Update Report

• DEVV as of March 13, 2020

Units Below 10% 5.00


Between 10% to 50% 8.00
Between 50% to 90% 9.00
Above 90% 4.00
Total 26.00
BLK 1 LT 16
To – Date %age 69.54%
Contractor (Engr.
Ryan Zaragosa)
‘- the plan is already in
17 steps and there are
changes but the
orientation of the plan
and its perspective
doesn’t match, so the
site asked for another
plan and this plan is not
in 17 steps rather in 14
steps, so all the changes
for the 17-steps doesn’t
met.
‘- 2nd plan followed but
the door rooms are
already changed but the
steps cannot turn to 17
steps.
BLK 6 LT 17
To – Date %age 26.86%
Foreman James
Talosig
‘- starting their 2F CHB Laying

‘- for follow up the roof framing


and roofing materials
‘- for follow up the tiles and
painting materials
BLK 7 LT 4
To – Date %age 87.48%
Foreman Herman
- Final painting and
tiles installation,
- Plumbing fixtures
installation
BLK 7 LT 15
To – Date %age 17.29%
Contractor (Engr.
Ryan Zaragosa)
-for second floor
preparation concrete
slab
BLK 8 LT 4
To – Date %age 96.77%
Foreman Manuel
- Final coating,
grouting and cleaning
BLK 8 LT 8
To – Date %age 54.67%
Foreman Manuel
- Waiting for the
delivery of roofing
materials
BLK 9A LT 6
To – Date %age 60.77%
Foreman Manuel
‘- problem is the plastering at the
left side firewall for there is a
structure of the next block
‘- changes of the aircon hole
requested by the owner, will be
checked when we resumed our
operation
BLK 9A LT 10
To – Date %age 60.77%
Foreman Manuel
‘- as of now no work has been
done because of the units we
need to deliver for this month and
the next month
BLK 9B LT 3
To – Date %age 100.00%
Contractor (Engr.
Ryan Zaragosa)
READY FOR TURN-OVER
BLK 9B LT 8
To – Date %age 96.36%
Foreman Herman
‘- follow up the sliding window
and door
‘- tiles are already done

‘- painting works interior, primer


application, 2 weeks the unit are
for turn – over
BLK 9B LT 9
To – Date %age 85.33%
Foreman Herman
‘- tile installation
painting works are
started
BLK 9B LT 10
To – Date %age 8.70%
Foreman Herman
‘- GF CHB Laying and
preparing for the
concreting of slab on
fill
BLK 9B LT 10
To – Date %age 14.82%
Foreman Herman
‘- Preparation for the
2F Slab concreting, no
enough manpower to
finish the work
(Carpenters)
BLK 9B LT 13
To – Date %age 69.94%
Foreman Herman
-Painting works and
Tile Works (waiting for
the delivery),
Plumbing works
BLK 10a LT 12
To – Date %age 96.66%
Foreman James
-Final Coating,
checking for the
plumbing works as
this is done by the
contractor
BLK 10a LT 13
To – Date %age 100 %
Foreman James
- Cleaning, ready for
turn-over
BLK 10b LT 11
To – Date %age 87.63%
Foreman Herman
‘- finishing painting is about to
finish
‘- follow up for sliding door and
window
‘- follow up for the remaining riles
needed
BLK 11 LT 9
To – Date %age 49.69%
Foreman James
‘- continuation of plastering

‘- installation of roofing materials

‘- follow up for the tiles and


paining materials
BLK 11 LT 10
To – Date %age 54.85%
Foreman James
‘- ready to accept paint

‘- follow up for the tiles and


painting materials
BLK 11 LT 12
To – Date %age 91.7809%
Foreman James
‘- additional painting materials are
need for the exterior paint
‘- ready for turn over (1 week
after the resume of the operation)
BLK 11 LT 18
To – Date %age 24.7640%
Foreman James
‘- preparation for 2F
slab
Steel decking are
already installed
Rebars are already
installed
Plumbing and
electrical already
installed
 
The schedule for
concrete pouring is
not yet finalize
BLK 11 LT 19
To – Date %age 25.8260%
Foreman James
‘- preparation for 2F slab
 Steel decking are already
installed
 Rebars are already installed
 
The schedule for concrete
pouring is not yet finalize
BLK 11 LT 20
To – Date %age 22.1448%
Foreman James
‘- preparation for 2F Slab
- Scaffolding installation
- Steel decking installation
not yet finish
BLK 11 LT 21
To – Date %age 21.2689%
Foreman James
‘- backfilling for almost 90%
‘- scaffolding fabrication started
 
Other Units
Block & Lot Status
Blk 10a Lt 14 - Excavation is done
- Column footing rebars are fabricated
and installed
Blk 10a Lt 15 - Excavation is done
Blk 10b Lt 14 - Excavation is done
Blk 12 Lt D - Clearing on going