The document provides an update on the progress of various construction projects, reporting the percentage completed for each block and lot. It notes that 5 units are below 10% complete, 8 are between 10-50%, 9 are between 50-90%, and 4 are above 90% complete. The summaries for each block and lot detail the current construction activities and any issues being addressed, such as material delays or design changes.
The document provides an update on the progress of various construction projects, reporting the percentage completed for each block and lot. It notes that 5 units are below 10% complete, 8 are between 10-50%, 9 are between 50-90%, and 4 are above 90% complete. The summaries for each block and lot detail the current construction activities and any issues being addressed, such as material delays or design changes.
The document provides an update on the progress of various construction projects, reporting the percentage completed for each block and lot. It notes that 5 units are below 10% complete, 8 are between 10-50%, 9 are between 50-90%, and 4 are above 90% complete. The summaries for each block and lot detail the current construction activities and any issues being addressed, such as material delays or design changes.
Between 10% to 50% 8.00 Between 50% to 90% 9.00 Above 90% 4.00 Total 26.00 BLK 1 LT 16 To – Date %age 69.54% Contractor (Engr. Ryan Zaragosa) ‘- the plan is already in 17 steps and there are changes but the orientation of the plan and its perspective doesn’t match, so the site asked for another plan and this plan is not in 17 steps rather in 14 steps, so all the changes for the 17-steps doesn’t met. ‘- 2nd plan followed but the door rooms are already changed but the steps cannot turn to 17 steps. BLK 6 LT 17 To – Date %age 26.86% Foreman James Talosig ‘- starting their 2F CHB Laying
‘- for follow up the roof framing
and roofing materials ‘- for follow up the tiles and painting materials BLK 7 LT 4 To – Date %age 87.48% Foreman Herman - Final painting and tiles installation, - Plumbing fixtures installation BLK 7 LT 15 To – Date %age 17.29% Contractor (Engr. Ryan Zaragosa) -for second floor preparation concrete slab BLK 8 LT 4 To – Date %age 96.77% Foreman Manuel - Final coating, grouting and cleaning BLK 8 LT 8 To – Date %age 54.67% Foreman Manuel - Waiting for the delivery of roofing materials BLK 9A LT 6 To – Date %age 60.77% Foreman Manuel ‘- problem is the plastering at the left side firewall for there is a structure of the next block ‘- changes of the aircon hole requested by the owner, will be checked when we resumed our operation BLK 9A LT 10 To – Date %age 60.77% Foreman Manuel ‘- as of now no work has been done because of the units we need to deliver for this month and the next month BLK 9B LT 3 To – Date %age 100.00% Contractor (Engr. Ryan Zaragosa) READY FOR TURN-OVER BLK 9B LT 8 To – Date %age 96.36% Foreman Herman ‘- follow up the sliding window and door ‘- tiles are already done
‘- painting works interior, primer
application, 2 weeks the unit are for turn – over BLK 9B LT 9 To – Date %age 85.33% Foreman Herman ‘- tile installation painting works are started BLK 9B LT 10 To – Date %age 8.70% Foreman Herman ‘- GF CHB Laying and preparing for the concreting of slab on fill BLK 9B LT 10 To – Date %age 14.82% Foreman Herman ‘- Preparation for the 2F Slab concreting, no enough manpower to finish the work (Carpenters) BLK 9B LT 13 To – Date %age 69.94% Foreman Herman -Painting works and Tile Works (waiting for the delivery), Plumbing works BLK 10a LT 12 To – Date %age 96.66% Foreman James -Final Coating, checking for the plumbing works as this is done by the contractor BLK 10a LT 13 To – Date %age 100 % Foreman James - Cleaning, ready for turn-over BLK 10b LT 11 To – Date %age 87.63% Foreman Herman ‘- finishing painting is about to finish ‘- follow up for sliding door and window ‘- follow up for the remaining riles needed BLK 11 LT 9 To – Date %age 49.69% Foreman James ‘- continuation of plastering
‘- installation of roofing materials
‘- follow up for the tiles and
paining materials BLK 11 LT 10 To – Date %age 54.85% Foreman James ‘- ready to accept paint
‘- follow up for the tiles and
painting materials BLK 11 LT 12 To – Date %age 91.7809% Foreman James ‘- additional painting materials are need for the exterior paint ‘- ready for turn over (1 week after the resume of the operation) BLK 11 LT 18 To – Date %age 24.7640% Foreman James ‘- preparation for 2F slab Steel decking are already installed Rebars are already installed Plumbing and electrical already installed
The schedule for concrete pouring is not yet finalize BLK 11 LT 19 To – Date %age 25.8260% Foreman James ‘- preparation for 2F slab Steel decking are already installed Rebars are already installed
The schedule for concrete pouring is not yet finalize BLK 11 LT 20 To – Date %age 22.1448% Foreman James ‘- preparation for 2F Slab - Scaffolding installation - Steel decking installation not yet finish BLK 11 LT 21 To – Date %age 21.2689% Foreman James ‘- backfilling for almost 90% ‘- scaffolding fabrication started
Other Units Block & Lot Status Blk 10a Lt 14 - Excavation is done - Column footing rebars are fabricated and installed Blk 10a Lt 15 - Excavation is done Blk 10b Lt 14 - Excavation is done Blk 12 Lt D - Clearing on going