CFA BORED PILING
https://sheppardpiling.com 4
BORED PILED
RETAINING WALLS
PILING
CONTIGUOUS PILED WALL
Contiguous piled retaining walls are formed using
either Rotary or CFA piling technics, piles are installed
at close centres, with typically 100-200mm gaps
between piles. These piles form temporary or
permanent support to excavations. This techniques is
suitable for basements, underground structures and
motorway cuttings where working space is limited or
adjacent to existing structures.
SECANT PILED WALL
Secant piled retaining walls are formed using either Rotary or CFA piling
technics, unreinforced female piles are installed at close centres using a
slow-gain (soft) concrete mix, after a sufficient curing period and once each
alternate pile has been installed, the reinforced male piles are installed
using a standard concrete mix. The overlap for a typical secant section is
approximately 75 – 100mm which ensures that water ingress is minimised
and fines wash-out is prevented. The interlocking secant wall is not
watertight; however water flow is greatly reduced.
https://sheppardpiling.com 5
RESTRICTED ACCESS
MINI PILING
Our rigs can work in a confined space of
approximately 2.0m headroom and 750mm
access point. This is particularly useful for
basement projects in land-locked areas such as
London, residential extensions where access for
the larger rigs might be an issue or poor ground
conditions. The three main techniques of mini
piling that we use are as follows:
SECTIONAL FLIGHT AUGER BORED PILES – OPEN AUGER BORE
https://sheppardpiling.com 6
ROTARY AUGER BORED
PILING
Rotary Auger Bored Piling are constructed with a
short solid stemmed auger attached to a
telescopic Kelly bar, once the design depth has
been reached the Kelly bar / auger is removed
from the bore and the pile reinforcement is
placed ready for concreting, once concrete has
been introduced the pile is completed. Where
unstable ground or ground water is encountered
this piling system can install temporary /
permanent lining tubes to allow sufficient
support for the pile bore during the concreting
process.
https://sheppardpiling.com 7
AWARDS &
ACCREDITATIONS
https://sheppardpiling.com 8
Head Office:
Sheppard Piling, Fetcham Park, Lower
Road, Fetcham, KT22 9HD
T: 01372 232 090
help@sheppardpiling.com
Brentwood Office:
Unit 6C, Cockridden Farm Estate,
Brentwood, CM13 3LH
T: 01277 572 090