Progress for Daltenganj Circle under IPDS as on 12.06.

2020
(Towns – Daltenganj, Hussainabad, Bishrampur & Latehar)
Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)
Cost of Work: Rs. 75.52 Cr. LOA date: 09.05.2017 Target Completion Month: January, 20
Cumulative
Total Cumulative Achieved in
Sl. Progress in Balance
Activity Unit Required Progress upto June'20 till Charged WIP
No June'20 till Work
Quantity May'20 date
date

33/11kV PSS (2X5 MVA)

1 - Daltenganj Town – At DAV Engg. College Nos 2 2 2 2


- Latehar Town – At Govt. Poly. College,
Rahera

Additional PTR (10 MVA)


2 Nos 2 2 2 2
- Daltonganj Town – Redma PSS
- Latehar Town – Latehar PSS

Aug. of PSS (5 MVA to 10 MVA)

- Daltonganj Town – Sudna PSS


3 Nos 4 4 4 4
- Hussainabad Town – Deori PSS
- Bishrampur Town – Rehla PSS
Progress for Daltenganj Circle under IPDS as on 12.06.2020
(Towns – Daltenganj, Hussainabad, Bishrampur & Latehar)
Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)

Cost of Work: Rs. 75.52 Cr. LOA date: 09.05.2017 Target Completion Month: January, 20

Cumulative
Total Cumulative Achieved in
Sl. Progress in Balance
Activity Unit Required Progress upto June'20 till Charged WIP
No June'20 till Work
Quantity May'20 date
date

PSS R &M

- Daltonganj Town – Sudna PSS


4 Nos 4 4 4 4
- Hussainabad Town – Deori PSS
- Bishrampur Town – Rehla PSS
- Latehar Town – Latehar PSS

5 33kV New Line CKms 27.507 25.707 25.707 3.2 1.8

6 33kV UG Cable CKms 0.665 0.665 0.665 0.165

7 33kV Re-conductoring CKms 12.425 10.7 10.7 10.7 1.725 1.525


Progress for Daltenganj Circle under IPDS as on 12.06.2020
(Towns – Daltenganj, Hussainabad, Bishrampur & Latehar)

Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)

Cost of Work: Rs. 75.52 Cr. LOA date: 09.05.2017 Target Completion Month: January, 20

Cumulative
Total Cumulative Achieved in
Progress in Balance
Sl. No Activity Unit Required Progress upto June'20 till Charged WIP
June'20 till Work
Quantity May'20 date
date

8 11kV New Line CKms 43.343 37.343 0.347 37.69 23.598 5.653 2.908

9 11kV UG Cable CKms 2.37 2.37 2.37 0.48

10 11kV Re-conductoring CKms 59.441 54.002 54.002 54.002 5.439

11 11/0.433kV New DTR Nos 163 163 163 160


Progress for Daltenganj Circle under IPDS as on 12.06.2020
(Towns – Daltenganj, Hussainabad, Bishrampur & Latehar)

Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)

Cost of Work: Rs. 75.52 Cr. LOA date: 09.05.2017 Target Completion Month: January, 20

Cumulative
Total Cumulative Achieved in
Progress in Balance
Sl. No Activity Unit Required Progress upto June'20 till Charged WIP
June'20 till Work
Quantity May'20 date
date

12 11/0.433kV Aug DTR Nos 86 86 86 86

13 R & M of DSS Nos 104 101 101 101 3

14 LT Line through AB Cable CKms 284.176 284.176 284.176 249.2

15 Metering Nos 5260 4459 8 4467 4467 793

16 Solar Panel Nos 22 22 22 22


Details Break up of Balance Work for Daltenganj Circle under IPDS
(Towns – Daltenganj, Hussainabad, Bishrampur & Latehar)

Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)

Sl. ROW Issues / Pending


Name of Activity Unit Balance
No Details of Work Clearances
Town     Work
 
From Existing Sudna GSS to New 33/11kV Pokhra PSS
Name of Feeder - Sudna

33kV New 1. Dubhiyakhad (Jhorkut) – 1.2 CKM ROW due to public hindrance for
1 CKms 1.8
Line 1.8 CKM line.
2. Near Heritage School – 0.3 CKM
3. Existing Sudna GSS to New 33/11kV Pokhra PSS – 0.3 CKM

Daltenganj From New 33/11kV Pokhra PSS to Ranchi Road


11kV New Name of Feeder – Town Feeder ROW due to public hindrance for
2 CKms 1.2
Line 1.2 CKM line.
Dubhiyakhad (Jhorkut) – 1.2 CKM

3 Meters Nos. 713 Meter Replacement under Progress. Location identification is an issue.
Details Break up of Balance Work for Daltenganj Circle under IPDS
(Towns – Daltenganj, Hussainabad, Bishrampur & Latehar)
Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)

Sl.
Name of Activity Unit Balance
No Details of Work ROW Issues / Pending Clearances
Town     Work
 

Deori Feeder:
33kV Re-
4 CKms 1.525
conductoring
Location - Deori PSS to Ahara locality

Hussainabad Existing Town Feeder:

Location: Gamaria to Mohamdabad – 0.8 CKM ROW issue in Biswanath Hata – 1.739 CKM
11kV Re-
5 CKms 3.339 Mohamdabad to Duttanagar – 0.5 CKM (Objection from land owner)
conductoring
Near Mehedinagar – 0.3 CKM

Biswanath Hata – 1.739 CKM


Details Break up of Balance Work for Daltenganj Circle under IPDS
(Towns – Daltenganj, Hussainabad, Bishrampur & Latehar)
Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)
Sl.
Name of Activity Unit Balance
No Details of Work ROW Issues / Pending Clearances
Town     Work
 
New Town Feeder
At Japla Choubey, the ROW issue due to
Location: Japla Choubey Railway Line –
objection from land Owner for pole pitching (one
0.250 CKM
Side) & another side is Railway Line.
11kV New Line CKms 0.515
New Town Feeder
6 At Purandar Bigha, the ROW issue due to
Hussainabad Location: Purandhar Bigha – 0.265 CKM.
objection from land Owner (Agricultural land) for
Charging of 2nos. DTR held up due to ROW
pole pitching.
issue.

List available. Meter Replacement under


Meters Nos. 80
Progress.
7
Goderma Feeder
Objection from PWD Department regarding Tree
11kV New Line CKms 3.938 Location: B. More Chowk to Bishrampur Bus
– Trimming Issue. (Approx. 120 nos)
Stand
ROW issue due to public objection to uproot the
8 Bishrampur installed DP and creating hindrance for further
11kV Re- Rehla Feeder
conductor stringing & putting stay.
conductoring CKms 2.1
Location: B. More Chowk to Rehla PSS
Objection from PWD Department regarding Tree
– Trimming Issue. (Approx. 15 nos)
ROW due to public hindrance.
Location: Jahaz Kothi, Amba Kothi Mohallah
9 Latehar R & M of DTR Nos 3 3nos. Of DTR to be re-located. Alternate nearby
& Thana Chowk
location not available.
JMC Status for Daltenganj Circle as on 12.06.2020
(Towns – Daltenganj, Hussainabad, Bishrampur & Latehar)

  Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)


JMC Status
Total Required
Sl. No Activity Unit SOR SOR JMC
Quantity JMC Raised JMC Pending
Received Rectified Completed
1 33/11kV PSS (2X5 MVA) Nos 2 6 6 6 6
2 Additional PTR (10 MVA) Nos 2 3 3 2 3
3 Aug. of PSS (5 MVA to 10 MVA) Nos 4 4 3 3 1 3
4 PSS R &M Nos 4 4 3 2 1 3
5 33kV New Line CKms 27.507 3.1 3.1 3.1 3.1
6 33kV UG Cable CKms 0.665 0.165 0.165 0.165 0.165

7 33kV Line Re-conductoring CKms 12.425


8 11kV New Line CKms 43.343 24.63 22.46 22.46 2.17 22.46
9 11kV UG Cable CKms 2.37 1.04 1.04 0.96 0.6
10 11kV Line Re-conductoring CKms 59.441 51.482 43.707 43.707 7.775 43.707
11 11/0.433kV New DTR Nos 163 162 137 137 25 137
12 11/0.433kV Aug DTR Nos 86 86 70 70 16 70
13 R & M of DSS Nos 104 74 55 52 19 55
14 LT Line through AB Cable CKms 284.176 250.98 181.905 181.905 69.075 181.905
15 Metering Nos 5260 4176 701 701 3475 701
16 Solar Panel Nos 22 19 10 10 9 10