Organization Method Procedure Finance
Organization Method Procedure Finance
Organization Method Procedure Finance
Method
Procedure
Finance
Organization
Ministry Of Construction
DHSHD
Working Committee
Design & Planning (Surbana)
Developer / Contractor
Piling
Super Structure
Piling & Super Structure
Piling , Super Structure & Precast
Q.C
Survey
Method
Foundation : Bored Piling
Super Structure : Semi Precast
Non Structural Member : Precast
Structural Member : Cast in Situ
Water Supply- Temporary, Permanent
Electricity - Temporary, Permanent
Procedure
Soil Test N Value
Pile Loading Test: Static , Dynamic
Revised Designed By Vector
Piling
Driving Pile
-Drive By Hammer (Precast Pile, H Beam)
-Checked Working Load By Graph L By L
- Welded Joint
Pressed Pile
-Drive By Hydraulic Pressure (Precast Pile, H Beam)
-Checked Working Load By Pressure Gauge L By L
- Welded Joint
Bored Pile
-Drive By Drilling Rig (Cast in Situ)
-Design Depth Calculated From Soil Data
Drilling Rig (Machine)
Auger
Stand Pipe
Service Crane
Bentonite
Pile Break Above
Cut Off Point
Precast
Work Place Shift to Ground
Safety
Time Save
Workability
Man Power Reduce
Quality
Machinery
Management
Skilled Labour
Outline
Prestressed Plank
Façade Wall
Staircase Flight
Refuse Chute
Infill Wall
Beam Clad
Type of Precast Component Used
Precast Staircase
• POST-POUR ACTIVITIES
Prestressed Plank
Pre-pour activities
Apply mould oil
Check Plank Dimensions
Lay Strands
Stress Strands To Nomial Force (Initial)
Stress Strands To Specified Stress Force (Final)
Check Strand Elongation
Calculation Of Strand Elongation (By Precaster)
Lay meshes
Pre-pour Inspection Form
Concreting
• Pre-Pour Activities
• Apply Mould Oil
• Check Plank Dimesions (Check By RTO)
• Lay Strands
• Sterss Strands to Nominal Force (Initial)
• Sterss Strands to Nominal Force=120kg/cm
• Sterss Strands to Specified Stress Force (Final)
• Sterss Strands to Specified Stress Force =245kg/cm2
• Check Strand Elongation (368mm to 405mm) (Check By RTO)
• Calculation Of Strand Elongation (By Precaster)
Pre-Pour Activities
Mould Preparation
Install Reinforcement
Formwork Closing
Concreting
Post-Pour Activities
Early Strength Concrete Cube test results
Demoulding
Storage
Check Pre-delivery Strength >=30MPa
Pre-delivery Checks
Pre-delivery Inspection Form
• Mould Preparation ( Check By RTO )
• Install Reinforcement (Check By RTO)
• Formwork Closing
• Demoulding
• Infill Wall
Pre-Pour Activities
Mould Preparation
Install Reinforcement
Formwork Closing
Post-Pour Activities
Early Strength Concrete Cube test results
Demoulding
Storage
Check Pre-delivery Strength >=30MPa
Pre-delivery Checks
Pre-delivery Inspection Form
• Resident Engineer (R.E)
Check Methods Of Statements By Precaster
Check Demonstration Once For Every
Components Production
• Resident Technical Officer (R.T.O)
Pre-pour activities
Check Mould Dimensions, Line ,Shapes, Maintain
Rigid
Strands Elongation
Check Reinforcements and Cast-in Items As Per Shop
Drawing
Post-pour activities
Check Early Strength For Demoulding
Check 3 Days Strength, Physical Appearances Of
Members For Delivery
• Safety
Take Care On
Climbing Up Above 1.5m
Wet Places
Sharp Materials
Machine ( Gantry Crane, Truck, Trailer)
Electric Wire
Fire Exit
Emergency Assembly,
Machinery Calibration Every 6 Months