Professional Documents
Culture Documents
Project Planning and CONTROL - Unit 1: Class 1
Project Planning and CONTROL - Unit 1: Class 1
o These levels depend upon the plan type, the nature and complexity of
the project and the expected degree of control.
o Project work breakdown enables splitting of the project work into hierarchical
work breakdown levels of sub-projects, tasks, work packages and activities.
o Each activity represents identifiable lower level job which consumes time and
possibly resources.
o Projects are best managed by work packages and best planned and monitored
by activities.
The work break down levels are broadly categorized into five levels
Sub-project level
Task level
Work-package level
Activity level
Operational level
Each level has certain features associated with it. However level
categorization is broad concept and at time their overlapping may
become unavoidable.
activity.
Actual duration,
Original duration,
Remaining duration.
o The sum total of the activity duration can also be broken up into
smaller parts in the establishment of project milestones, points at
which either the current state of the project will be assessed, or
potentially sum or all deliverables will be submitted in either final
or draft form.
Activity Duration Estimating
Activity duration estimating represents the act of quantifying the
amount of time that it is anticipated that the activity will take.
o Use this method at the beginning of a project when we don’t have all
the details. Adjust the estimates as a learning grows about the tasks and
how long they can be expected to take with the resources available.
4. Parametric Estimation
o The parametric estimation is similar, but more accurate than the
analogous estimation. To use it, multiply the number of units we need by
the time it takes to produce the units. We need historical information
about similar activities to complete the estimate. The method is
scalable.
5. Expert Judgment
o If the project is complicated and a number of factors can influence the
duration of the activities, we might want to use expert judgment to
estimate activity duration.
What are the activities that you have to do in the project? By using a
Work Breakdown Structure (WBS) and a deliverables diagram, take these
activities and organize them by mapping out the tasks necessary to
complete them in an order than makes sense.
Do Estimates
With the activities defined and broken down into tasks, next have to
determine the time and effort it will take to complete them. This is an
essential piece of the equation in order to calculate the correct schedule.
Determine Dependencies
Tasks are not an island, and often one cannot be started until the
other is completed. That’s called a task dependency, and the schedule is
going to reflect these linked tasks. One way to do this is by putting a bit
Assign Resources
Scheduling
People
Scheduling
Projects
Another way to stay on top of scheduling is by integrating the
task scheduling view on the Gantt chart with resource and workload
scheduling features.
Simple construction scheduling techniques that will help
represent and create construction schedules techniques.
o Q Scheduling
1. Using Bar Charts
o Bar Charts are the most simple and easiest way to generate construction
schedules.
o It is widely used due to its simplicity and multiple adaptations to numerous
events.
o A bar chart is formed with a list of activities, specifying the start date, duration of
the activity and completion date of each activity, and then plotted on a project
timescale.
o The detailed level of the bar chart depends on the project complexity and the
intended use of the schedule.
o A variation of the bar chart schedule is the linked bar chart. A linked bar chart
uses arrow and lines to tie the activities and subsequent items, specifying the
successors and predecessors of every activity. The previous activities are linked
one to another to demonstrate that one activity must be completed before the
other activity can start.
o Bar charts are useful and used to detect the amount of resources needed for one
particular project. Resource aggregation is done by adding resources vertically in
the schedule.
o The purpose of this aggregation is to estimate the work production
and establishing estimates for man-hour and equipment needed.
2. Critical Path Method
o This process is more complex and detailed than the bar chart.
o With a large list of activities, each activity is then linked to previous
and subsequent activities, specifying that each activity has at least
another one that must be completed prior to starting the preceding
one.
o The Critical Path Method establishes and assigns start and end dates
based on certain logic like ES, EF, LS, LF that are key indicators of how
activities must be sequenced.
o These constraints determine the first date that an activity can start;
late start, specifying the last possible date that this activity must be
started to avoid delays in the overall construction process; early
finish, the earlier date that the proposed activity will be completed;
and the late finish, that is the last date the activity must be completed
without affecting the start of the next one, and subsequently affecting
the entire construction scheduling resources.
The steps in producing a network are:
o Listing of Activities
LEADS AND LAGS - A lead may be used to indicate that an activity can start before its
predecessor activity is completed. For example, editing of a book may start before the
write-up is finished. A lag is inserted waiting time between activities, such as needing to
wait for completion of the application testing before the final roll-out of the application.
Sequence Activities process can also result in the identification of new risks. It may also
lead to updates to the activity list and activity attributes.