Quality Training Part 2 (Telecom Sites Building)
Quality Training Part 2 (Telecom Sites Building)
For
Tower Vision India (P) Ltd.
QA Deptt.
Prepared by: Pawan K Sharma
Shuttering
Beam reinforcement
Side shuttering
Material to be used
Plywood
Steel Plates
Place the reinforcement on the
bottom shuttering with required as
mentioned in the drawing
It results
Quality shuttering
Template
Foundation Bolts
Template & Foundation bolts fixing
m 2.1
Calculations for diagonal distance 2.1 m
2.12+2.12 = 2.97 m
2.97 m
2.97 m
2.1 m
m 2.1
Template & Foundation bolts fixing Template
Template Plate
Template Plate
Side View
Template & Foundation bolts fixing Template
Side View
Template & Foundation bolts fixing Template
Results in eccentricity
Side View
Template & Foundation bolts fixing
Foundation
bolts
Template & Foundation bolts fixing
Template
Now the site is ready for concreting
Foundation
bolts
TOP VIEW
Concreting
Checks: before concreting
Concrete MIX
Generally used mix is M20
‘M’ indicates MIX
’20’ indicates compressive
strength of concrete cube
(150x150x150mm) after
28days curing
Water proof
coping
In the same way construct Shelter foundation and DG foundation
Tower Foundation
Shelter Foundation
DG Foundation
•
Survey Tools
Survey tools are same for RTT & GBT sites;
White Paper, Scale (30cm), Pencil, etc,. to draw the rough layout
Compass
With the above details we can find out whether the given size of the site is
suitable or not to arrange the all above equipments.
SITE SURVEY – GBT
Tower Excavation Width
If foundation drawing is available, excavation width can be know from that drawing
If foundation drawing is NOT available: take excavation width = 2 x Tower Base width
3.2
Excavation Line
40 m 6.4 = 2 x 3.2
Tower
This is only for survey purpose; during execution we have to follow as per foundation
drawing only.
PREPARATION OF LAYOUT AT SITE Kota – 40m, Near Petrol Pump, Main Road, Nellore Dt.
PROCEDURE / CHECKS N
Street road
1. Write Site Name, Tower Ht., Site 20m
Address at the top of the page.
1.5
1.2 1.5
3.3 3.5 1.5
4.0
2. Draw the boundary line with 1.5
3.2 DG EP
dimensions. Make sure that, 0o Should be
3. Indicate the NORTH direction. placed upward of your page 0.5 x 0.5
2 x 1.5
4. Mark the adjacent roads, surrounding 40 m
structures and its distances. Tower
Green Field
5. Mark the site level w.r.t. the road level EP
Green Field
0.5 x 0.5
6. Mark the proposed area of tower, DG & 15m 15m
Shelter 1.5
EP EP
7. Mark all dimensions w.r.t. the boundary Shelter
0.5 x 0.5 0.5 x 0.5
as shown
2.5x3.2
8. Mark the cable tray rooting 2.5
Security
9. Mark the proposed Earth Pits Room
GATE
10. Mark the Security room and gate 3x3
11. Mark the nearest Elec. Pole / Transformer 20m
to the site Electric Pole
Main Road
12. Write your name, Employee ID No., Date
& Sign
+ 0.5 m w.r.t. the road level
13. Take the Owner sign and h
Rajes
customer site engineer sign P
P Rajesh
401501
14. This Rough layout should be sent to Owner Customer
03.03.06
Design department to prepare CAD
Kota – 40m, Near Petrol Pump, Main Road, Nellore Dt.
SOIL TEST
Street road N
20m
To design the foundation, we require soil
parameters like SBC, Density, Angle of 1.5
1.2 1.5
3.3 3.5 1.5
4.0
1.5
repose etc., DG
2 x 1.5
Soil sample to be collected within the
proposed area of the tower
Green Field
Soil report should be sent to design
Green Field
department to design the foundation 15m 15m
1.5 Soil sample
The following are the different types of collected areas
foundations depends upon the soil Shelter
conditions 2.5x3.2
2.5
Security
Isolated Foundation Room
GATE
Raft Foundation 3x3
20m
Pile Foundation Electric Pole
Main Road
Rock-Anchor Foundation
Green Field
Ex.: 6 m is the width of the
Green Field
excavation
Check the diagonal distances
6
6 +62 2
= 8.485 m
Main Road
Seepage of water
Excavation
Levelling
Volumes per Cu M
Grade Ball
Sand
of Proport ast
Cement (cum)
Concre ion (cu
(cum)
te m)
1:3:6 0.9 0.45 0.15 4.5 bags
M10 1:4:8 0.92 0.46 0.115 3.45 bags
1:5:10 0.95 0.475 0.095 2.85 bags
PCC
After laying the PCC, mark the column Check the c/c distances and diagonal
positions to place the column distances
reinforcement.
Bar bending – Shuttering – Concreting
Bottom reinforcement
in two way direction
Side view
Bar bending – Shuttering – Concreting
Side view
Bar bending – Shuttering – Concreting
Stirrups at the top of the
column reifn.
Column Stirrups
Set
First arrange the stirrups at top and
bottom of the column reinf.
Bar bending – Shuttering – Concreting
Chairs
Bar bending – Shuttering – Concreting
Stirrups
Bar bending – Shuttering – Concreting
Raft Shuttering
Picture at site
After Concreting
Position of T B Bars
Template fixing
Recall the procedure which we have discussed in RTT site
Template & Foundation bolts fixing
Template fixing
Procedure for
water level
checking
Alignment & Fixing of Anchor Bolts
Side View
Isometric View
Top View
Bar bending – Shuttering – Concreting
Template fixing
Template fixing
Drilling
Anchorage
Excavation in Hard Rock
Drilling
Anchorage
Boring
Pile Foundation
Boring
Documents :
Tools:
1. EPM
Part A : To be followed by Partners
The Process starts after the TI has been completed.
Step1.
The Partner have to do the quality inspection of 100% of the sites as per the
applicable checklist for the project. TI & CW checklists attached.
Step2.
The Hardcopy of the filled checklist have to be submitted along with site
folder.
Step3.
A consolidated excel sheet of all the quality inspection checklist should be
mailed to Nokia by 20TH Of every month.
The Excel sheet should contain :
• Name of team leader of Installation team
• Name of Quality Inspector
• Timelines to rectify the deficiencies.
Part B : To be followed by NSN SE
After getting the checklist and consolidated excel sheet from all the partners
within agreed timeline. The Nokia SE should Inspect at least 10% of the
above sites.
Step1. Nokia SE should select the sites to inspect based on below guidelines.
Guidelines for selection of the sites
Every quarter the sites inspected should fulfill the following criteria's:
1. Vendor: Sites by all the vendors should be selected. Example: If there are
three vendors A, B and C. The sites selected should have sites from all A, B
and C in ratio of sites installed by them.
2. Equipment Type: Sites with all type of equipment should be selected.
Example: IF Ultra Indoor, Outdoor and Metro has been installed. The sites
selected should have sites with ultra site Indoor, Outdoor and Metro in
ratio of sites installed.
3. Type of Site: If there are types of site like RTT, GBT and IBS. Selected sites
should have RTT, GBT and IBS in ratio of sites installed.
These guidelines should be followed very religiously to give us a
Complete and True picture of the SQI.
Step2. After selection NSN SE should visit sites for quality inspection.
The previously submitted Quality report from subcon should be
taken for reference and verified as per the actual site. The
timelines given in the report should also be checked for
compliance. Difference in SQI between audits done by subcon and
Nokia SE should be escalated to top management.
Step3. NSN SE should fill his own checklist.
Step4. NSN SE should update the same in EPM under the quality
Assessment heading.
Action Plan
• Identify the resources from Project/O&M for Auditing 100% sites
• Indentify 3 best sites
• 1 RTT site
• 1 GBT site
• 1 Sharing site
• Conduct Workshops to make these resources ready for Audit
• Audit Report
• EPM Updation
Audit Process to start immediately the next day
after the training session.
. Vendors claiming the Bill will have to produce cleared site photograph for Bill
clearance. Compare these photograph with our record before clearing the
Bills.
• Every engineer inducted in the system with have a orientation program on
site process SQ, SQI and subsequent site visit before he is asked to handle site
development/audit independently.
• All the Quality reports will have to be accessible to Billing engineer for
reference and cross verification before clearing the bill.
• One cluster lead and One senior engineer will be nominated in each cluster
as mentor to the new Joiner.( Orientation is for Minimum 7 days).
• Engineers having less than 2 years of work experience will have to be
accompanied by senior members to conduct site Audit at least in 10 sites
before they are asked to handle independently.
• One Copy of the Rejected and Poor site quality report along with photograph
will be sent to respective vendors for rectification (Maximum 7 days given to
vendors for rectification work). This will be coordinated by the Central Site
Engineer with help of Cluster Leas, PC & PA for logistics support (Calling the
Vendors, Photocopying & Posting/Handover of document). Note:- Keep a
receipt of the document handed over to vendor.