10-5 YEARS 1-5 YEARS: Real Time 15 MT Blocks Week To Day Ahead
10-5 YEARS 1-5 YEARS: Real Time 15 MT Blocks Week To Day Ahead
MARKET
TIME LINE
Capacity charges
Energy charges
3
SCHEDULING
1000
Forecast ex-bus capability of Power Plant
900
Net Injection Schedule
800
700
MW
600
500
SEB - A's Entitlement - (40% )
400
SEB - A's Requisition
300
200
100
0
0 2 4 6 8 10 12 14 16 18 20 22 24
Hours 4
CAPACITY CHARGE
7
UNSCHEDULED INTERCHANGE (U I)
:
8
UI RATE
650
600 Rate of Unscheduled Drawal/Injection
Below 49.0 Hz UI rate =570 p/u Frequency Rate
550
(Hz) (p/u)
500
Above 50.5 0
450 50.0 150
UI rate ----------------->
Frequency ----------->
9
AVAILABILITY BASED TARIFF
(A) CAPACITY CHARGE
(B) ENERGY CHARGE
(C) ADJUSTMENT FOR DEVIATIONS
(U I CHARGE)
(A) = a function of the Ex-Bus MW
availability of Power Plant for the day
declared before the day starts x
SEB’s % allocation from the plant
(B) = MWh for the day as per Ex-Bus drawal
schedule for the SEB finalised before
the day starts x Energy charge rate
(C) = Σ (Actual energy interchange in a 15
minute time block – scheduled energy
interchange for the time block) x UI rate10
FEATURES :
(A) and (B) do not depend on actual plant
generation / drawal. No metering required
for this as they are based on off-line
figures. All deviations taken care of by (C)