Construction of 220kV Gas Insulated Sub Station at Punjab University
Construction of 220kV Gas Insulated Sub Station at Punjab University
Construction of 220kV Gas Insulated Sub Station at Punjab University
BUSINESS CASE
The National Transmission Modernization I Project (NTMP-I) will be executed by National Transmission
and Despatch Company (NTDC). The objective of NTMP-I is to provide an immediate relief to the overall
NTDC transmission system under stress due to inadequate transformation capacity and to facilitate
evacuation of electricity from new generation facilities and from the regional power trading.
NTDC plans to build a new 220 kV GIS Grid Stations at Punjab University (PU) to improve the reliability of
transmission network and to provide relief to the 132 kV Grid Stations in Lahore Electric Supply Company
(LESCO). The scope of work of this sub-project includes: 220 kV GIS Grid Station at PU with three 220/132
kV; 150 MVA transformers along with allied equipment and accessories; and Two 220 kV Double Circuit
transmission lines (D/C T/L) on single Rail conductor for In/out of New Kot Lakh Pat (NKLP) Bund Road
D/C T/L (2+2 km). The interconnection with associated G/S and T/L will be carried out by LESCO with its
own resources.
Government of Pakistan, People of Lahore, NTDC, LESCO & World Bank are Stack holders
Initiation Phase:-
PROJECT CHARTER
Construction of control Room Building.
Construction of 220kV Gas Insulated Sub Station Indoor Switch Yard.
Construction of 132kV 220kV Gas Insulated Sub Station Indoor Switch Yard.
Construction of 3 No. Transformer Bays
Installation of three 220/132 kV; 150 MVA transformers on Transformer Bay
Two 220 kV Double Circuit transmission lines (Double Circuit Transmission Line D/C T/L) on single Rail
conductor for In/out of New Kot Lakh Pat (NKLP)-Bund Road D/C T/L (2+2 km).
Testing & Commissioning (Synchronization with National Grid) of 220kV Gas Insulated Sub Station.
Tree plantation across the transmission lines of 4kM & in the vicinity of 220KV Grid Station to save
environment.
Initiation phase:-
PROJECT OBJECTIVES
Identify overall project objectives:
Construction of 220kV Gas Insulated Sub Station with three 220/132kV, 150MVA Transformer
along with allied equipment and accessories and construction of Control room Building.
The project should be completed with the budgeted cost $166 million funded $ 140 millions
SDO-II
Xen Grid System
Staff Officer Installation of Grid System
Installation of 132kV Switch
Yard
SDO-I Civil
Superintending Engineer Civil Construction of T/L Civil Work
Xen Civil Works
supervision of construction of
Construction of Civil Works SDO-II Civil
civil works
Construction of Building
Wroks
Manger Finance
Deputy Manager Finance
Monitoring of financial Account Assistant
Execute financial activities
activities
Civil Works
Installation of
Line
Power Transformers
Testing &
Commissioning Note: Each Activity
is further defined
Tree Plantation in next slides
Planning Phase:-
Work Break Down Structure
Construction of Control
Room Building
Construction Office
Building
CIVIL WORKS
Construction of
Transmission Tower
Foundation
Construction of
Transformers Bay
Construction of Boundary
wall
Planning Phase:-
Work Break Down Structure
Installation of
Instrument Transformer
Installation of GIS Switch Yard Construction of 220kV GIS
Switch Yard Installation of 220kV GIS
Bus Bar
Installation of 220kV
Circuit Breakers
Installation of 132kV
Instrument Transformer
Instantion of power
Placement on Bay
transformer P-1
Installation of Power
HT/LT Connections
Transformer
Unloading
Instantion of power
Placement on Bay
transformer P-2
HT/LT Connections
Unloading
Instantion of power
Placement on Bay
transformer P-3
HT/LT Connections
Planning Phase:-
Work Break Down Structure
Testing of Power Transformers
Synchronization
Tree Plantation
Tree Planation across
Office Building
RESOURCE PLAN
Testing &
Outside Manufacturin
People Equipment Commissionin
Services g
g
The Consultancy
services, Electrical
Man power is To Install the GIS Testing &
Substation, Equipment will be
provided by NTDC, equipment must be Commission must
transmission line & provided by above
Contractor and hire accordance to IEC be done according
Civil work must be mentioned
daily wages staff standard to IEC standards.
done through well companies
reputed companies
Planning Phase:-
$110
$100
$90
82
$80
$70
$60
$50
$40
30
$30
$20 17 15
$10 5 5 5
2 3 2
$-
Equipment & Land Salaries Civil works Inhabitant transportation Insurance Consultancy Training Enviroment
accessories Acqusition Resettlement fee upgradation
Planning Phase:-
Recruitment and
selection of workers
through adopting
process including:
- Company policy for
Perception of unfair recruitment
Recruitment and recruitment and Unpleasant work - Preference to local
selection of workers selection practices. environment, which NTDC (ESIC)/ citizens to avoid
may affect the project Contractor labour influx
- Child labour and activities. - Communication on
hiring criteria,
school drop-out minimum age, and
applicable laws
- Enforcement of
legislation on child
labour
Planning Phase:-
EXECUTION
The construction of Office Building, Office Control Room, Boundary wall & Foundation
of Transmission Lines will be carried out by “Habib Rafiq Construction Company”
The Electrical Installation of 220kV GIS switch Yard and 132kV Switch yard will be
carried out by TEPC - Tianjin Electric Power Construction Company
The Installation of 3 No. 150 MVA power Transformer will be done by TBEA Shenyang
Transformer
The Construction of Power Transmission Line will be done by DESCON.
Execution Phase:-
CLOUSRE
Project will close when 220kV GIS Grid Station is successfully synchronized with the
national Grid.
All the contract will be cancelled after successfully commissioning of 220kV GIS Grid
Station.
The supplier will be responsible for proper functioning of all electrical system under
warranty clause.
Site office will be dismantled.
Project office will be disposed off
Thank You