Construction of 220kV Gas Insulated Sub Station at Punjab University

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 32

Construction of 220kV Gas Insulated Sub

Station at Punjab University


Ishfaque Ali Shah (2183222)
Zafer Iqbal (2183185)
Initiation phase:-

BUSINESS CASE
The National Transmission Modernization I Project (NTMP-I) will be executed by National Transmission
and Despatch Company (NTDC). The objective of NTMP-I is to provide an immediate relief to the overall
NTDC transmission system under stress due to inadequate transformation capacity and to facilitate
evacuation of electricity from new generation facilities and from the regional power trading.
NTDC plans to build a new 220 kV GIS Grid Stations at Punjab University (PU) to improve the reliability of
transmission network and to provide relief to the 132 kV Grid Stations in Lahore Electric Supply Company
(LESCO). The scope of work of this sub-project includes: 220 kV GIS Grid Station at PU with three 220/132
kV; 150 MVA transformers along with allied equipment and accessories; and Two 220 kV Double Circuit
transmission lines (D/C T/L) on single Rail conductor for In/out of New Kot Lakh Pat (NKLP) Bund Road
D/C T/L (2+2 km). The interconnection with associated G/S and T/L will be carried out by LESCO with its
own resources.
Government of Pakistan, People of Lahore, NTDC, LESCO & World Bank are Stack holders
Initiation Phase:-

FEASIBILITY STUDY OF PROJECT


Initiation Phase:-

PROJECT CHARTER
 Construction of control Room Building.
 Construction of 220kV Gas Insulated Sub Station Indoor Switch Yard.
 Construction of 132kV 220kV Gas Insulated Sub Station Indoor Switch Yard.
 Construction of 3 No. Transformer Bays
 Installation of three 220/132 kV; 150 MVA transformers on Transformer Bay
 Two 220 kV Double Circuit transmission lines (Double Circuit Transmission Line D/C T/L) on single Rail
conductor for In/out of New Kot Lakh Pat (NKLP)-Bund Road D/C T/L (2+2 km).
 Testing & Commissioning (Synchronization with National Grid) of 220kV Gas Insulated Sub Station.
 Tree plantation across the transmission lines of 4kM & in the vicinity of 220KV Grid Station to save
environment.
Initiation phase:-

PROJECT OBJECTIVES
 Identify overall project objectives:

 Construction of 220kV Gas Insulated Sub Station with three 220/132kV, 150MVA Transformer

along with allied equipment and accessories and construction of Control room Building.

 Completion date is 30-06-2020

 The project should be completed with the budgeted cost $166 million funded $ 140 millions

by World bank and $ 26 millions NTDC.


Initiation Phase:-

Project Team Roles and Responsibilities


SDO-I
Installation of 220kV Switch
Yard

SDO-II
Xen Grid System
Staff Officer Installation of Grid System
Installation of 132kV Switch
Yard

Superintending Engineer EHV SDOIII


supervision of construction of Installation of Power
electrical system Transformer
Chief Engineer GSC, NTDC

Xen Transmission line SDO TLC


Project Manager

Installation of T/L Installation of T/L

SDO-I Civil
Superintending Engineer Civil Construction of T/L Civil Work
Xen Civil Works
supervision of construction of
Construction of Civil Works SDO-II Civil
civil works
Construction of Building
Wroks

Manger Finance
Deputy Manager Finance
Monitoring of financial Account Assistant
Execute financial activities
activities

Deputy Manager HR Assistant Manager HR


Responsible for management Responsible of management of Office Superintendent
of HR activities HR activities
Initiation phase:-

Establishing Project Office


For executing the project, the office is established on following address
 Project Office
Established at the office of Chief Engineer EHV NTDC, NTDC House Guru Mangat Rd,
Block A3, Gulberg, Lahore, Punjab.
Four Numbers are Office Room are allocated to the project with allied furniture and
office equipments.
Planning Phase:-

DEVELOPMENT OF PROJECT PLAN


Construction of new grid stations of 220 kV
 Land acquisition (locations have been broadly identified but the exact coordinates are not yet known will
be provided by Punjab University );
 Construction of Control Room building/structures;
 Installation of transformers and other equipment/ accessories; and
 Energization of grids.
Installation of feeding transmission lines
 Land acquisition on temporary basis;
 Excavation & foundation;
 Erection of towers; and
 Stringing of transmission lines
Planning Phase:-
Work Break Down Structure

Civil Works

Station with feeding Transmission


Construction of 220kV GIS Grid
Installation of GIS
Switch Yard

Installation of

Line
Power Transformers

Testing &
Commissioning Note: Each Activity
is further defined
Tree Plantation in next slides
Planning Phase:-
Work Break Down Structure
Construction of Control
Room Building

Construction Office
Building

CIVIL WORKS
Construction of
Transmission Tower
Foundation

Construction of
Transformers Bay

Construction of Boundary
wall
Planning Phase:-
Work Break Down Structure
Installation of
Instrument Transformer
Installation of GIS Switch Yard Construction of 220kV GIS
Switch Yard Installation of 220kV GIS
Bus Bar

Installation of 220kV
Circuit Breakers

Installation of 132kV
Instrument Transformer

Installation of 132kV GIS


Bus Bar
Construction of 220kV GIS
Switch Yard Installation of 132kV
Circuit Breakers
Planning Phase:-
Work Break Down Structure
Unloading

Instantion of power
Placement on Bay
transformer P-1

Installation of Power
HT/LT Connections

Transformer
Unloading

Instantion of power
Placement on Bay
transformer P-2

HT/LT Connections

Unloading

Instantion of power
Placement on Bay
transformer P-3

HT/LT Connections
Planning Phase:-
Work Break Down Structure
Testing of Power Transformers

Testing & Commissioning Testing of 220kV GIS Switch yard

Testing By 3rd Party Testing of 132kV Switch yard

Testing of Transmission Line

Testing of Power Transformers

Testing by NTDC Testing of 220kV GIS Switch yard

Testing of 132kV Switch yard

Testing of Transmission Line

Synchronization

Commissioning/Acceptance Closure of Circuit Breaker

Interlink with national Grid


Planning Phase:-
Work Break Down Structure

Tree Plantation across


Control Room

Tree Plantation
Tree Planation across
Office Building

Tree Planation across


Transmission Line
Planning Phase:-

RESOURCE PLAN
Testing &
Outside Manufacturin
People Equipment Commissionin
Services g
g

3*150MVA Power NESPAK GM (system


NTDC employees Transformers TEPC - Tianjin General Electric protection) NTDC
Contractor work GIS Bus Bar Electric Power Company
force GM (NPCC) NTDC
Construction TBEA Shenyang
Daily wages worker Circuit Breakers Northwest Electric
Company  Transformer
Current DESCON Siemens AG Power Design
Transformer Habib Rafiq ABB Ltd Institute Co.
Electric Towers Construction Ltd China

The Consultancy
services, Electrical
Man power is To Install the GIS Testing &
Substation, Equipment will be
provided by NTDC, equipment must be Commission must
transmission line & provided by above
Contractor and hire accordance to IEC be done according
Civil work must be mentioned
daily wages staff standard to IEC standards.
done through well companies
reputed companies
Planning Phase:-

PROJECT FINANCIAL PLAN


Project Cost (millions)
$120

$110

$100

$90
82
$80

$70

$60

$50

$40
30
$30

$20 17 15
$10 5 5 5
2 3 2
$-
Equipment & Land Salaries Civil works Inhabitant transportation Insurance Consultancy Training Enviroment
accessories Acqusition Resettlement fee upgradation
Planning Phase:-

PROJECT QUALITY PLAN


The following IEC standards and NTDC Design Specification must • IEC 66044-2 – Voltage transformers
be adopted to ensure quality and Safety of personnel &
equipments • IEC 60137 – Bushings for alternating voltages above

1000 V
IEC 62271-203 – Gas Insulated metal-enclosed switchgear for rated
voltages above 52KV. • IEC 60859 – Cable connections for gas-insulated
switchgear
 IEC 60376 – New sulphur hexafluoride
• IEC 60480 – Guide to checking of sulphur hexafluoride
 IEC 62271- 100 – High voltage alternating current Circuit breakers taken from electrical equipment
 IEC 60694 – Common clauses for high voltage Switchgear and • IEC 60099-1/4 – Non-linear resistor type arresters for
control-gear standards AC systems
 IEC 62271-102 – Alternating current disconnectors (isolators) and • IEC 60439 – Factory-built assemblies of low-voltage
earthing switches. switchgear and control gear.
 IEC 61128 – Alternating current disconnectors. Bus-transfer
• IEC 60427 – Report on synthetic testing of high-voltage
current switching by disconnectors. alternating current circuit breaker.

• IEEE 80 (2000) – IEEE Guide for Safety in AC Substation
IEC 61129 – Alternating current earthing switches. Induced current
switching grounding.
• NTDC Design Specification given
 IEC 66044-1 – Current transformers
Planning Phase:-

PROJECT RISK PLAN


Risk Worker Impact/Risk Project Impact/Risk Owner Mitigation Plan

Recruitment and
selection of workers
through adopting
process including:
- Company policy for
Perception of unfair recruitment
Recruitment and recruitment and Unpleasant work - Preference to local
selection of workers selection practices. environment, which NTDC (ESIC)/ citizens to avoid
may affect the project Contractor labour influx
- Child labour and activities. - Communication on
hiring criteria,
school drop-out minimum age, and
applicable laws
- Enforcement of
legislation on child
labour
Planning Phase:-

PROJECT RISK PLAN


Risk Worker Impact/Risk Project Impact/Risk Owner Mitigation Plan

Company policy needs


to include the
following:
Workers embark on - Effective grievance
various forms of redress process which
actions. should be gender
Labour relations Workers feel Workers take matters sensitive
(Conflict Handling) aggrieved and don’t into their own hands, NTDC (ESIC)/ - Disciplinary procedure
know how to vent which results violence Contractor - Workplace rules and
their grievances. and conflict that regulations
affects workplace - Demobilization
harmony procedure
- Effective Information
dissemination to
workers
Planning Phase:-

PROJECT RISK PLAN


Risk Probability Impact Owner Mitigation Plan

Insufficient security Ensure the camp


and control on security personnel
Inconsistent and security personnel, are:
aggressive behaviour which may lead - Adequately trained
of security personnel towards the in appropriate
towards workers can inappropriate use of conduct towards
Security result in tensions and force for protecting NTDC/ Contractor workers and
conflict at workplace project workers and community members
and a perception of assets, or - Exercising constraint
human rights inappropriate and caution and
affected. behaviour resulting in understand how force
human rights claims may be used.
.
Planning Phase:-

PROJECT TIME SCHEDULE

Land Acquisition Civil works Electrical Installation Testing &


• 30.09.2019` • 31.03.2020 • 30.09.2020 Commissioning
• 31.12.2020
Planning Phase:-

PROJECT ACCEPTANCE PLAN


 Project will be accepted when the 220kV GIS Grid station successfully synchronized
with National Grid after proper Testing carried out by System protection NTDC.
Planning Phase:-

PROJECT COMMUNICATION PLAN


 The corresponding will only be carried out on proper way through the paper and email
and address to the Project Director on the following address
Project Director/ Chief Engineer EHV
GSC house NTDC
Guru Mangat Road, Lahore.
Planning Phase:-

PROJECT PROCUREMENT PLAN


 All Procurement should be made through proper bidding and according to PPRA rules
& Regulation.
 Procurement contract will only be awarded to eligible and registered firms under
Pakistan Engineering Council & SECP
Execution Phase:-

EXECUTION
 The construction of Office Building, Office Control Room, Boundary wall & Foundation
of Transmission Lines will be carried out by “Habib Rafiq Construction Company”
 The Electrical Installation of 220kV GIS switch Yard and 132kV Switch yard will be
carried out by TEPC - Tianjin Electric Power Construction Company 
 The Installation of 3 No. 150 MVA power Transformer will be done by TBEA Shenyang
Transformer
 The Construction of Power Transmission Line will be done by DESCON.
Execution Phase:-

MONITORING & CONTROL


 The Project will be the monitored by Project Director.
 Project Director is responsible to submit progress report on weekly basis to the
management of NTDC and MD NTDC will review the progress.
 GM Planning NTDC and GM design NTDC will carried out inspection of project on
fortnight basis.
 GM system protection NTDC is responsible for conducting routine testing and
commissioning and is also responsible of proper synchronization with national Grid
System.
 The NESPAK is appointed as consultant to monitor the specification of electrical and
civil works according to NTDC Design and IEC Standards.
Closure Phase:-

CLOUSRE
 Project will close when 220kV GIS Grid Station is successfully synchronized with the
national Grid.
 All the contract will be cancelled after successfully commissioning of 220kV GIS Grid
Station.
 The supplier will be responsible for proper functioning of all electrical system under
warranty clause.
 Site office will be dismantled.
 Project office will be disposed off