Piping Work From Patalganga to Aadhoshi

Dam

A B INFRA
STRUCTURAL CONSULTANCY BY - STRUCTSOURCE ENGINEERING SOLUTIONS, PUNE
Index

1. Input

2. Options Considered.

3. Calculation of Piping Length

4.Sample Calculation of BOQ (For recommended option)

5. Summary
1. Input

a) Water Demand-
Current- 5 lacs Litre/Day
After completion – 20 lacs Litre/Day.

b) 4” GI piping work from Adoshi Dam to site is


completed.

c) Water availability in Patalganga river – Perennial.


Options Considered

Case Description Alignment

1 MS Pipe with 300 mm Dia Along Nalla

2 MS Pipe with 300 mm Dia Along Road

3 MS Pipe with 150 mm Dia Along Nalla

4 MS Pipe with 150 mm Dia Along Road

5 GI Pipe with 150 mm Dia Along Road

Presented by: STRUCTSOURCE ENGINEERING SOLUTIONS


Calculation of Piping Length

1.Alignment by Nalla

2.Alignment by Road

Presented by: STRUCTSOURCE ENGINEERING


SOLUTIONS
Notes –
1.Price above is exclusive of
a) Lisening Cost
b) Cost required to resolve local issues.
c) All applicable taxes
2.Pipe Length considered are based on measurement done using Google earth and
basic survey by road ,Actual length will be decided only after detailed survey

Presented by: MATRIX & STRUCTSOURCE SOLUTIONS


OPTIONS FOR CASTING YARD
OPTION 4:
 Advantages:
• Nearest to the proposed bridge.
• Well accessible as such.
Option1 • Only 2 cranes needed.

 Disadvantages:
• No permission to disturb the
Option3
natural water body.

on4
Opti

on2
Opti

OPTION 3 IS FINALISED

OPTION 2: OPTION 1: OPTION 3:


 Advantages:  Advantages:  Advantages:
 Close to bridge • Area is well connected to existing • Near to the proposed bridge.
 Disadvantages: temporary road. • Crane movements will be simple
• Area is not sufficient. • Need minimum land preparation  Disadvantages:
• Might be a problem for • Crane movements will be simple • Undulations on the site.
other construction activity  Disadvantages: • Additional temporary road is
• Need to remove 4 to 5 • 3 cranes will be needed with a multi- required to be prepare.
trees. axle vehicle for loading of girders.
Presented by: MATRIX & STRUCTSOURCE SOLUTIONS
METHODOLOGY FOR EXECUTION OF “OPTION1”

Casting Yard SECTOR D


CRANE 3 CRANE 2
which will be stagnant which will be moving

Multi-axle for loading


& deloading Nallah

SECTOR C

CRANE 1
which will be stagnant

Presented by: MATRIX & STRUCTSOURCE SOLUTIONS


Aerial view 2

Crane 2 Crane 3
Crane 1
Casting Yard

Multi-axle for
loading & deloading

Presented by: MATRIX & STRUCTSOURCE SOLUTIONS


Rear view

Crane 2

Crane 1

Crane 3
PSC Girders

Abutment 2
Abutment 1

Presented by: MATRIX & STRUCTSOURCE SOLUTIONS


Plan showing general arrangement and mobility of cranes and axle

Crane 2:Moving

Temporary Road
Casting yard Casting yard

Crane 2:Moving

Crane 3:Stagnant
Crane 3:Stagnant

Temporary Road
Crane 1:Stagnant
Crane 1:Stagnant

Presented by: MATRIX & STRUCTSOURCE SOLUTIONS


WORK SEQUENCE
Site Detour preparation Preparation of Benchmark,
for vehicle casting bed for Center layout and
cleaning movements PSC girder bridge alignment

Material Excavation Transporting


equipment's and
procurement of footings other tools

Concreting Parallel casting Concreting


of foundation of PSC girders of abutments Pedestals

Casting of slab Launching of


Shuttering for trench which PSC girders by
for deck slab contains cables crane

Preparing and
Casting of Curing of Laying precast
laying wearing
deck slab deck slab cover slab coat

Finishing
items.

Presented by: Pravin Bhukan (Founder, Matrix


Structural Consultancy)
BAR CHART
Thank You