Dedicated Car Park For Electric Cars Powered by Solar: Group G
Dedicated Car Park For Electric Cars Powered by Solar: Group G
Group G
Project Outline
Dedicated car parking for electric cars with charging
points
Covered to provide comfortable environment for users
Addition of solar panels to provide power for use and
Council revenues
Grid connection and battery ready
Access controlled
Security Cameras
Amenities for users – eg vending machines.
Proposed Location
Easy Access
Close to CBD
Public Transport links to city
Mechanical design
A directly east or west facing panel will never operate at better than 85% of
its rated output. To put this in perspective, rather than generating the usual
4.5kWh average daily energy per 1kW of solar, the system will only produce
3.835kWh. For example, a 3kW system would lose a full 2kWh a day if it were
facing more east or west than north. This translates into a reduction in the
amount of savings that would other be possible.
Tilt frames that counteract a sub-optimal tilt and orientation will cost you a
little extra. How much will depend on how many panels make up the system,
and how the installer sources and prices the labour and parts required.
Curved panels
Advantages:
Improved efficiency
Avoided any need of tilting mechanism which decrease installation costs significantly
Parking space specification
Parallel parking
Charging points at the centre.
5m in length and 2.5 mts in width
Parking for 10 cars ,5 on either sides.
Charging Stations
Central Design
Standard Outlets
Access to the electric car park
Boom Gates
6m wide
Each for Entry and Exit
12Volt -Solar Powered Boom Gate
Access Cards
2 Vending machines
Snacks and Drinks
For refreshment purposes
Key days and milestone
Activity Start date Duration(days) End date
Project start 05/03/2018
1. Pre-Construction Task 05/03/2018 28 02/04/2018
SAPN Approvals 05/03/2018 1 06/03/2018
Site Surveyors 06/03/2018 21 27/03/2018
Materials to Site 27/03/2018 6 02/04/2018
2. Construction 03/04/2018 77 19/06/2018
Initial Groundworks 03/04/2018 14 17/04/2018
Cable Install 17/04/2018 14 01/05/2018
Second Phase Ground Works 01/05/2018 7 08/05/2018
Second Materials Delivery 06/05/2018 7 13/05/2018
Mechanical Construction 08/05/2018 14 22/05/2018
Boom Gates 08/05/2018 7 15/05/2018
Second Phase Electrical 22/05/2018 14 05/06/2018
Commissioning 05/06/2018 14 19/06/2018
3. All Stages 05/03/2018 119 02/07/2018
Project Manager 05/03/2018 119 02/07/2018
Site Security 27/03/2018 97 02/07/2018
Safety Manager 27/03/2018 97 02/07/2018
Weather delay 19/06/2018 14 02/07/2018
4. Project End 02/07/2018
Project Schedule
05/03/... 19/03/... 02/04/... 16/04/... 30/04/... 14/05/... 28/05/... 11/06/... 25/06/...
Pre-Construction ...
SAPN Appro...
Site Surve...
Materials to ...
Construc...
Initial Groundw...
Cable Ins...
Second Phase Ground W...
Scond Materials Deli...
Mechanical Construct...
Boom G...
Second Phase Electr...
Commissio...
All St...
Project Man...
Site Secu...
Safety Man...
Weather d...
Project...
Risk management
Environmental Impact
Resource Effort Rate Approximate Cost
Cost
Project Manager 18 wks $2500/wk $45000
Safety Officer 18 wks $2000/wk $36000
- First Aid Equipment
- Fire safety tools
Site Security 15wks $3000/wk $45000
SAPN Approval 1 day N/A N/A
- Permission Grant
Surveyor : 2 wks $2000/wk $4000
Enviromental impact report
General Surveying
Earth Works $12000
3 wks $4000/wk $12000
Steel fixing $8000
2 wks $4000/wk $8000 Subtotal $26549
Solar Panels 180 panels $250/each $45000
5
Extras $5000 Contingency Cost Through 15% $37424
Electrical Installs $5000 out
4 Wks $5000/wk $20000 Project
Temporary/Permanent Fencing 110m $17 / m $1870 TOTAL COST $303120
Portable Restroom 15 wks $50 / wk $750
Site Security / Management Building 15 wks $125 / wk $1875
Security Gates / Boom Gates 2 gates $2500 $5000
1Wk $2000/wk $2000
Security Camera $3000 $3000
1Wk $3000/wk $3000
Vending Machines 2 No $1500 each $3000
2 day $100/day $200
Future Scope
Repeatability : Success of design can be
repeated at alternative locations