Professional Documents
Culture Documents
01 Introduction of KMG
01 Introduction of KMG
Shitalakhya
Bridge
N1
Dhaka
Dhaka
Meghna Bridge
Gumti Bridge
N8
N1 Comilla
Comilla
Chittagong
Chittagong
1. Background of the Project
Existing Bridges .....
3
1. Background of the Project
2013 10 March: JICA Loan Agreement BD-P72 (1st Phase: 28,945 Million Yen)
2013 18 November: Contract for No.PS-01: Consultancy Services for Detailed Survey,
investigation, Design and Construction Supervision
5
3-1. Overall Project Implementation Schedule
Feb
Detailed Design
Oct
Nov
Bidding
Dec
Construction Jan
Jan
Defect Liability
6 Jan
3-2. Each Bridge Implementation Schedule
7
3-3. Technical Feature of KMG Project
Superstructure – Steel Narrow Box Girder
Top Slab
Steel Pipe
Foundation – SPSP Foundation
15m
C.I.P Pile
38m
4.1 Scope of Works for Kanchpur
Existing
Existing Bridge
Bridge
22nd
nd Bridge
Bridge
Approx.
Approx. 340m
340m 22nd
nd Bridge. : 397.3m
Bridge. : 397.3m
(Dhaka
(Dhaka Side)
Side)
Approx.
Approx. 873m
873m
(Chittagong
(Chittagong Side)
Side)
9
Outline of Kanchpur Bridge
397.3 m
A1
A1 43.3 P1
P1 42.9 P2
P2 42.5 P3
P3 42.4 P4
P4 55.2 P5
P5 72.6 P6
P6 54.4 P7
P7 44.0 A2
A2
A1
A1 43.3 P1
P1
85.4 P3
P3
97.6 P5
P5
72.6 P6
P6
54.4 P7
P7
44.0 A2
A2
CIP
CIP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP CIP
CIP CIP
CIP
10
4.2 Scope of Works for Meghna
(4-lane
(4-lane Widening)
Widening) (4-lane
(4-lane Widening)
Widening)
nd Bridge :
Approx.1,071m
Approx.1,071m 22nd Bridge : Approx.1,018m
Approx.1,018m
(Dhaka
(Dhaka Side)
Side)
930m 930m (Chittagong
(Chittagong Side)
Side)
22nd
nd Bridge
Bridge
Existing
Existing Bridge
Bridge
Toll
Toll Gate
Gate
11
Outline of Meghna Bridge
930.0m
48.5
A1 48.5 P1
A1 P1 87 P2
P2 87 P3
P3 87 P4
P4 87 P5
P5 87 P6
P6 87 P7
P7 87 P8
P8 87 P9
P9 87 P10
P10 P11
P11
50 A2
A2
48.5
A1 48.5 P1
A1 P1 87 P2
P2 87 P3
P3 87 P4
P4 87 P5
P5 87 P6
P6 87 P7
P7 87 P8
P8 87 P9
P9 87 P10
P10 P11 P12 A2
P11 P12 A2
CIP
CIP CIP
CIP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP CIP
CIP
CIP
CIP
12
4.3 Scope of Works for Gumti
(4-lane
(4-lane Widening)
Widening) (4-lane
(4-lane Widening)
Widening)
Approx.
Approx. 940m
940m 22nd
nd Bridge : 1,410m
Bridge : 1,410m Approx.
Approx. 703m
703m
(Dhaka
(Dhaka Side)
Side) (Chittagong
(Chittagong Side)
Side)
Existing
Existing Bridge
Bridge
22nd
nd Bridge
Bridge
Toll
Toll Gate
Gate
13
Outline of Gumti Bridge
Affluent of Meghna River Gumti River
1,410.0m
52.5 87 87 87 87 87 87 87 87 87 87 87 87 87 87 87 52.5
A1
A1 P1
P1 P2
P2 P3
P3 P4
P4 P5
P5 P6
P6 P7
P7 P8
P8 P9
P9 P10
P10 P11
P11 P12
P12 P13
P13 P14
P14 P15
P15 P16
P16 A2
A2
52.5 87 87 87 87 87 87 87 87 87 87 87 87 87 87 87 52.5
A1
A1 P1
P1 P2
P2 P3
P3 P4
P4 P5
P5 P6
P6 P7
P7 P8
P8 P9
P9 P10
P10 P11
P11 P12
P12 P13
P13 P14
P14 P15
P15 P16
P16 A2
A2
CIP
CIP CIP
CIP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP SPSP
SPSP CIP
CIP CIP
CIP CIP
CIP CIP
CIP CIP
CIP CIP
CIP CIP
CIP CIP
CIP CIP
CIP CIP
CIP
14
5. Typical Cross Section
Kanchpur Bridge
Road Section
Bridge Section
15
5. Typical Cross Section
Meghna Bridge
Road Section
Bridge Section
16
5. Typical Cross Section
Gumti Bridge Road Section
Bridge Section
17
6. Traffic Management during Construction
Meghna Bridge (& Gumti Bridge)
During 2nd Bridge Under
Under Construction
Construction
Construction
(2 Lanes)
18
During 2nd Bridge Construction
(2 Lanes)
A1
P1 P10 P11
P2 P3 P4 P5 P6 P7 P8 P9
HINGE
1410000
357000 348000 705000
52500 3@87000=261000 43500 43500 3@87000=261000 43500 43500 7@87000=609000 52500
P 5 P 9 P 0
1 P 1 P 2
1 1
P 3 1
P 4 1
P 5 P 6
1
1
A
A1 A2
P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12 P13 P14 P15 P16
HINGE HINGE
20
7. Rehabilitation of Existing Bridges
Removal of Hinge – Integration of the existing Superstructure
Hinge device
PC bar
(2) After Integration
External PC tendon
22
23
THANK YOU FOR YOUR KIND ATTENTION
24