The document presents a feasibility study for a proposed two-storey evacuation center in Brgy. Baracca Villasis, Pangasinan. Specifically:
1. Tropical Storm Pepeng caused massive flooding in Villasis 9 years ago, damaging infrastructure and agriculture. The existing gymnasium evacuation center also flooded. A new elevated center is proposed to accommodate more people.
2. The proposed Villasis Evacuation Center will provide temporary emergency shelter before disasters and accommodate vulnerable communities for a few hours to days. It will be funded by the local government.
3. A technical, financial, management, and socio-economic analysis found the project feasible, as it will boost employment and living standards
Original Description:
Sample presentation for home for the aged feasibility study
The document presents a feasibility study for a proposed two-storey evacuation center in Brgy. Baracca Villasis, Pangasinan. Specifically:
1. Tropical Storm Pepeng caused massive flooding in Villasis 9 years ago, damaging infrastructure and agriculture. The existing gymnasium evacuation center also flooded. A new elevated center is proposed to accommodate more people.
2. The proposed Villasis Evacuation Center will provide temporary emergency shelter before disasters and accommodate vulnerable communities for a few hours to days. It will be funded by the local government.
3. A technical, financial, management, and socio-economic analysis found the project feasible, as it will boost employment and living standards
The document presents a feasibility study for a proposed two-storey evacuation center in Brgy. Baracca Villasis, Pangasinan. Specifically:
1. Tropical Storm Pepeng caused massive flooding in Villasis 9 years ago, damaging infrastructure and agriculture. The existing gymnasium evacuation center also flooded. A new elevated center is proposed to accommodate more people.
2. The proposed Villasis Evacuation Center will provide temporary emergency shelter before disasters and accommodate vulnerable communities for a few hours to days. It will be funded by the local government.
3. A technical, financial, management, and socio-economic analysis found the project feasible, as it will boost employment and living standards
IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF BACHELOR OF SCIENCE IN CIVIL ENGINEERING
A FEASIBILITY STUDY OF A PROPOSED TWO- STOREY EVACUATION CENTER IN BRGY. BARACCA VILLASIS, PANGASINAN
PRESENTED BY:
BAYYA, CHRISTIAN V. ILDEFONSO, JEFFERSON A. BSCE – 5A
ENGR. RESURRECCION V. GARROTE CONSULTANT BACKGROUND OF THE STUDY NINE YEARS AGO, ON OCTOBER 7TH, TROPICAL STORM "PEPENG" RAVAGE OUR PROVINCE (PANGASINAN), SUBMERGING AREAS LIKE VILLASIS IN FLOODS AND CAUSED ENORMOUS DAMAGES IN INFRASTRUCTURES, AND AGRICULTURE. RAIN AND WATER RELEASED FROM THE DAMS CAUSED WATER LEVEL TO RISE QUICKLY AND FLOODED EVEN THE GYMNASIUM WHICH SERVED AS EVACUATION CENTER . DUE TO THE SAID EVENT, WE'RE PROPOSING A NEW EVACUATION CENTER WITH ELEVATION AND INCREASE ITS CAPACITY TO ACCOMMODATE.
THE EVACUATION CENTER WILL PROVIDE SAFE EMERGENCY SHELTER
FOR A SHORT TIME BEFORE THE DISASTER STRIKES. IN PRINCIPLE, EVACUATION CENTERS WILL PROVIDE SAFE SHELTER TO COMMUNITIES AT POTENTIAL RISK OF DISASTER (CYCLONE, FLASH FLOOD, FIRE, ETC.). THE EVACUATION CENTER WILL PROVIDE LIFESAVING SHELTER TO AFFECTED OR VULNERABLE COMMUNITIES AND PEOPLE OF THE BARANGAY AND AT THE POINT ONSET OF NATURAL DISASTERS FOR A FEW HOURS TO A FEW DAYS.THE PROPOSED PROJECT WILL BE FUNDED BY THE LOCAL GOVERNMENT OF VILLASIS. PROJECT LOCATION TECHNICAL ASPECT SITE DEVELOPMENT PLAN VICINITY MAP GROUND FLOOR PLAN SECOND FLOOR PLAN FACADE RIGHT SIDE ELEVATION LEFT SIDE ELEVATION REAR ELEVATION SCOPE OF WORKS TOTAL PROJECT COST FINANCIAL ASPECT COST BENEFIT PRO-FORMA FINANCIAL ASPECT MANAGEMENT ASPECT DURING FEASIBILITY STUDY DURING CONSTRUCTION DURING OPERATION SOCIO-ECONOMIC ASPECT OVERALL BENEFIT • THE PROPOSED PROJECT WILL SHOULDER THE NEEDS OF THE RESIDENTS IN TIMES OF CALAMITIES AND OTHER DISASTERS. IT WILL HELP THE COMMUNITY TO HAVE A PLACE TO STAY RATHER THAN STAYING ON ROOFS OR LOITERING AT THE STREETS. INSTEAD, THEY WILL HAVE A SHELTER TO STOPOVER IN A CERTAIN PERIOD OF TIME. IT WILL ALSO PROVIDE HE NEEDS OF THE EVACUEES LIKE, A PLACE FOR THEIR FAMILY, MEDICAL CARE, AND OTHER NECESSITY NEEDS.
• THE EVACUATION CENTER WILL PROVIDE SAFE EMERGENCY
SHELTER FOR A SHORT TIME BEFORE THE DISASTER STRIKES. IN PRINCIPLE, EVACUATION CENTERS WILL PROVIDE SAFE SHELTER TO COMMUNITIES AT POTENTIAL RISK OF DISASTER (CYCLONE, FLASH FLOOD, FIRE, ETC.). EVACUATION CENTERS WILL PROVIDE LIFESAVING SHELTER TO IDPS/AFFECTED OR VULNERABLE COMMUNITIES AND AT THE POINT ONSET OF NATURAL DISASTERS FOR A FEW HOURS TO A FEW DAYS. • THE PROJECT WILL UPLIFT THE LIVING STANDARD AND LIFESTYLE OF THE PEOPLE IN THE BARANGAY, IN TERMS OF EMPLOYMENT AND FAST DEVELOPMENT OF LIVING CONDITIONS & EVEN IN TERMS OF FUTURE INDUSTRIAL AND COMMERCIAL DEVELOPMENT. THE WILL ENHANCE THE LIVES OF PEOPLE LIVING NEARBY IN TERMS OF HIGHER INCOME ACCUMULATED FROM EMPLOYMENT ON THE DEVELOPMENT AND MAINTENANCE OF THE BUILDING.
• THE ESTABLISHMENT WILL CHANGE THE PERSPECIVE OF
THE CONVENTIONAL EVACUATION AREA. THE PROPOSED PROJECT WILL ACCOMMODATE NOT ONLY THE NEEDS OF COMMUNITY IT WILL ALSO CATER THE NECESSITIES OF THE UNEMPLOYED INDIVIDUAL OF VILLASIS PANGASINAN. PROJECT SUMMARY A. NAME OF THE PROJECT
VILLASIS EVACUATION CENTER
THE PROPOSED PROJECT IS TO BE NAMED “VILLASIS EVACUATION CENTER”. IT IS OWNED BY THE GOVERNMENT UNDER THE SUPERVISON OF MUNICIPALITY OF VILLASIS.
B. LOCATION
BRGY. BARACCA VILLASIS, PANGASINAN
THE PROPOSED PROJECT IS TO BE LOCATED IN BRGY. BARACCA VILLASIS, PANGASINAN. IT IS BEST FITTED AS THE LOCATION BECAUSE IT IS LOCATED ON STABLE GEOTECHNICAL LAND, NOT SUBJECT TO POTENTIAL LANDSLIP OR EXPOSED TO POTENTIAL LANDSLIDES OF ADJACENT LAND; HAVE NO NEARBY LARGE TREES, STRUCTURES, POWER LINES (OR OTHER POTENTIAL HAZARDS) THAT MIGHT REPRESENT A THREAT; NOT BE CLOSE TO FACILITIES THAT MANUFACTURE, USE OR STORE HAZARDOUS MATERIALS; BE EASILY ACCESSIBLE BY VEHICLE AND FOOT, AND FOR THOSE WITH DISABILITY (FOR ALL TYPES OF A HAZARD EVENT, WHETHER CYCLONE, FLOODING OR TSUNAMI); AND HAS BEEN ASSESSED AS BEING FREE FROM NATURAL HAZARDS. C. DESCRIPTIVE DEFINITION OF THE PROJECT
EVACUATION CENTERS PLAY A FUNDAMENTAL ROLE
IN MANAGING THE IMPACTS OF A NATURAL DISASTER AND IN PROTECTING THE LIVES OF VULNERABLE COMMUNITIES AT RISK BEFORE SUCH A DISASTER. THE PROPOSED PROJECT WILL BE AN IMPROVED CYCLONE AND EARTHQUAKE RESISTANCE IN DESIGNS LOCATED AT BRGY. BARACCA VILLASIS PANGASINAN. D. PROJECT’S LONG-RANGE OBJECTIVES THIS PROJECT WILL SURELY UPLIFT THE LIVING STANDARD AND LIFESTYLE OF THE PEOPLE IN THE BARANGAY IN THE LONG RUN, IN TERMS OF EMPLOYMENT AND FAST DEVELOPMENT OF LIVING CONDITIONS & EVEN IN TERMS OF FUTURE INDUSTRIAL AND COMMERCIAL DEVELOPMENT. IN TEN YEARS, TIME, THE PROJECT IS EXPECTED TO ENHANCE THE LIVES OF PEOPLE LIVING NEARBY IN TERMS OF HIGHER INCOME ACCUMULATED FROM EMPLOYMENT ON THE DEVELOPMENT AND MAINTENANCE OF THE BUILDING. E. FEASIBILITY CRITERIA • ENVIRONMENTAL FACTOR, PUBLIC ASSISTANCE CONCERNS, AND ECONOMICAL IMPROVEMENT SPECIFICALLY TO THE RESIDENTS OF THE BARANGAY ARE THE SIGNIFICANT FACTORS CONSIDERED TO THE FEASIBILITY OF THIS PROPOSED PROJECT. IT IS PROFITABLE IN THE SENSE THAT IT WILL PROVIDE IMPROVEMENT TO THE LIFESTYLE SPECIALLY THE EMPLOYMENT OF THE PEOPLE DURING THE CONSTRUCTION AND IN THE DEVELOPMENT AND MAINTENANCE OF THE PROPOSED PROJECT ON THE SAID LOCATION.
• THE ABOVE SAID SIGNIFICANT FACTORS ARE THE BASIS THAT
THE PROPOSED PROJECT ISNDESIGNED WITH THE CONSIDERATIONS OF THE SOCIO – ECONOMIC ENVIRONMENT. SO, THE CONTRIBUTION TO SOCIO – ECONOMIC ENVIRONMENT IS SERIOUSLY CONSIDERED WHEN EVALUATING THIS STUDY. ALTHOUGH THE PROFITABILITY OF THE PROJECT IS GOOD, IT IS ONLY THE SECOND CONSIDERATION. F. HIGHLIGHTS OF THE PROJECT • PHILIPPINES EXPERIENCES AT LEAST 25 TYPHOONS IN A YEAR, AND THERE IS ALSO THE FACTOR OF POPULATION THAT IS RAPIDLY GROWING NOWADAYS AND THE NEEDS OF THE PEOPLE ARE ALSO INCREASING. THE PUBLIC IN NEED OF EVACUATION CENTER IS WAY UP TO THE LIMITS OF THE PRESENT FACILITY IN THE MUN ICIPALITY. OVERCROWDED CENTERS, LIMITED SPACES PER FAMILY, VIRUSES THAT ARE HURRIEDLY SPREADING AND MEDICAL ASSISTANCE ARE INSUFFICIENT TO THE EVACUEES.
• DUE TO LACK OF EQUIPMENT OF THE EVACUATION CENTERS AND MINIMAL SPACES OF THE FACILITY. IT IS HARD TO FIND A PLACE FOR THEM TO REST. THE RESIDENTS HAVE NO CHOICE BUT TO STAY IN THE ROOF OF THEIR HOUSES INSTEAD OF GOING TO EVACUATION AREAS. TO PREVENT SUCH CIRCUMSTANCES, AN EVACUATION CENTER IS DESIGNED MAINLY TO PROVIDE PROPER ASSISTANCE TO THE RESIDENTS OF THE MUNICIPALTY DURING CALAMITIES AND NATURAL DISASTERS.
• THE CONSTRUCTION PHASE WILL TAKE ABOUT ONE YEAR AND NINE MONTHS EXPECTED TO BE FULLY OPERATIONAL ON THE LAST QUARTER OF 2020.
• THE SOURCE OF FUND OF THE PROJECT WILL COME
FROM THE LOCAL GOVERNMENT UNIT FUNDS, AND WILL BE AIDED BY THE DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS FOR THE INFRASTRUCTURE DEVELOPMENT. THIS PROPOSED PROJECT OVERALL COST IS ₱46,167,820.53 INCLUDING ITS MATERIALS COST, LABOR COST, CONTRACTOR’S PROFIT, CONTINGENCY COST, TAXES, LAND COST, EQUIPMENT COST AND AMENITIES COST. MAJOR ASSUMPTIONS AND SUMMARY OF FINDINGS AND CONCLUSION
• TECHNICAL FEASIBILITY:
THE MATERIALS TO BE USED FOR THE CONSTRUCTION OF
EVACUATION CENTER SUCH AS SAND AND GRAVEL ARE READILY AVAILABLE WITHIN THE AREA. THE OTHER CONSTRUCTION MATERIALS ARE AVAILABLE AT SOME CONSTRUCTION SUPPLY AT THE TOWN PROPER OF VILLASIS AS WELL AS AT THE CITY OF URDANETA WHICH IS 8-9 KM AWAY FROM THE SITE. FOR THE MANPOWER, THERE ARE CONSIDERABLE NUMBER OF SKILLED AND UNSKILLED WORKERS AT THE AREA OF WHICH THEY COULD BE HIRED ON DAILY BASIS. PROFESSIONALS AND OTHER MANPOWER MAY BE HIRED WITHIN THE MUNICIPALITY OR AT NEARBY CITIES OR MUNICIPALITIES. • MANAGEMENT FEASIBILITY:
THE PROPOSED PROJECT WILL BE MANAGED BY
THE PROPONENTS, THE DEVELOPERS OF THE PROJECT AND WITH THE COOPERATION OF THE LOCAL GOVERNMENT UNIT OF THE VILLASIS. ALSO, DURING THE CONSTRUCTION, THE REQUIRED MANPOWER ARE AVAILABLE. THE SALARY RATE SHALL CONFORM TO THE SALARY STANDARD SET BY THE REGIONAL TRIPARTITE WAGE BOARD. • FINANCIAL FEASIBILITY:
THIS PROPOSED PROJECT OVERALL COST IS
₱46,167,820.53 INCLUDING ITS MATERIALS COST, LABOR COST, CONTRACTOR’S PROFIT, CONTINGENCY COST, TAXES, LAND COST, EQUIPMENT COST AND AMENITIES COST WHICH WILL BE FUNDED BY THE LOCAL GOVERNMENT UNIT, WITH THE AID OF DPWH. WITH A RETURN OF INVESTMENT (ROI) OF 10.225% AND A PAYBACK PERIOD OF 9.78 SAY 10 YEARS. • SOCIO-ECONOMIC FEASIBILITY:
THE PROJECT CONTRIBUTED IN THE
SOLUTION OF UNEMPLOYMENT PROBLEMS DURING ITS DEVELOPMENT, CONSTRUCTION AND OPERATION OF THIS PROPOSED PROJECT AND HELPS ALLEVIATE POVERTY IN THE MUNICIPALITY AND IN THE DIFFERENT BARANGAYS. CONCLUSION AND RECOMMENDATION THE PROPOSED VILLASIS EVACUATION CENTER IS HIGHLY RECOMMENDED AND VIABLE BASED ON ITS TECHNICAL, FINANCIAL AND SOCIO-ECONOMIC ASPECTS. THIS EVACUATION CENTER HAS A GREAT SOCIAL AND ECONOMIC BENEFITS TO THE BARANGAYS AS WELL AS TO THE NEARBY TOWNS THROUGH OPPORTUNITIES IT GIVES. THE NECESSITY OF THE CONSTRUCTION OF THE EVACUATION CENTER HAS BEEN POINTED OUT TO UPLIFT THE LIVING STANDARD AND LIFESTYLE OF THE RESIDENTS WITHIN THE AREA. IT IS IMPORTANT AND A MUST TO FOLLOW ALL THE REQUIRED PLANS ESPECIALLY FOR THE OPERATION FOR THE SAID PROJECT TO REACH ITS FUNCTIONS.