08/19/20 nsi-ikpt 1

List of Content,

1.Update Progress February 03, 2020


2.Hydro Test Readiness of ISBL
3.Material Status List
4.Readiness to start OSBL

08/19/20 nsi-ikpt 2
SUMMARY SCHEDULE

2. OSBL AREA

08/19/20 nsi-ikpt 3
SUMMARY SCHEDULE

1. ISBL AREA

08/19/20 nsi-ikpt 4
1. Progress Achievment per January 23, 2020

- Plan Actual Progress Achievement,


i-III Project Nippon Shokubai Indonesia
Field Erected Tank
Cilegon,Banten - Indonesia

OWNER : PT.NIPPON SHOKUBAI INDONESIA


CLIENT : PT.INTI KARYA PERSADA TEHNIK
SUBCONTRACTOR : PT. CAHAYA HIDUP PRIMAKARYA
PROJECT TITLE : NSI - Field Erected Tank
LOCATION : Cilegon - Banten

SUMMARY OVERALL PROGRESS


Asper To February 03, 2020

Last Week This Week Commulative


No. Work Item Plan Actual Var. Plan Actual Var. Plan Actual Var. Remark
A B C = B-A A B C = B-A A B C = B-A

1 Field Erected Tank 41,62% 34,76% -6,87% 5,41% 1,16% -4,25% 47,03% 35,92% -11,12%

TOTAL 47,03% 35,92% -11,12%

08/19/20 nsi-ikpt 5
Status Tank per February 03, 2020

- Status Tank

08/19/20 nsi-ikpt 6
Curve S ISBL Area per February 03, 2020

08/19/20 nsi-ikpt 7
Curve S OSBL Area per February 03, 2020

08/19/20 nsi-ikpt 8
2. Hydro Test Readiness of ISBL Tank

- Readiness List of ISBL tank to be tested

08/19/20 nsi-ikpt 9
3. Material Status Summary List

- Material summary list status of all tank

08/19/20 nsi-ikpt 10
4. Readiness to start OSBL
1. CHECKLIST READINESS FOR HYDROTEST AV 1139C

Fabrikasi Installasi
Qty
NO TANK NAME Qty Delivery Completed Date REMARKS
Delivered Fit Up Welding
Mark/Cutting Fit Up Welding
Qty Progress Qty Progress

1 Bottom Plate 100% 100% 100% Done 100% Done 100%


Waiting Material Nozzle (ETA Site 23
2 Shell Plate 100% 100% 100% Done 100% Done 100% Finish Assembly
January 20)
3 Roof Plate 100% 100% 100% Done 100% Done 100%

2. CHECKLIST READINESS FOR HYDROTEST AV 1119D

Fabrikasi Installasi
Qty
NO TANK NAME Qty Delivery Fit Up Welding Completed Date REMARKS
Mark/Cutting Fit Up Welding Delivered
Qty Progress Qty Progress

1 Bottom Plate 100% 100% 100% ETA Site 3 feb 20


(material 10"=15, 12"=3, 8"=6) Already
2 Shell Plate 69% 69% 69%
KARINDA
3 Top Angel 0% 0% 0% ETA Site 3 feb 20

08/19/20 nsi-ikpt 11
4. Readiness to start OSBL

3. CHECKLIST READINESS FOR HYDROTEST AV 3100B

Fabrikasi Installasi
Qty
NO TANK NAME Qty Delivery Fit Up Welding Completed Date REMARKS
Mark/Cutting Fit Up Welding Delivered
Qty Progress Qty Progress

1 Bottom Plate 0% 0% 0%
Start Fabricate : 02 Feb 20 at Karinda
2 Shell Plate 0% 0% 0%
Workshop
3 Roof Plate 0% 0% 0%

4. CHECKLIST READINESS FOR HYDROTEST UV 2081

Fabrikasi Installasi
Qty
NO TANK NAME Qty Delivery Completed Date REMARKS
Delivered Fit Up Welding
Mark/Cutting Fit Up Welding
Qty Progress Qty Progress

1 Bottom Plate 0% 0% 0%
2 Shell Plate 0% 0% 0% Material At Workshop Karinda
3 Roof Plate 0% 0% 0%

08/19/20 nsi-ikpt 12
4. Readiness to start OSBL

5. CHECKLIST READINESS FOR HYDROTEST UV 2083

Fabrikasi Installasi
Qty
NO TANK NAME Qty Delivery Fit Up Welding Completed Date REMARKS
Mark/Cutting Fit Up Welding Delivered
Qty Progress Qty Progress

1 Bottom Plate 100% 100% 100%


Material already at Karinda Workshop
2 Shell Plate 100% 100% 100%
ETA Site : 27 Jan 20
3 Roof Plate 100% 100% 100%

6. CHECKLIST READINESS FOR HYDROTEST UV 2100A

Fabrikasi Installasi
Qty
NO TANK NAME Qty Delivery Fit Up Welding Completed Date REMARKS
Mark/Cutting Fit Up Welding Delivered
Qty Progress Qty Progress

1 Bottom Plate 100% 100% 100%


Material already at Karinda Workshop
2 Shell Plate 100% 100% 100%
ETA Site : 27 Jan 20
3 Roof Plate 100% 100% 100%

08/19/20 nsi-ikpt 13
5. Foto Graph

                                   
         
         
         
         
         
         
         
         
         
         
                                   
Welding Nozzle to Shell AV 3114 Fit Up Pad Manhole Shell AV 3114 Fit Up Horizontal Shell 5-6 AV 3133A
                                   
       
       
       
       
       
       
       
       
       
       
                                   
Install Alco Foam AV 3116 Cleaning Tag Weld Roof to Shell AV 3116 Welding Bottom AV 3100B

08/19/20 nsi-ikpt 14
5. Foto Graph

Welding Center Drum AV 3116 Cleaning Welding Manhole AV 3100A Welding Pad Alco Foam AV 3115

Fit Up Manhole AV 3115 Welding Pad Manhole Shell AV 3113 Prepare Laying Shell 9 AV 3611A