CREW 3 AND 4 WEEKLY DRILLING REVIEW

PERFORMANCE

FROM 10TH TO 16TH AUGUST 2020

8/18/20 BATHSHEBAH MUMBI NAYAME


CREW 3 WEEKLY DRILLING PERFORMANCE
CREW 3 Drilling Production Drill Rig Utilisation
3,000

2,500 80%

70%
2,000
60%
1,500
2,467 50%
1,000 40%
1,381 1,543
500 1,046 30%

0 20%
Dat 13th 14th 15th 16th
10%
es Flushing Redrills Boulders
PresplitDrilling ProductionDrilling Budget 0%
Daily Call Linear (Daily Call) 13th 14th 15th 16th

DRILLED METERS
CREW 3 UTILISATION FACTORS
  Actual Budget 100
Total meters drilled 9,008 10,679 80
Production drill meters 6,435 7,910 60
92 86
Pre-split, (m) 957 791 40 74
54
Re-drills (m) 1,525 20
1978 0
Flushing 701 13th 14th 15th 16th
Boulders 91 Dates
Average Penrate (meters/hour) 31 27 incident blasting general breakdowns Await Tram No Drilling Area

8/18/20 2
CREW 4 WEEKLY DRILLING PERFOMANCE
100% Drill Rig Utilisation
CREW 4 Drilling Production 90%
4,500 80%
4,000 70%
3,500 60%
3,000 50%
2,500 40%
2,000 3,817 30%
1,500
2,348 20%
1,000 2,206
10%
500
0 0%
10th 11th 12th
10th 11th 12th
Dates

Flushing ProductionDrilling Budget


Daily Call

CREW 4 DRILLED METERS


  Actual Budget CREW 4 UTILISATION FACTORS
Total meters drilled 8,872 8,010 100
Production drill meters 8,371 5,934 80
Pre-split, (m) 501 593 60
Re-drills (m)   87
40 69
81
Flushing   1,483
Boulders   20
Drilled BCM     0
10th 11th 12th
Average Penrate (meters/hour) 30 27
Dates
general breakdowns Await Tram No Drilling Area

BATHSHEBAH MUMBI NAYAME 3


RECOMMENDATIONS
Expedite free face shots
clean ups to be done in good time
for drilling areas
we continue using the rock breaker on boulders
plan nicely for relocations
low beds should always be available for tramming
8/18/20 . 4