Professional Documents
Culture Documents
Total Primavera
Total Primavera
Total Primavera
GENERAL INFORMATION
ACTIVITY TYPES
Task Dependent:
When the work needs to be accomplished in a given time frame,
regardless of the assigned resources’ availability.
Activity’s resources are scheduled to work according to the activity
calendar.
Duration is determined by the assigned calendar’s workweek.
Resource Dependent:
When multiple resources assigned to the same activity can work
independently.
Activity’s resources are scheduled according to their individual resource
calendar.
Duration is determined by the availability of the resources assigned to
work on the activity.
ACTIVITIES
GENERAL INFORMATION
ACTIVITY TYPES
Start Milestone:
Used to mark the beginning of a phase or to communicate project
deliverables.
Zero duration activity and only has a start date.
Can assign constraints, expenses, work products, and documents.
Cannot assign resources/roles.
Finish Milestone:
Used to mark the end of a phase or to communicate project
deliverables.
Zero duration activity and only has a finish date.
Can assign constraints, expenses, work products, and documents.
Cannot assign resources/roles.
ACTIVITIES
GENERAL INFORMATION
ACTIVITY TYPES
Level of Effort
Typically used for ongoing tasks dependent on other activities.
Duration is determined by its predecessor/ successor activities.
Clerical work, security guard, meetings, and project management
tasks.
Cannot assign constraints
WBS Summary
Typically used to summarize at WBS levels.
The WBS summary activity comprises a group of activities that share a
common WBS level.
Cannot assign constraints to WBS summary activities.
ACTIVITIES
GENERAL INFORMATION
DURATION TYPE
Setting which allows you to control how P6 synchronizes the
Duration, Labor/Non-labor Units and Resource Units/Time for
activities so that the following equation is always true:
Fixed Units: used on activities where the number of resource units are
fixed.
Fixed Duration & Units: used in case where both Duration and Units
are fixed, as in the rate at which a resource can work on the activity can be
changed.
ACTIVITIES
GENERAL INFORMATION
Duration:
Selected activity's Activity % Complete is tied to its Duration % Complete
Use if activity progress can most easily be reported based on actual days of
work accomplished and scheduled days of work remaining.
The activity’s percent complete is calculated from the actual and remaining
duration. For example, if you have a 10-day activity that has 5 days
remaining, it is 50% complete.
EXPENSES
Expenses are non-resource costs associated with a project and
assigned to a project's activities.
Assign resources
In the Activity window:
Enter the resource name and amount of work planned for the
activity.
P6 calculates the cost based on the resource quantity and
price/unit as defined in the Resource window.
RESOURCES
STEPS FOR RESOURCE MANAGEMENT
Analyze resources and costs
In the Activities or Tracking windows:
Use a resource profile to view resource quantity/cost graphically,
displaying when and how much of the resource will be used.
RESOURCES
CREATING RESOURCE DICTIONARY
The Resources window contains information about all resources
within the enterprise. These resources are shared by all projects
in the organization, allowing for centralized resource
management.
RESOURCES
CREATING RESOURCE DICTIONARY
Steps:
1) To create resource dictionary click on Resources from HOME
page.
2) Create a resource pool by clicking ADD menu.
3) Add the following resources under the created resource pool.
4) To add new resource, click on ADD option.
5) Give Resource ID and in the detail tab select the resource
classification. P6 supports 3 type of resource classifications,
namely Labor, Non-Labor and Material resource.
6) Click on Units & Prices tab and give the resource availability
and the Price /Time.
RESOURCES
ASSIGNING RESOURCES TO ACTIVITIES:
Steps:
Choose Project, Activities.
Select the activity to which you want to assign a resource.
Display Activity Details, and then click the Resources tab.
Click Add Resource.
Select the resource you want to assign.
Click the Assign button, and then click the Close button.
ROLES
Roles are project personnel job titles or skills, such as mechanical
engineer, inspector, or carpenter.
Once you finalize your plans, you can replace the roles with
resources that fulfill the role skill levels. Five proficiency levels
can be assigned to roles: Master, Expert, Skilled, Proficient and
Inexperienced.
ROLES
Roles can be assigned in the Resource Details window or from
the Roles dialog box.
ROLES
ADDING A ROLE
Steps:
1) Choose Enterprise, Roles.
2) Click Add.
3) Click the General tab, and then type a unique ID for the role.
4) Type the role's name.
5) Type a description of the role's responsibilities.
ROLES
ASSIGN ROLES TO RESOURCES FROM THE RESOURCES
WINDOW
Steps:
1) Choose Enterprise, Resources, then select the resource to
which you want to assign a role.
2) Click the Roles tab, and then click Assign.
3) Select the role you want to assign.
4) Click the Assign button, and then click the Close button.
5) In the Roles tab, double-click the Proficiency column and
select a skill level.
6) If this is the resource’s primary role, mark the Primary Role
checkbox
COST ACCOUNTS
You can create cost accounts and associate them with activity
resource assignments or expenses in a project.
Benefits
Build a schedule that more accurately reflects the real-
world aspects of the project.
Provide added control to the project.
Use to impose a restriction on the entire project or an
individual activity.
CONSTRAINTS
CONSTRAINTS
Steps:
To apply constraints activate Activity Details.
In Activity Details enable Status / Constraints menu, select the
constraint and apply appropriate constraint date.
Schedule the project through Schedule command.
CONSTRAINT TYPES
MUST FINISH BY
START CONSTRAINTS
FINISH CONSTRAINTS
MANDATORY CONSTRAINTS
LATE CONSTRAINT
CONSTRAINTS
MUST FINISH BY
Used when an overall project deadline must be met.
Forces all activities in the project to finish by the date (and time)
specified.
Affects the total float of the entire project.
Must be applied in the Project window on the Dates tab.
CONSTRAINTS
MUST FINISH BY
Steps:
1) From the Directory bar, click Projects.
2) From the Display Options bar, click Expand All.
3) Click the Dates tab.
4) Highlight the project
5) Click the ellipses in the Must Finish By field to select a date
The next step is to reschedule the project to see the effect of the
imposed deadline on the late dates and total float in the project
plan.
6) Choose Tools, Schedule or press F9.
7) Click Schedule.
CONSTRAINTS
START CONSTRAINTS
Start On
Forces the activity to start on the constraint date. Unlike the
mandatory start constraint, which can violate the network logic,
this constraint protects it.
Shifts both early and late start dates.
Delays an early start or accelerates a late start.
Used to specify dates submitted by contractors or vendors.
CONSTRAINTS
START CONSTRAINTS
Start On or Before
Forces the activity to start no later than the constraint date.
Shifts the late start to the constraint date.
It only affects late dates (affects the late dates of its predecessors).
Used to place a deadline on the start of the activity.
When calculating a schedule, this constraint is used in the
backward pass only if the calculated late start date will be later
than the imposed date.
This constraint may decrease total float.
CONSTRAINTS
START CONSTRAINTS
Start On or After
Use the Start On or After constraint to set the earliest date an
activity can begin.
Forces the activity to start no earlier than the constraint date.
Pushes the early start date to the constraint date.
This constraint affects only early dates (affects the early dates of
its successors).
When calculating a schedule, this constraint is used in the
forward pass only if the calculated early start date will be earlier
than the imposed date.
The early start date of an activity with a start on or after
constraint cannot be earlier than the imposed date, although the
network logic may cause the early start to occur later.
CONSTRAINTS
FINISH CONSTRAINTS
Finish On
Forces the activity to finish on the constraint date.
Shifts both early and late finish dates.
Delays an early finish or accelerates a late finish.
Used to satisfy intermediate project deadlines.
Finish On or Before
Forces the activity to finish no later than the constraint date
Pulls the late finish date to the constraint date.
Affects the late dates of its predecessors.
Used to place a deadline on the finish of the activity.
CONSTRAINTS
FINISH CONSTRAINTS
Finish On or After
Forces the activity to finish no earlier than the constraint date
Shifts the early finish to the constraint date.
Affects the early dates of its successors.
The finish on or after constraint reduces float to coordinate
parallel activities, ensuring that the finish of an activity is not
scheduled before the specified date.
CONSTRAINTS
MANDATORY CONSTRAINTS
Mandatory Start and Finish
Forces early and late dates to be equal to the constraint date.
Affects late dates of predecessors and early dates of successors.
It is used regardless of its effect on network logic which may
violate network logic.
BASELINING THE PROJECT PLAN
A Baseline is a complete copy of a project plan that you can
compare to the current schedule to evaluate progress. Before
updating a schedule for the first time create a baseline.
DELETE A BASELINE
You can delete a baseline from the project database. Select the
project that contains the baseline you want to delete. Choose
Project, Maintain Baselines. Select the baseline, then click Delete.
Note:
You cannot delete an active baseline. An active baseline is any
baseline designated as the primary, secondary, or tertiary baseline
in the Assign Baselines dialog box.
BASELINING THE PROJECT PLAN
UPDATING BASELINES
As a project progresses, certain types of project data are likely to
change. When a project is in progress and data changes, the
original baseline you created for the project will not accurately
measure performance against the current project.
Likewise, creating a new baseline may not yield accurate results for
measuring performance because some data will change during the
life of the project that should be measured against the original
project data.
BASELINING THE PROJECT PLAN
UPDATING BASELINES
For example, changes to any of the following data types can affect
results when comparing a project to its baseline:
Added/dropped activities
Modified activity data including dates, costs, resources, steps,
documents, notebooks, relationships, codes, expenses, and
user-defined fields
Modified project-level data including details, documents, risks,
issues, thresholds, calendars, and codes
Using Primavera’s Update Baseline utility, you can update the
original baseline plan with new activity, resource/role assignment,
and project data. When updating a baseline, you can choose to
update all activities or you can apply a filter to update activities
that meet the filter’s criteria. You can also specify the types of data
to update.
BASELINING THE PROJECT PLAN
UPDATING BASELINES
Steps:
To update a baseline, open the project that contains the data you
want to add to the baseline.
Choose Project, Maintain Baselines.
Select the baseline you want to update. Click Update.
Select the project-level data you want to update.
Choose to update all activities or select a filter to only update
activities that meet the filter’s criteria.
Choose to add new activities from the current project, delete
activities no longer in the current project, and/or update existing
activities. If you choose to update existing activities, click Update
Options to select the types of activity and resource/role
assignment data you want to update.
BASELINING THE PROJECT PLAN
UPDATING BASELINES
Steps:
To save the results of the baseline update to a file (including errors
and warnings), enter a pathname or select a file.
After selecting options, click Update.
When the update is complete, click View Log to view the results of
the update.
BASELINING THE PROJECT PLAN
RESTORE BASLINE VS UPDATE BASELINE