Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 12

The Kanchpur, Meghna and Gumti

2nd Bridges Construction


And Existing Bridges Rehabilitation Project
JICA Loan Agreement No. BD-P72 & BD-P94

Application of   Steel Narrow Box Girder

8th May, 2017


Narrow Box Girder
Conventional Box Girder Narrow Box Girder

Narrow box girder is a rationalized box girder based on reduction of number of


structural members and parts by narrowing the box shape.
1. Superstructure of 2nd Bridges
 Cross-section of Superstructure

3
Gumti Bridge Girder Cross Section
 Kanchpur Bridge
(Bridge L = 397.3m)

Minimum yield stress

SM570
50mm

4
 Meghna Bridge
(Bridge L = 930m)

Minimum yield stress

5
 Gumti Bridge
(Bridge L = 1,410m)

Minimum yield stress

SM570
56mm

SM570
47mm
6
2. Deck Slab of 2nd Bridges
 Steel Concrete Composite Deck (SCCD) Slab

concret
e

Main re-bar Rib Steel


Distribution re-bar Bottom Steel
anti-slide hole 7
3. Construction Method of Superstructure
 Superstructure : Launching Erection Method

8
4. Maintenance of Steel Bridge
 Bridge Inspection

Periodic Inspection
- Visual inspection twice a year

Detailed Inspection
- Approximately 1 time/5year
and as necessary

Inspection way is installed


between girders.
It’s also possible to enter
inside of box girders.
10
4. Maintenance of Steel Bridge
 Re-painting during in-service period
Exterior Painting System for Girder
and Composite Slab Deck
Re-Painting Cycle
Top coat : 25 ㎛ /
(deterioration : 2/3 ㎛ /year)
= 37.5 year

Once in 30 years

11
THANK YOU FOR YOUR KIND ATTENTION