reservoir
Since 1996 the Bakaru reservoir has been largely filled up with sediments despite of various measures taken by PLN to re-establish and
maintain at least part of the active storage.
Specific sediment yield = 1.65 x 106 m3/year /1,080 km2 = 1,530 m3/km2/year
Sedimentation History of Bakaru Reservoir
(Reference: Page 8-16 Chapter 8 Cost Estimate, Final Feasibility Report Stage III Vol I – Main Report, April 2016, Poko
and Bakaru II HPP Update of Existing Study)
3. BAKARU II HPP – Reservoir Restoration – Sediment Management (2)
General Principal of the Suction Dredge
Table Theoretical dredging capacity
(50% of theoretical max., by SEDICON, Norway)
:
The SEDICON dredge is a hydrosuction syatem that
uses that the available water head between the
reservoir and the outlet of the discharging pipe for
pumping water and sediment.
: dredge has following advantages
The
Miwa dam is located near Ina City, in the Nagano district west of Tokyo
(Reference: Page 8-16 Chapter 8 Cost Estimate, Final Feasibility Report Stage III Vol I – Main Report, April 2016, Poko
and Bakaru II HPP Update of Existing Study)
3. BAKARU HPP (+ Poko HPP) – Sedimentation Simulation Analysis (1)
Reproduction Simulation
Poko Dam
- Bakaru Dam
1990 to 1999
1985 to 2013
Prediction Simulation
Bakaru Dam
Reproduction Simulation
- Bakaru I
1991 to 2000
1985 to 2014
1985 1991
(Bakaru Commencement) Year
2014 Prediction Simulation (100 Years)
1994
1995
1996
Initial.Bed 1994 Riverbed Initial.Bed 1997
Riverbed
Obs.(1994)
Obs.(1997)
Obs.(1999)
1995
1996
1997 900
1991
1992
1993
1998
1999
Max.WL.
- HPPs
1991 1998
640
1992
1993
1999
Max.WL.
850
Bakaru I
635
Comparison between Bakaru I + II
800
625 700
- Countermeasures
620 650
None
615
600
0 5 10 15 20 25 30 35 40 45 50 55 60 Flushing
Distance [km]
610 1994_WL.
1995_WL.
Dredging
Flushing + Dredging
1996_WL.
Water Level 1997_WL.
1991_WL. 1998_WL.
1992_WL. 1999_WL.
605 1993_WL. InitialBed
2.2 Flushing
No Measure
100-yr
”Surplus energy senario: Allocation of additional energy in excess of Bakaru I HPP to Bakaru II HPP”
Total energy: 351.5 GWh, Firm peak energy: 142.1 GWh, Off-peak energy: 209.4 GWh
6. Project Implementation Schedule
Preliminary Implementation Schedule for BAKARU II HEPP
The present Update Studies reconfirm the technical and economic viability of the BAKARU II HPP, which
is, therefore, strongly recommended for implementation, i.e. to proceed to the next planning stage, tender
design and tender procedures to obtain a possible early commissioning of the hydropower plant. The
milestones of the Consultants activities during this Update Studies are summarized below.
(Reference: Page 11-7 Chapter 11 Conclusion and Recommendation, Final Feasibility Report Stage III Vol I – Main Report, April 2016, Poko and Bakaru II HPP Update of Existing Study)