Project Management

2 Storey Residence
1 A. MOBILIZATION

2 B. EARTHWORK

3 C. FORMWORK

4 D. CONCRETING

5 E. MASONRY WORK

6 F. ROUGHING-IN

7 G. ROOF FRAMING

8 H. ROOFING

9 I. PLUMBING

10 J. ELECTRICAL WORKS

11 K. CARPENTRY

12 L. FABRICATION OF MATERIALS

13 M. INSTALLATION OF DOORS & WNDW

14 N. PLUMBING FIXTURES & ACCESSORIES

15 O. TILE WORKS &SPECIAL FINISHES

16 P. PAINTING

17 Q. DEMOBILIZATION
A. Mobilization ( 1
week )
B. Earthwork ( 1.5 week )
C. Formwork ( 2 week )
D. Concreting ( 6 week )
E. Masonry Work ( 1.5
week )
F. Roughing In ( 1 week )
G. Roof Framing ( 2
week )
H. Roofing ( 2 week )
I. Plumbing ( 1.5 week )
J. Electric Work ( 1
week )
K. Carpentry ( 2 week )
L. Pre-Fabricated Matls
( 2 week )

M. Door and Windows


Installation ( 1.5 week )
N. Plumbing Fixtures and
Accessories ( 1 week )
O. Tile Works & Special
Finishes ( 2 week )
P. Painting ( 2.5 week )

Q. Demobilization and Site Clearing ( 1 week )


ACTIVITY DESCRIPTION IMMEDIATE PREDECESSOR DURATION COSTING
NO. (IN WEEKS) (PESO)

1 A. MOBILIZATION - 1 15K

2 B. EARTHWORK A 1½ 55K

3 C. FORMWORK B 2 60K

4 D. CONCRETING C 6 120K

5 E. MASONRY WORK D 1½ 30K

6 F. ROUGHING-IN D 1 35K

7 G. ROOF FRAMING E,F 2 70K

8 H. ROOFING G 2 120K

9 I. PLUMBING H 1½ 35K

10 J. ELECTRICAL WORKS H 1 40K

11 K. CARPENTRY I,J 2 65K

12 L. FABRICATION OF MATERIALS I,J 1½ 70K

13 M. INSTALLATION OF DOORS & WNDW I,J 1½ 60K

14 N. PLUMBING FIXTURES & ACCESSORIES K,L,M 1 35K

15 O. TILE WORKS &SPECIAL FINISHES N 2 150K

16 P. PAINTING O 2½ 100K

17 Q. DEMOBILIZATION Q 1 10K
E
5
1.5
A B C D G
START 1 2 3 4 7
1 1.5 2 6 2
F
6
1

I K
9 11
1.5 2
H L N O P Q
2
8 1.5 12 14 15 16 17 FIN.
1 2 2.5 1
J M
10 13
1 1.5

CRITICAL PATH=26 weeks