Outdoor Eltek Rectifier Commissioning

Guide
General Objectives

To be familiarize into Eltek Commissioning


Set properly the standard parameters
Activate some features incorporated into Eltek
rectifier system
Tools Needed

 Laptop
 PowerSuite software
 LAN cable
Accessing Eltek Rectifier System
Access via LAN cable
 Set Laptop IP Address into 192.168.10.21/24

Open Web Browser


 Type on the URL; 192.168.10.20
Accessing Eltek Rectifier System
Enter needed parameters
 UN & PW: admin
Accessing Eltek Rectifier System
Successfully Connected
Accessing Eltek Rectifier System
Activating Parameters for PowerSuite connection
 Click System Conf
Accessing Eltek Rectifier System
Activating Parameters for PowerSuite connection
 Click Device Settings
Accessing Eltek Rectifier System
Activating Parameters for PowerSuite connection
 Click TCP/IP Security
 Check the needed set up
Accessing Eltek Rectifier System
Open PowerSuite software
Accessing Eltek Rectifier System
Click Connect Button
Accessing Eltek Rectifier System
Choose Network
 Set the need parameters
Accessing Eltek Rectifier System
Select Log In
 Type 3 as password
Accessing Eltek Rectifier System
Successfully Connected
Commissioning Proper: System Voltage Levels
Click System Voltage Levels
Commissioning Proper: System Voltage Levels
Set the following
 Reference: 2.25*
 Boost: 2.35*
 Rectifier Standby: 1.85
 Battery Disconnect: 1.8
 Battery Reconnect: 1.9666
 Rectifier OSV limit: 2.4583

*-depends on the battery specs


Commissioning Proper: Alarms Overview
Click Alarms Overview
Commissioning Proper: Alarms Overview
Defined the Alarms that need to be monitor
Commissioning Proper: Alarms Overview
 Set the Alarms into their specific Alarm output number
 Battery High Voltage: Alarm Output 81.1
 Rectifier Failure: Alarm Output 81.2
 Mains Fail: Alarm Output 81.3
 Battery Low Voltage: Alarm Output 81.4
 Load MCB Fail: Alarm Output 81.5
 Battery MCB Fail: Alarm Output 81.5
 High Temperature: Alarm Output 81.6
 Symmetry Fault: Alarm Output 81.6
Commissioning Proper: Power System
Click Power System
 Modify:
Site Name: 552 San
Fernando 2 Rectifier #
Responsible: name of
personnel
Commissioning Proper: Mains
Click Mains
 Number of Phases: 2
Commissioning Proper: Mains
Click MainsPhase 1
 Click MainsVolt 1
Commissioning Proper: Mains
Set the following
 Check Enable
 Major High: 270
 Minor High: 270
 Minor High: 185
 Major High: 185
 Alarm Group: Mains Fail
 Apply then Ok
Commissioning Proper: Mains
Click MainsPhase 2
 Click MainsVolt 2
Commissioning Proper: Mains
Set the following
 Check Enable
 Major High: 270
 Minor High: 270
 Minor High: 185
 Major High: 185
 Alarm Group: Mains Fail
 Apply then Ok
Commissioning Proper: Rectifier
Click Rectifier
 Click Rectifier Error
Commissioning Proper: Rectifier
Set the following
 Check Enable
 Major alarm: 1
 Minor alarm: 1
 Alarm Group: Rectifier Alarm
 Apply then Ok
Commissioning Proper: Rectifier
Click Rectifier
 Click Rectifier Comm Error
Commissioning Proper: Rectifier
Set the following
 Check Enable
 Major alarm: 1
 Minor alarm: 1
 Alarm Group: Crict Rect Alarm
 Apply then Ok
Commissioning Proper: Rectifier
Click the Configuration Tab
 Number of rectifiers: x
 Check the Suppress..
 Walk in time: Long time
 OSV limit: 2.4583
 Apply then Ok
Commissioning Proper: Rectifier
Click the Efficiency Tab
 Enable efficiency manager
 Rectifier-off delay: 10
 Shuffle time: 2
 Apply then Ok
Commissioning Proper: Load
Click LoadBank 1
 Click LoadFuse 1
Commissioning Proper: Load
Set the following:
 Click Enable
 Alarm Group: Load MCB Fail
 Apply then Ok
Commissioning Proper: Battery
Click Battery
 Click Status Tab
 Click Battery Voltage
Commissioning Proper: Battery
Set the following
 Click Enable
 Major High: 57
 Minor High: 57
 Alarm Group: High Voltage
 Minor Low: 48
 Major Low: 48
 Alarm Group: Low Voltage
 Apply then Ok
Commissioning Proper: Battery
Click Battery
 Click Status Tab
 Click Battery Temp
Commissioning Proper: Battery
Set the following
 Click Enable
 Major High: 40 (35*)
 Minor High: 35 (30*)
 Alarm Group: High Temp
 Apply then Ok

*-for indoor type


Commissioning Proper: Battery
Click Battery
 Click Status Tab
 Click LVBD
Commissioning Proper: Battery
Set the following
 Click Enable
 Disconnect Voltage: 43.2
 Reconnect Voltage: 47.2
 Apply then Ok
Commissioning Proper: Battery
Click Battery
 Click Configuration Tab
 Number of banks: 1
 Number of Strings: 4
 Description:
 Capacity AH: 150
Commissioning Proper: Battery
Click Battery
 Enable Temp comp
 Reference voltage: 2.25
 Reference temp: 25
 Temp slope: 3*
 Min comp voltage: 2.1*
 Max comp voltage: 2.35*

*-depends on battery specs


Commissioning Proper: Battery
Click Battery
 Click Current Limitation
 Enable Current Limitation
 Enable string current limit
 Set Current Limit: 60*
 Apply then Ok

*-current limit always 10%


of total battery capacity
Commissioning Proper: Battery
Click Battery
 Click Test Tab
 Click Interval test
 Click Enable
 Next start date: yyyy-mm-dd
 Next start time: HH:MM
 Interval period: 90*

*-one quarter cycle period


Commissioning Proper: Battery
Click Currents
 Click BattCurrent1.1
Commissioning Proper: Battery
Click General Tab
 Click Enable
 Apply then Ok
Commissioning Proper: Battery
Click Fuses
 Click BattFuse1.1
Commissioning Proper: Battery
Click General Tab
 Click Enable
 Alarm group: Battery
MCB Fail
 Apply then Ok
Commissioning Proper: Battery
Click Temperatures
 Click BatteryTemp1.1 (only BatteryTemp1.1 will
be configure)
Commissioning Proper: Battery
Click General Tab
 Click Enable
 Major High: 40
 Minor High: 35
 Alarm group: High
Temperature
 Apply then Ok
Commissioning Proper: Battery
Click BattMonStr.1
 Configure all BattMonSym1.1 to 1.4
 Repeat process for BattMonStr.2 to 4
Commissioning Proper: Battery
Click General Tab
 Click Enable
 Major alarm: 1.5
 Minor alarm: 1.5
 Alarm group: Symmetry
Fault
 Apply then Ok
Repeat process for 1.2 to
1.4
THANK YOU!!!