Project Scheduling Terms
• Merge activities
• Burst activities
• Node
• Path
• Critical Path
A D E F
C
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-3
Network Diagrams
Show Help
interdependence schedule
resources
Show
Facilitate start &
communication finish
dates
Determine project Identify
completion critical
activities
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-4
AOA vs. AON
The same mini-project is shown with activities on
arrow…
D E
B F
C
C
Node and activity labels in AoA
diagrams
(NOT following the textbook)
Deadline
Free float
Activity Descriptor
Late Activity Late
Start Duration Finish
Duration Estimation Methods
• Past experience
• Expert opinion
• Mathematical derivation – Beta distribution
– Most likely (m)
2
– Most pessimistic (b) ba
– Most optimistic (a)
Activity Variance = s
2
6
a 4m b
Activity Duration = TE
6
Beta distribution
Task Predecessor a m b TE s2
A -- 7 8 15 9 1.8
B A 13 16 19 16 1.0
C A 14 18 22 18 1.8
D B, C 12 14 16 14 0.4
E D 1 4 13 5 4.0
F D 6 10 14 10 1.8
G F, E 11 14 19 14.3 1.4
Solution with AoN diagram
2 2
9 2 25 41 5 46
b e
11 16 27 46 5 51
0 0 0
0 0 9 27 0 41 51 0 65
a d g
0 9 9 27 14 41 51 14 65
0 0
9 0 27 41 0 51
c f
9 18 27 41 10 51
0 Hammock 18
0 18 18
Useful with a complex
project or one that has
a shared budget
Reducing the Critical Path
• Eliminate tasks on the CP
• Convert serial paths to parallel when possible
• Overlap sequential tasks
• Shorten the duration on critical path tasks
• Shorten
– early tasks
– longest tasks
– easiest tasks
– tasks that cost the least to speed up
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-17
Optional HW
• Create the AoA & AoN networks of your project
using the symbols of this class.
• Prize: 15%
• Task list with cost estimation: +5%