Professional Documents
Culture Documents
DS Lecture 3 - PERT CPM
DS Lecture 3 - PERT CPM
DS Lecture 3 - PERT CPM
8
PERT/CPM – 3 Aspects
1.Project Scheduling with known
Activity Times
9
Project Scheduling with known Activity
Times – Case Study
○ The owner of the Western Hills Shopping
Center is planning to modernize and
expand the current 32-business shopping
center complex. The project is expected
to provide room for 8 to 10 new
businesses. Financing has been arranged
through a private investor. All that
remains is for the owner of the shopping
center to plan, schedule, and complete
the expansion project.
10
List of Activities for the Western Hills
Shopping Center Project
Activity Immediate Activity
Activity Description Predecessor Time .
A. Prepare architectural
drawings — 5
B Identify potential new tenants — 6
C Develop prospectus for tenants A 4
D Select contractor A 3
E Prepare building permits A 1
F Obtain approval for building permits E 4
G Perform construction D, F 14
H Finalize contracts with tenants B, C 12
I Tenants move in G.H 2
NOTE:
Total 51
• 9 Activities are described and denoted A – I
• The Table shows the Immediate Predecessor(s)
• The Activity time for each activity 11
List of Activities for the Western
Hills Shopping Center Project
Activity Immediate Activity
Activity Description Predecessor Time .
A. Prepare
architectural drawings — 5
B Identify potential new tenants — 6
C Develop prospectus for tenants A 4
D Select contractor A 3
E Prepare building permits A 1
F Obtain approval for building permits E 4
G Perform construction D, F 14
NOTE: H Finalize contracts with tenants B, C 12
I Tenants move in G.H 2
• For a given activity, the Intermediate Total Predecessor51 column
identifies the activities that must be completed immediately
prior to the start of that activity.
• Activity A and B do not have Immediate Predecessors and
can be started as soon as the project begins, thus a dash (-)
is entered in the Intermediate Predecessor column for these
activities. 12
List of Activities for the Western
Hills Shopping Center Project
Activity Immediate Activity
Activity Description Predecessor Time .
A. Prepare architectural drawings
— 5
B Identify potential new tenants — 6
C Develop prospectus for tenants A 4
D Select contractor A 3
E Prepare building permits A 1
F Obtain approval for building permits E 4
G Perform construction D, F 14
H Finalize contracts with tenants B, C 12
I Tenants move in G.H 2
NOTE: Total 51
D
G
A Select
Construction
Prepare Contractor
Drawings
I
H
Start C
Develop
Finalize Tenant
Contracts
Tenants Move in
Finish
Prospectus
B
Identify new
Tenants
16
Activity Immediate Activity
Activity Description Predecessor Time .
A. Prepare architectural drawings
— 5
B Identify
potential new tenants — 6
C Developprospectus for tenants A 4
D Select contractor A 3
E Prepare building permits A 1
F Obtain approval for building permits E 4
G Perform construction D, F 14
H Finalize contracts with tenants B, C 12
I Tenants move in E G.H 2 F
Prepare ObtainTotal
Approval 51
Permits
A D
G
Prepare Select
Construction
Drawings Contractor
I
H
Start C
Develop
Finalize Tenant
Contracts
Tenants Move in
Finish
Prospectus
B
Identify new
Tenants
17
THE CRITICAL PATH
○ To determine the project completion time, we
have to analyze the network and identify the
CRITICAL PATH for the network
○ A PATH is a sequence of connected nodes that
leads from the START NODE to the FINISH
NODE. E.G. A-E-F-G-H-I. Other PATHS are
possible.
○ All paths in the network must be traversed in
order to complete the project.
○ NB. The longest path determines the total time
required to complete the project.
E F
Prepare Obtain Approval
Permits
A D
G
Prepare Select
Construction
Drawings Contractor
I
H
Start C
Develop
Finalize Tenant
Contracts
Tenants Move in
Finish
Prospectus
B
Identify new
Tenants
19
Western Hills Shopping Center Project Network
with Activity Times
E
F
1 4
A D G
5 3 14
Star
t C H I Finish
4 12 2
6 20
THE CRITICAL PATH – 3 steps
3.SLACK
21
Determining the Critical Path – the
FORWARD PASS through the network
22
Determining the Critical Path
- Earliest Start & Finish Times
○ The earliest start and earliest finish
times are written in the nodes to
the right of the activity
Earliest Finish
Earliest start Time
time
Activity A 0 5
Activity Time
5
23
Determining the Critical Path
- Earliest Start & Finish Times
Start
C H
4 12
B 0 6
6
Earliest Finish
Earliest Time
start time
25
Determining the Critical Path – FORWARD PASS
- Earliest Start & Finish Times For Activity H
Earliest
start time
A 0 5 Earliest Finish
Time for activity C
5 is 9
Start
C 5 9 H
4 12
Earliest
start time
A 0 5 Earliest Finish
Time for activity C
5 is 9
Start
C 5 9 H 9 21
4 12
E 5 6 F 6 10
1 4
A 0 5 D 5 8 G 10 24
5 3 14
Star
t C 5 9 H 9 21 I 24 26
Finis
4 12 2
h
B 0 6
6
28
Determining the Critical Path – FORWARD PASS
- Earliest Start & Finish Times For all Activities
Activity I 24 26
2 24 26
Activity Time
Latest start time Latest Finish Time
31
Determining the Critical Path – the BACKWARD
PASS through the network
32
BACKWARD PASS through the network – The
Latest Start and Latest Finish Times
E 5 6 F 6 10
1 4
A 0 5 D 5 8 G 10 24
5 3 14
Star
t C 5 9 H 9 21 I 24 26
Finish
4 12 2 24 26
B 0 6
6
33
BACKWARD PASS through the network –
The Latest Start and Latest Finish Times
E 5 6 F 6 10
1 5 6 4 6 10
A 0 5 D 5 8 G 10 24
5 0 5 3 7 10 14 10 24
Star
t C 5 9 H 9 21 I 24 26
Finis
4 8 12 12 12 24 2 24 26
h
B 0 6
6 6 12
34
Determining the Critical Path – STEP 3 - SLACK
1 5 6 4 6 10
A 0 5 D 5 8 G 10 24
5 0 5 3 7 10 14 10 24
Star
t C 5 9 H 9 21 I 24 26
Finish
4 8 12 12 12 24 2 24 26
B 0 6
6 6 12
37
THE CRITICAL PATH: A-E-F-G-I
E
F
Prepare
Obtain Approval
Permits
A D
G
Prepare Select
Construction
Drawings Contractor
Start C
H
Finalize Tenant
Tenants Move in Finish
Develop
Contracts
Prospectus
B
Identify new
Tenants
38
CONTRIBUTIONS OF PERT/CPM ANSWER TO THE
QUESTIONS POSED AT THE START
40
Program Evaluation & Review
Technique/Critical Path Method
(PERT/CPM) Final Words.
○ Although larger projects may increase
substantially the time required to make the
necessary calculations, the procedure and
contributions of PERT/CPM to larger projects are
identical to those for the shopping center
expansion project. Furthermore, computer
packages may be used to carry out the steps of
the PERT/CPM procedure
41
Program Evaluation & Review
Technique/Critical Path Method
(PERT/CPM) Final Words.
○ The activity schedule for the shopping center
expansion project was also developed by The
Management Scientist software package. Input
to the program included the activities, their
immediate predecessors, and the expected
activity times. Only a few minutes were required
to input the information and generate the
critical path and activity schedule.
42
PROJECT SCHEDULING WITH
UNCERTAIN ACTIVITY TIMES
43
PROJECT SCHEDULING WITH
UNCERTAIN ACTIVITY TIMES
44
PROJECT SCHEDULING WITH
UNCERTAIN ACTIVITY TIMES
45
PROJECT SCHEDULING WITH
UNCERTAIN ACTIVITY TIMES – 3
Time Estimates.
46
Calculation of the Expected Timer (t)
from the 3 Time Estimates .
○ FORMULA
t = a + 4m + b
6
47
Calculation of the Expected Timer (t) from the 3 Time
Estimates
Activity Optimistic Most Pessimistic Expected Time
(a) Probable (m) (b) t = a + 4m + b
6
A -- 4 5 12 6
B -- 1 1.5 5 2
C A 2 3 4 3
D A 3 4 11 5
E A 2 3 4 3
F C 1.5 2 2.5 2
G D 1.5 3 4.5 3
H B,E 2.5 3.5 7.5 4
I H 1.5 2 2.5 2
J F,G,I 1 2 3 48 2