Professional Documents
Culture Documents
Activity Duration Estimating
Activity Duration Estimating
ESTIMATING
Input to Activity Duration
Estimating
• Activity list
• Constraints
• Assumption
• Resource requirements
• Resource requirements
Transform to Random
Variates
Continue
Analyze Output
Schedule Simulation
in which the project in network is used as the model of
the project. The results of a schedule simulation may used
to quantify the risk of various schedules alternatives,
different project strategies, different through the network,
or individual analysis. Schedule simulation should be
used on any large complex project since traditional
mathematical analysis such as the Critical Path Method
(CPM) and the Program Evaluation and Review
Techniques (PERT) do not account for path convergence
and thus tend to underestimate project duration.
Output from Activity Duration
Estimation
• Activity duration estimates
• Activity duration estimates
are quantitative assessment of the likely number
of work period that will be required to complete
an activity. To avoid building inefficiency into the
plan usually no provision is made in the duration
estimate for overtime, extended work week,
strikes, late deliveries, authorization delays,
abnormal weather, and acts of God.
Output from Activity Duration
Estimation
• Activity duration estimates
• Basis of estimates
• Basis of estimates
Assumptions made during development of
estimates must be documented. If available,
historical data for the different trades(productivity)
rates of the performing construction organization
derived from the past projects and accumulated
experience of the construction supervisor should
be included in the documentation.
Output from Activity Duration
Estimation
• Activity duration estimates
• Basis of estimates
• Activity list updates
THANK
YOU