Work Permit Application

You might also like

Download as ppt, pdf, or txt
Download as ppt, pdf, or txt
You are on page 1of 23

Oman India Fertiliser Project

“PERMIT TO WORK” PHILOSOPHY

SPF TKP OMIFPRO SNC


Sur Site 1
Essential features of any Permit To
Work (PTW) System
 A clear definition as to whom may authorise
particular work and who is responsible for
specifying the necessary precautions

 Instruction and continuous training in both the


issuing and receiving of work permits

 Monitoring to ensure that permit procedures are


being followed and that the system functions
correctly.
SPF TKP OMIFPRO SNC
Sur Site
2
Purpose of a work permit system
By controlling the work carried out in a certain
area by using a permit to work system, we can
make sure that activities do not clash with one
another.

For example, if we know in advance where we are


blowing a line, we can postpone other more
routine work in that area. If someone needs to do
some hot work in a live gas area, we can control
his activity by ensuring that there is no live gas
present before he starts.
SPF TKP OMIFPRO SNC
Sur Site
3
Purpose of the PTW
 Describe the work that is to be carried out
 Specify the conditions and impose limitations
under which potentially hazardous work may be
carried out
 Ensure that the safe conditions established at
the time of issuing the work permit remain so
throughout the validity of the permit and hence
duration of the operation
 Reduce the chances of misunderstanding and
ensure that supervisors take account of all
foreseeable circumstances

SPF TKP OMIFPRO SNC


Sur Site
4
PTW within OMIFCO site

 A work permit system has been introduced for the


PC&C phase. This applies to all systems and
facilities taken over for PC&C. All work permits
will be coordinated through the Permit
Coordinator (in OMIFPRO office).

 The Construction permit systems will continue to


operate in parallel for the systems and facilities
under Construction control, as appropriate.

SPF TKP OMIFPRO SNC


Sur Site
5
Split of work JV / sub-contractor

 Before Mechanical Completion, during operations


relative to Construction and Pre-Commissioning
(according to split of work) in these areas, the
sub-contactor will issue a PTW and submit it to JV
for approval.

 After Mechanical Completion, during operations


relative to Commissioning, JV will issue and
approve the PTW.

SPF TKP OMIFPRO SNC


Sur Site
6
Area under JV PC&C Control and submitted
to PTW

 Unit 38 – Natural Gas Preparation


 Unit 45 – Fire Water pumps station
 Unit 36 and instrument air header
 Unit 41A – Power generation
 SS #1 / SR 1
 SS #6 / SR 6

SPF TKP OMIFPRO SNC


Sur Site
7
Who ?

SPF TKP OMIFPRO SNC


Sur Site 8
Issuing Authority
 Who
During Construction and Pre-Commissioning until
Mechanical Completion activities (according to split of
work), the sub-contractor pre-Commissioning manager or
his designee is the issuing authority.
After Mechanical Completion during Commissioning, JV
Commissioning manager or his designee is the issuing
authority.

 Responsibilities
Gets the job prepared and ensure the compliance with the
safety rules and precautions set out in the Permit to Work.
Sets the checks and tests to be carried out before starting
the job

SPF TKP OMIFPRO SNC


Sur Site
9
Approving authority
 Who
The approving authority is the JV commissioning manager
or his designee.

 Responsibilities
He is responsible of providing the working and safety
procedures and instructions. He will address to the issuing
authority the additional request/ checks (if any) to be
fulfilled in order to allow the work to start.

SPF TKP OMIFPRO SNC


Sur Site
10
Receiving Authority

 Who
The receiving authority will be at least at the level of sub-
contractor supervisor such as mechanical supervisor,
instrumentation supervisor,…

 Responsibilities
Receive the permit and ensure safe working practices,
housekeeping and mechanical clean-up of the area upon
completion of the work.

SPF TKP OMIFPRO SNC


Sur Site
11
Operating Authority

 Who
The operating authority (also called area supervisor) is in
charge of one unit or a group of units. This person works
for the JV team (Ex. In unit 38, the JV Utilities supervisor)

 Responsibilities
He is in charge of the preliminary checks required by the
issuing /approving authority and ensures that the work can
be carried out safely.

SPF TKP OMIFPRO SNC


Sur Site
12
Performing Authority

 Who
The performing authority is responsible for carrying out
the job.

 Responsibilities
Use proper tools and equipment for the safe execution of
the work.
Leave the area in safe conditions.

SPF TKP OMIFPRO SNC


Sur Site
13
JV HSE Coordinator

The HSE authority is NOT responsible for


the issue or authorization of Permits To
Work. He is there to check for conflicts
and audit validity of permits.

SPF TKP OMIFPRO SNC


Sur Site
14
Types of PTW

Cold work permit


Hot work permit
Excavation permit
Radiography permit
Electrical Isolation Clearance
Vessel entry permit

SPF TKP OMIFPRO SNC


Sur Site
15
Cold Work Permit
 Cold Work Permits will be
issued for work on all
equipment and machines
where electric power, moving
parts, dangerous materials or
other hazards are suspected, or
known to be present.
 The Cold Work Permit covers
work that does not involve
equipment or materials
producing flames, spark or
heat, or are classified as a
source of ignition.
 Will often be used to prepare
equipment and site for other
permit required activities such
as hot work, confined space,
isolation etc.
SPF TKP OMIFPRO SNC
Sur Site
16
Hot Work Permit
 The Hot Work Permit covers
work that involve equipment
or materials producing
flames, spark or heat, or are
classified as a source of
ignition.

SPF TKP OMIFPRO SNC


Sur Site
17
Cold Work Permit
(step 1- Request)
This request will be filled by a
sub-contractor supervisor
responsible of the work to be
performed

1
XX/XX/2004 7:00 am XX/XX/2004 7:00 am
38 / 45 / SS6 / SR6
DESCRIPTION OF THE WORK TO BE PERFORMED WITH INDICATION OF THE
LOCATION ( IF NECESSARY ADD A P&ID OR A PLOT)
INDICATE ALSO THE NUMBER OF PERSON AND JOIN A LIST OF PERSONNEL

3 Mr. XXXXX ( SUPERVISOR LEVEL) 2


Mr. YYYY (DISCIPLINE SUPERVISOR LEVEL)

SPF TKP OMIFPRO SNC


Sur Site
18
Cold Work Permit
(step 2 - Raise)
The issuing authority will raise this
part of the PTW and the
approving authority will add some
instructions (if any)

At this level, JV keep the second


ADDITIONAL SAFETY
copy of the PermitINSTRUCTIONS
To Work
5
Mr. X (Sub-C OR JV) Mr. Y (JV) Mr. Z
XX/XX/2004 XX/XX/2004 XX/XX/2004

SPF TKP OMIFPRO SNC


Sur Site
19
Cold Work Permit
(step 2 bis - Raise)

RAISE IN PARALLEL Excavation permit


AND ATTACH TO
THE WORK PERMIT Radiography permit
THE SPECIFIC
PERMIT IF NEEDED Electrical Isolation Clear
ance
Vessel entry permit

SPF TKP OMIFPRO SNC


Sur Site
20
Cold Work Permit
(step 3-Checking)
Until live gas comes into the plant,
gas testing is not necessary for cold
work permit. Once live gas is on site,
the shift supervisor will conduct gas
testing

6
XX/XX/2004 XX:YY At this stage, the operating
Before starting the work,
XX/XX/2004 XX:YY the
authority keep the Performing
first copy Authority certifies
and
Operating

Authority willgive
ensure
the original to thethatperforming
he is aware of the work
that the workplace isDuring
properly
the validity
authority of and precautions
the Permit
upon completion of the specified have
prepared according toTo the here this latter
Work, workis renewedbeen implemented
above requirementseach day by the operating
authority
SPF TKP OMIFPRO SNC
Sur Site
21
Cold Work Permit
(step 4-Closure & Custody)
After work completion and before leave the
area, the performing/operating authority will
ensure that the workplace is clean and in a
safe conditions. Each part signs the Permit
to Work for closure

XX/XX/2004 YY:ZZ XX/XX/2004 YY:ZZ

7 XX/XX/2004 XX/XX/2004

The
Afterauthorization
closure, all copies
to re-energize
of the Permit
a system
To
which
Work will
hasbebeen
returned
locked-out
to JV can
for archiving
be given
(in case of Electrical Clearance
Certificate)
SPF TKP OMIFPRO SNC
Sur Site
22
Thank You