Professional Documents
Culture Documents
Ecm 367 - Project and Construction Management
Ecm 367 - Project and Construction Management
Ecm 367 - Project and Construction Management
25 June 2020
Content
Introduction / Project Identify critical activities.
brief. Project cost estimation.
Factors of site selection. Locality Plan.
Feasibility Study
(Business and Technical Site Layout Plan
Aspects). (AutoCad)
Site investigation. Standard Condition of
Contract.
Organization chart.
Site safety (checklist,
Construction Plan (WBS procedure, flowchart, PPE
and bar chart). etc)
Network Diagram Construction safety
(planning & scheduling – regulations (OSHA,
MSP). Factory & Machinery Act)
2
1.Introduction /
Project brief.
3
■ Location: Alor Setar, Kedah,
Malaysia
■ Site project area: Titi
Keliling, Alor Setar, Kedah,
Malaysia
4
WHO MANAGE THIS PROJECT?
• MAHZ SDN.BHD.
The name orgin was from the combination of share holder name ( M =
Muqhrey, A = Asyraf ,
H = Haniff AND Z = Zarish)
5
■ Objective: Expand UiTM’s branches
at the strategic location.
■ What Alor Setar have?
– Public transport station
■ Shahab Perdana Bus Terminal
■ KTM Alor Setar
■ Sultan Abdul Halim Airport
Duration: 4 years
Physical of site project:
- Ground level
- Paddy field area
- About 6400000 sq. ft.
6
2.Factors of site
selection.
7
Site selection reflects the process of building new buildings, for
company and government alike. Site selection includes considering a new
project needs against the quality of prospective sites.
Project Objective
The project is construct a new campus for
UITM student at Alor Setar to give an
easier access for student and local people to
get knowledgeand opportunity to improve
themselves.
8
• TYPE OF GROUND SOIL
• PURPOSE OF THE BUILDING
• NATURAL LIGHT AND AIR
• FRIENDLY NEIGHBOURHOOD
• ENVIRONMENTAL
• AVAILABLE FACILITITIES CONDITION
• LEGAL AND FINANCIAL
• GOVERNMENT LAWS
ASPECTS
• SHAPE AND SIZE
• NEAREST TO PUBLIC
• TERRAIN CONDITION FACILITIES
• NEAREST TO SOURCES OF
• ACCESSIBILITY
OPERATING POWER 9
3.Feasibility Study
(Business and
Technical
Aspects).
10
1. PROJECT OBJECTIVE
2. BUSINESS POINT IF VIEW
• LAND VALUATION
12
4. Site
investigation.
13
Site investigation is to examine the suitability of the site in terms of
physical properties, geological and geotechnical properties of materials
such as soils , rocks and geological structures, and the last term is building
environment.
Assessment of data collected from geological and geotechnical data that
will be used in structural design to ensure that construction is economical,
safe for living beings & ecosystem, and perform satisfactorily within the
limits and standards imposed by the authorities.
14
• PHYSICAL PROPERTIES
• GEOLOGICAL
• GEOTECHNICAL PROPERTIES OF MATERIALS
• BUILDING ENVIRONMENT
• INTRODUCTION AND PURPOSE
• INTERFACING IMPACTS
• 3 STAGES
• ENGINEERING ASSESSMENT
1. SITE EXPLORATION
• LIMITATION OF SITE INVESTIGATION
2. SITE INVESTIGATION
• METHOD AND PROCEDURE
( INCLUDING TWO METHOD )
DEPEND ON – STAGE INVESTIGATION / TOPOGRAPHY /
3. FOUNDATION INVESTIGATION
TYPE STRUCTURE / INFORMATION REQUIRED /
ALLOCATED FUND / ACCESSIBILITY / MATERIALS
METHOD – DESK STUDY / SEISMIC REFLECTION AND
REFRACTION / TRIAL PITS / MACKINTOSH PROBE TEST
/ LAND SURVEY 15
• FACTOR GOVERNING SITE INVESTIGATION
1. ECONOMICAL FACTORS
2. TECHNICAL FACTORS
• PLANNING EXUCATION
2. DESIGN
3. CONSTRUCTION
16
5. Organization
chart.
17
18
6.Construction
Plan (WBS and
bar chart).
19
WBS
20
BAR CHART
21
22
23
24
7. Network Diagram
(planning &
scheduling – MSP).
25
26
27
28
29
30
31
8. Identify critical
activities.
The Critical Path Method is the sequence of scheduled activities
that determines the duration of the project.”
32
33
34
35
36
37
38
39
40
41
42
43
44
45
9. Project cost
estimation
46
47
48
49
10. Locality
Plan.
50
Susuran Stargate, Lebuhraya
Sultanah Bahiyah, 05400 Alor
Setar, Kedah
• Public facilities
I. Tesco Hypermarket
II. Aman Central
III. Terminal Shahab Perdana
IV. Sultan Abdul Halim Airport
V. Hospital Sultanah Bahiyah
51
11. Site
Layout Plan
(AutoCAD)
52
A site layout plan provides a thorough map of the whole site and the
relationship between the works being planned and the boundaries of the
land, surrounding roads and neighboring buildings.
Some applications would include an existing layout plan for sites and
a new layout plan for sites. The existing and proposed site can be
combined and displayed on one plane for simple applications so long as
what is present, what is proposed and what is to be demolished is clearly
highlighted and annotated.
53
54
55
12. STANDARD
CONDITION OF
CONTRACTS
56
WHAT IS STANDARD
CONDITION OF
CONTENT IN STANDARD CONDITION OF
CONTACT?
CONTRACT
57
DUTIES
a) Be the custodian of the contract documents. [Clause 7(a)]
1. ROLE OF b) Contractor will paid for work caused by S.O. negligence. (i.e. S.O.
OWNER will bear the cost of making good of any work due to S.O.I. (open up or
re-execute) if found to be S.O. negligence). [Clause 9(b)]
d) Pay contractor for any or additional works not mentioned in the
PWD 203A used when the contract documents, i.e. V.O. [Clause 25(f)]
project was under e) Give possession of site to the contractor on the date of possession.
government. According to [Clause 38(b)]
PWD 203A Condition of
f) Pay the contractor amount certified within period of honoring
Contract, the owner (may
be represented by JKR certificate. [Clause 47(d)]
officers) has the following g) Pay the contractor amount awarded by the Arbitrator. [Clause 54(f)]
implied powers and duties.
58
POWER OF OWNER
• POWER
• a) Inspect the contract documents. [Clause 7]
• b) Sub-letting (sub-contract) any part of the works with the S.O. consent in writing. [Clause 27(a)]
• c) Assign the contract if S.O. consent is given. [Clause 27(d)]
• d) Make reasonable objection to entering into sub contract with a named person.[Clause 28(c)]
• e) Determine his employment. [Clause 38(e)]
• f) Serve a default notice on the owner specifying the faults 60
62
5. PRIME COST AND
PROVISIONAL SUMS
• a “Prime cost” is limited to the cost of supplying the relevant item, and does not
include the cost of any work that relates to it (such as its installation).
• “Provisional sums” include allowances for both the supply item and all related work to
be performed by the contractor.
• This project took 4 years to complete. So, there have delay 15 days from
the Date of Completion due to Delay and Extension time causes by force
majeure, bad weather.
66
9. DAMAGE FOR
NON- COMPLETION
• 1. If the Contractor shall complete the works by "Date for
Completion" or within any extended time under Clause 43, S.O. shall
issue the "Certificate of Non-completion". Contractor shall pay
government a sum calculated at the rate stated in Appendix as
Liquidated and Ascertained Damages (LAD) for the period during
which the works remained incomplete. S.O. may deduct from any
monies which is due to Contractor. [Clause 40.2]
67
10. DELAY AND
EXTENSION OF TIME
CLAUSE 43
• a) By force majeure*
• b) By reason of any exceptionally inclement weather
• c) By reason of S.O. directions, consequential upon disputes with
neighboring owners.
• d) By reason of the loss or damage due to Clause 36.
68
11. DEFECT
LIABILITY PERIOD
• LAD shall be defined as the penalty imposed for failure of contractor to
complete the work by the date of Completion stated in the Contract
Document or after Extension of Time (E.O.T.) is granted.11 DAMAGES
FOR NON-COMPLETION 40
• If the contractor shall complete the works by “Date for Completion” or
within any extended time under Clause 43, S.O. shall issue “Certificate of
Non-completion”. Contractor shall pay government a sum calculated at the
rate stated in Appendix as Liquidated and Ascertained damages (LAD) for
the period during which the works remained incomplete. S.O. may deduct
from any monies due to contractor.
69
13. Site safety
(checklist,
procedure,
flowchart, PPE
etc.)
70
■ PERSONAL PROTECTIVE EQUIPMENT
– Is equipment worn to minimize exposure to hazards that cause serious workplace
injuries and illness
– Some protection in construction:
■ Eye and face protection
■ Foot protection
■ Hand protection
■ Head protection
■ Scaffolding
■ Electrical safety
■ Floor and wall openings
■ Elevated surfaces
■ Hazard communication
■ Crane safety 71
PROCEDURE AND FLOWCHART
72
14.Construction
safety regulations
(OSHA, Factory &
Machinery Act)
73
■ OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA)
– A regulation to ensure safe and healthful working conditions for working men
and women by setting and enforcing standards
– Providing training, outreach, education and assistance
– Some safety of factory and machinery in construction are:
■ Scaffolding
■ Fall protection
■ Ladders
■ Stairways
■ Trenching
■ Cranes
■ Hazard communication
■ Head protection
74
Scaffolding
75
Fall protection
76
Ladders
77
Stairway
78
Trenching
79
Cranes
80
Hazard Communication
81
Head Protection
82
References
1. https
://www.ejcdc.org/construction-contract-documents/#:~:text=Construction%20%E2%80%9CContract%20Docu
ments%E2%80%9D%20are%20the,parties%20(Owner%20and%20Contractor
).
2. http://www.geoconsiteinvestigations.com/site-investigation-8974.html#:~:text=Site%20Investigation%20is
%20the%20process,Geologic%20survey%20maps.
3. 2. https://www.sciencedirect.com/science/article/abs/pii/0013795267900269
4. 3. https://edoc.pub/report-ecm367-pdf-free.html
5. 4. https://www.n-somerset.gov.uk/my-services/planning-building-control/planning/planning-advice/drawing-
standards/drawing-standard-site-location-plan/
6. 5. https://civilblog.org/2015/07/30/10-key-factors-affecting-selection-of-a-building-site/
83
THANK
YOU!