Professional Documents
Culture Documents
Risk in Capital Budgeting Decision
Risk in Capital Budgeting Decision
Risk in Capital Budgeting Decision
• If the project is risky, then a higher rate should be used to allow for
the perceived risk. Assuming this rate to be 15 per cent, the net
present value of the project will be:
• αt = NCFt * /NCFt
• = Certain net cash flow / Risky net cash flow
• For example, if one expects a risky cash flow of
Rs.80,000 in period t and considers a certain
cash flow of Rs.60,000 equally desirable, then
αt, will be 0.75 = 60,000/80,000.
• ILLUSTRATION 13: A project costs Rs.6,000 and it has cash flows
of Rs.4,000, Rs.3,000, Rs.2,000 and Rs.1,000 in years 1 through 4.
Assume that the associated αt factors are estimated to be: αo = 1.00,
αl = 0.90, α2 = 0.70, α3 = 0.50 and α4 = 0.30, and the risk-free
discount rate is 10 per cent. The net present value will be:
• NPV=1.0(-6,000) + 0.9(4,000) / (1+0.10) + 0.7 (3,000) / (1+0.10)2
• +0.5(2,000) / (1+0.10)3 + 0.3(1,000) / (1+0.10)4
• = -Rs37
• If the IRR method is used, we will calculate that
rate of discount which equates the PV of
certainty-equivalent cash inflows with the PV of
certainty-equivalent cash outflows. The rate so
found will be compared with the minimum
required risk-free rate. Project will be accepted if
the IRR is higher than the minimum rate;
otherwise it will be rejected.
Sensitivity Analysis
Variables
Investment (Rs) 10,000
Sales volume (unit) 1,000
Unit selling price (Rs) 15
Unit variable cost (Rs) 6.75
Annual Fixed costs (Rs) 4,000
Depreciation (WDV) 25%
Corporate tax rate 35%
Discount rate 12%
Table 2: Net Cash Flows of the project
C0 C1 C2 C3 C4 C5 C6 C7
Investment -10,000
Revenue 15,000 15,000 15,000 15,000 15,000 15,000 15,000
variable cost 6,750 6,750 6,750 6,750 6,750 6,750 6,750
Fixed costs 4,000 4,000 4,000 4,000 4,000 4,000 4,000
Depreciation 2,500 1,875 1,406 1,055 791 593 1780
EBIT 1,750 2,375 2,844 3,195 3,459 3,657 2470
Tax 613 831 995 1,118 1,211 1,280 865
PAT 1,138 1,544 1,848 2,077 2,248 2,377 1605
NCF -10,000 3,638 3,419 3,255 3,132 3,039 2,970 3385
• The project’s NPV at 12 percent discount rate and IRR are as
follows:
• NPV = +4973
• IRR = 27.05%
• Since NPV is positive (or IRR > discount rate), the project can be
undertaken.
• Let us assume the pessimistic and the optimistic values for volume,
price and cost as shown in Table 3.
Table 3: Forecasts Under Different Assumptions
• The most critical variables are sales volume and unit selling price.
• If the volume declines by 25%, NPV becomes negative (-Rs1146).
• Similarly if the net selling price falls by 15%, NPV is minus Rs1,702
SCENARIO ANALYSIS
Variable combinations:
Sales volume (unit) 1,000 750 1,250 1,250
Selling price / unit (Rs) 15.00 12.75 16.50 13.50
Variable cost/unit (Rs) 6.75 7.43 6.75 7.10
Fixed cost 4,000 4,800 3,200 4,400
Results:
NPV (Rs) 4,972 -10,038 19,026 3,044