Professional Documents
Culture Documents
Course No. 10109 By-T.Vijayakumar Axen/Fbw/Ajj, S. Rly S.Arumugam Arulappan Axen/Cn/Tbm, S.Rly H.S.Saxena, Axen (Con) /CCG, W. Rly
Course No. 10109 By-T.Vijayakumar Axen/Fbw/Ajj, S. Rly S.Arumugam Arulappan Axen/Cn/Tbm, S.Rly H.S.Saxena, Axen (Con) /CCG, W. Rly
on
By-
T.VIJAYAKUMAR AXEN/FBW/AJJ, S. RLY
S.ARUMUGAM ARULAPPAN AXEN/CN/TBM, S.RLY
H.S.SAXENA, AXEN(CON)/CCG, W. RLY
Acknowledgement
We are grateful to –
5
INSPECTION OF WELDED TYPE
GIRDERS
INSPECTION BEFORE WELDING
6
INSPECTION BEFORE
WELDING
Inspection of raw steel and its conformation to IS : 2062 Gr. ‘B’
killed and normalised variety for plates over 12 mm thick.
For plates of 10 mm and 12 mm thick, the condition of
normalisation is not necessary.
In the absence of SAIL or Mill certificate, samples of plates with
code no. are being tested at ACMT/LAB/EWS/AJJ.
Preparation of welding procedures specification sheets for various
welds involved in the fabrication of a particular span.
Welding procedure qualification records and approval of welders
are to be taken up after the approval of WPSS is received. (Ref.
IS - 7307 part I and IS – 7310 part I).
Whether welding consumables are of the brands as per the latest
instructions received from RDSO, as supplemented to IRS-M.28
and IRS-M.39.
Transferring of cast number to cut pieces from parent metal.
7
INSPECTION DURING WELDING
Checking whether approved welding consumables are used by
the welders.
Checking whether the approved welders do the weld.
Checking the approved parameters for welding is being
employed and are being recorded in the register.
Checking for any distortions and suggesting methods to
minimize them.
Marking defects etc observed during the inspection for
rectification.
Attempts to make I-section or any other member is permitted
only after passing Radiographic Test on the Butt welded joint.
8
INSPECTION AFTER WELDING
The fillet welds are checked by visual and
Dye-penetrant test.
Defects noticed are to be rectified and details
are recorded.
Etching tests.
Radiographic film test.
9
VISUAL INSPECTION
The finished welds shall be visually inspected and shall conform
to the size and contour specified in the drawing.
The following types of defects can be detected during visual
inspection.
– Weld defects at the surface such as blow holes, pipes,
exposed porosity, exposed inclusions, etc.
– Surface cracks in the weld metal or in the parent metal
adjacent to it.
– Damage to the parent metal such as undercut, burning,
overheating, etc.
– Profile defects such as excessive convexity, concavity or
unequal leg lengths etc.
– Incorrect finish, uneven welds, spatter, etc.
10
DYE PENETRANT TEST
In the dye or liquid penetrant testing, a suitable liquid penetrant
is applied to the surface of the portion under examination and
remains there for a sufficient time to allow the liquid in to any
defect open at the surface.
After the penetration time, the excess penetrant which remains on
the surface is removed.
Then, a light color absorbent called developer is applied on the
surface.
This developer acting as a blotter draws out a portion of
penetrant which had earlier seeped in to the surface opening.
As the penetrant is drawn out, it diffuses in to the coating of the
developer forming the indication of the surface discontinuities as a
flaws.
11
Defects noticed in D.P. Blow hole After rectification of
Test ( Enlarged view ) defects
12
ETCHING TESTS
Etching tests on run-off coupons and at the
edges of girders for checking the root
fusion and throat length.
Etching tests are conducted on smooth,
clean surface by –
14
NUMBERING OF PANEL
POINTS
16
CAMBER IN STEEL GIRDER – Contd..
Steel triangulated (open web) girders are provided
with camber to compensate the deflection under
load.
Out of the total design camber, the part
corresponding to dead load is called dead load
camber.
The balance is called live load camber which should
be available as visible and measurable camber in the
girder when not carrying the live load
17
MAIN COMPONENTS OF
OPEN WEB GIRDER
PRIMARY MEMBERS
SECONDARY MEMBERS
18
19
PRIMARY MEMBERS
Bottom chord
Top chord
End Rakers
Diagonals
Vertical members
Floor system
– Cross girders
– Rail bearers or stringers
20
SECONDARY MEMBERS
Bottom lateral bracings
Top lateral bracings
Sway bracings and knee sway
Portal bracings and knee portal
Corner brackets
End stools and end bracket
Main gussets
Bearings
21
BOTTOM CHORD
22
TOP CHORD
23
END RAKERS
24
DIAGONALS
25
VERTICAL MEMBERS
26
FLOOR SYSTEM – CROSS GIRDERS
27
FLOOR SYSTEM –
RAIL BEARERS OR STRINGERS
28
TRIAL ASSEMBLY AT THE
WORKSHOPS
Erection facilities
Assembly
Camber measurement
29
SELECTION OF ASSEMBLY SITE
30
ERECTION FACILITIES
31
ASSEMBLY
The bed for assembly was made with ISMB 400
mm and packing plates about 200mm to facilitate
assembly.
The bed was checked and leveled with water level.
32
Contd..
• Bottom chords 2 nos. were
laid from one end with
bottom gussets and the cross
girders assembled in between
bottom chords, also stringers
in between cross girders.
Contd..
Black bolts 50 % and
drifts 50 % are used
for connecting the
joints. (In fields 40
% holes filled with
drifts and remaining
with black bolts as
per manuals.)
Contd..
Similarly the successive
bottom chords were laid with
cross girders and stringers.
Bottom laterals were
assembled in position.
The cross measurement and
diagonal measurements
checked and tightened all the
black bolts.
Insert the camber jacks over
platform below every bottom
panel joints in such away that
all the joints are in run out
condition except central jack.
Contd..
Levels were taken at top of bottom
chord at every nodal joint
36
Contd..
Provide camber to all panel joints of bottom chords as per camber
diagram by lowering the jacks at the ends, keeping central jacks with
out disturbing.
37
contd
Top chord members are to be elastically strained, so that erected
from centre to outwards.
Temporary gussets were replaced with permanent gussets before
drifting.
Drifts are driven with hammer, check for trueness of holes in the
adjacent group holes.
Care should be taken so that holes are not damaged.( elongated or
teared).
Contd..
5 Ton Pulley block was used for
assembling the members to keep the
joint in position.
End Rakers were erected in the last, the
upper end was first connected and
drifted, then connection was made at
lower end.
Sway bracings, top laterals bracings
and portal bracing were erected
subsequently.
All joints were tightened and drifted.
39
Contd..
Lowered the jacks duly keeping the
end supports in position.
Dead load camber was checked by
leveling instrument, also with water
level. The measurements recorded as
L1-11 mm (13.1 mm) , L2- 22 mm
(21.0 mm) , L3- 26 mm (26.3 mm) ,L4-
22 mm (21.0 mm) and L5- 10 mm
(13.1 mm).
COST OF THE GIRDER (Per MT)
Revenue Rate Foreign Rly. Rate
Home Rly. Rate