Professional Documents
Culture Documents
Lecture 4,5,6 - Mba Network Analysis
Lecture 4,5,6 - Mba Network Analysis
c
b
a c
a c
b Dummy
activity
b d
Errors and logical sequence
Three types of errors in logic may arise when
drawing network, particularly when it is a
complicated one. These are known as
• Looping: Normally in the network, the arrow points
from left to right. This convention is to be strictly
adhered, as this would avoid the illogical looping, as
shown wrongly below.
1 2 3 4
• Dangling: The situation represented by the
following diagram is also at fault, since the
activity represented by the dangling arrow 7-8 is
undertaken with no result.
6 7 9
8
• Duplicate activities: consider the following
figure
A
6 7 8
6 8
B
7
Dummy Arrows
Dummy arrows are used to transfer logic
from one event node to another in the net
work. They are represented by broken
arrows. A dummy arrow has zero
duration and does not represent an
activity. These symbols are used to
represent the relationships among the
activities.
Question 1
Show by representation, through arrows and nodes, the partial
situations described below; "the letters in each case are to be
taken” as an activity description.
1. Z is controlled by T, i.e. (Z depends on T).
2. T is controlled by P and Q.
3. T controls Y and Z.
4. Y and Z are controlled by S and T.
5. Y is controlled by S and T. with Z controlled by T.
6. S and T control X, whilst T and U control Y.
7. S and T control X, T controls Y, with T and U controlling Z.
8. S controls X and Y. whilst U controls Y and Z.
9. S controls X and Y. T and U control Y with Z depending on
U.
(Hint: Prepare dependency table to facilitate solution)
Question 2
Draw a network for the following conditions:
1. U and R can be performed concurrently and are the start
of the project.
2. K must follow E.
3. X is dependent on both Q and K.
4. Neither F nor G can start before R is finished but F and
G can be performed concurrently.
5. U must precede E and Q.
6. Q must precede J.
7. C is dependent on both F and G.
8. F and Q can be done concurrently.
9. H can begin only after C, X and J are completed.
10. H is the last operation.
Analysis of the project normally involves:
• Determining the Critical Path. The critical path is
the group of activities in the project that have a
slack time of zero. This path of activities is
critical because a delay in any activity along it
would delay the project as a whole.
Name
Activity
Earliest Earliest
Start ES EF
Finish
Latest LS
Duration
LF
Start Activity Latest
Finish
• Typical Network diagram
Earliest
Event
Activity
Time
Label
Event Direction
Label
Latest
Event
Time
Example 1
Complete the network diagram including the EET and LET.
2
B 3 E
6
A C 3 F 5 H 6
0 1
5 7 8
4
G
D 5
5
4
Example 2
A company has decided to redesign its electronic component. The
project involves several activities which are listed below:
Crash
cost
COST
F
Normal
cost
C
O B A
DURATION FOR THE JOB
Crash Normal
Time Time
• Let OA represent the normal duration of completing a job and
OC the normal cost involved to complete the job. Assume that
the management wish to reduce the time of completing the job
to OB from normal time OA. Therefore under such a situation
the cost of the project increases and it goes upto say OD (Crash
Cost). This only amounts to saving that by reducing the time
period by BA the cost has increased by the amount CD. The
rate of increase in the cost of activity per unit decrease in time
is known as cost slope and is described as follows.
Activity cost slope = CD OD OC
AB OA OB