Professional Documents
Culture Documents
S104-PPT - Hydrostatic and Pneumatic Tests
S104-PPT - Hydrostatic and Pneumatic Tests
S104-PPT - Hydrostatic and Pneumatic Tests
8/29/20
Contents
hydraulic tests
pneumatic tests
Saipem Procedures
COR-CR-HSE-125-E
COR-CR-HSE-123-E
Safety Feedback
2
8/29/20 2
Hydrostatic & Pneumatic Test
Purpose of the course
The purpose of this course is to describe
the safety precautions to establish to
ensure that PRESSURE TESTS are
undertaken in a manner that both
personnel carrying out the works and
personnel working in surrounded area will
not be exposed to hazards which may
derive from this specific activity
3
8/29/20 3
Hydrostatic & Pneumatic Test
Introduction to pressure tests
4
8/29/20 4
Hydrostatic & Pneumatic Test
Objectives of pressure testing
These tests are performed in order to ensure tightness and mechanical
strength of piping, vessels and pressure systems prior to commissioning by
detecting and locating potential leaks
incomplete welds
wrong pipes
wrong fittings
loose flanges
damaged fittings
5
8/29/20 5
Hydrostatic & Pneumatic Test
Warning…
EXPECT FAILURES!!!
6
8/29/20 6
Hydrostatic & Pneumatic Test
Pressure Test: Hydraulic vs. Pneumatic
2 MAIN DIFFERENT TYPOLOGY OF PRESSURE TEST EXIST:
HYDRAULIC TEST
PNEUMATIC TEST
7
8/29/20 7
Hydrostatic & Pneumatic Test
Hydraulic Tests
Hydraulic Tests are used for confirming mechanical integrity of installed
pressure vessels and pipe lines before put it in use
according to “ASME Section VIII Division I”, hydraulic tests are conducted at
the pressure of 1.5 times design pressure
8
8/29/20 8
Hydrostatic & Pneumatic Test
Pneumatic Tests
Pneumatic Tests have the same purpose of Hydraulic Test
9
8/29/20 9
Hydrostatic & Pneumatic Test
Hydro or Pneumatic tests???
Pneumatic tests are inherently more dangerous than Hydro Tests!
its instantaneous release works as a bomb and may cause severe damage to
persons and equipment
8/29/20 11
Hydrostatic & Pneumatic Test
Potential hazard for Pressure testing
Main HAZARDS are:
MISSILES
rupture of an equipment part under test can result in fragments projection
potentially leading to personnel injuries and equipment/structure damage
12
8/29/20 12
Hydrostatic & Pneumatic Test
Potential hazard for Pressure testing
BLAST OVER PRESSURE
rupture of a line and/or capacity can generate a shock wave (a pressure wave
which moves at supersonic speeds) which can be hazardous for personnel
working around and surrounding equipment and structures
13
8/29/20 13
Hydrostatic & Pneumatic Test
GAS JET
Potential hazard for Pressure testing
effects of blast wave and fragments are obvious and well known; the effect of
the gas jet is less common; it results from the emptying of the equipment and
the release of the pressurised gas; a thrust effect is also generated by the
release of the gas; this could lead to the displacement of the equipment being
tested:
translation/lifting of the vessel
whipping effect of a pipe
14
8/29/20 14
Hydrostatic & Pneumatic Test
Be aware!
ABSOLUTELY YES!
15
8/29/20 15
Hydrostatic & Pneumatic Test
Vacuum
16
8/29/20 16
Hydrostatic & Pneumatic Test
Safety precaution for pressure testing
COR-CR-HSE-125-E
COR-CR-HSE-123-E
17
8/29/20 17
Corporate Criteria: Hydro Testing
18
8/29/20 18
Hydrostatic & Pneumatic Test
Hydro Testing: Roles and Responsibilities
SUBCONTRACTOR
shall develop comprehensive Testing Procedures that address the safety
of all personnel and include the provision of specific Work Instructions
and related Training and/or induction for all personnel involved in
testing operations
the Training and Induction log shall be maintained and an identification
mark for the helmet shall be provided only to qualified personnel for the
execution of hydraulic tests
SAIPEM CONSTRUCTION MANAGER
responsible for ensuring the project safety requirements and specific
safety issues related to the activity considered
SAIPEM CONSTRUCTION MECHANICAL SUPERVISOR
responsible for ensuring the compliance with the established schedule,
project and safety requirements
19
8/29/20 19
Hydrostatic & Pneumatic Test
Hydro Testing: Roles and Responsibilities
20
8/29/20 20
Hydrostatic & Pneumatic Test
Hydro Testing: Roles and Responsibilities
21
8/29/20 21
Hydrostatic & Pneumatic Test
Preparation for Testing, notification and documentation
the SCTS and the CTS shall submit to the Contractor Site Manager (SM) and
to the Field HSE Manager (FHSEM) on site a written detailed “Hydraulic
Testing Report” which fully describes the methods, equipment and
precautions to be used
this procedure shall incorporate Job Safety Analysis (JSA), applicable local
safety regulations and include personnel training and certification, test
equipment and specifications
Hydraulic Testing Operations shall not start until approval of the
procedure document has been given by SM / FHSEM on site
before starting the hydraulic test activity Construction personnel have to
prepare dedicated P&ID in which the pipes to be pressure tested have to be
highlighted
this P&ID must be attached to the Work Permit together with the JSA.
22
8/29/20 22
Hydrostatic & Pneumatic Test
Hydro Testing: test execution
joints
8/29/20 23
Hydrostatic & Pneumatic Test
Hydro Testing: SAFETY BULLETTIN
PIPE FITTER SEVERELY INJURED TO HEAD BY A HIGH PRESSURE WATER JET
suddenly a high pressured water jet came out from pipe through the flange joint
as confirmed by the inspection of the temporary gaskets, after dismantling of the
pipe spool, the temporary gasket broke and through the crack a high pressure
(1500 Psi) water came out
the high pressure water with a piece of gasket hit the victim‘s face & fore head
causing severe injury to the victim’s head
24
8/29/20 24
Hydrostatic & Pneumatic Test
Hydro Testing: Safety instruction
GENERAL INSTRUCTION
25
8/29/20 25
Hydrostatic & Pneumatic Test
Hydro Testing: Safety instruction
NOTIFICATION
Before starting any operation, the Construction
personnel responsible of hydrotest has to give
notification to all people present at site
26
8/29/20 26
Hydrostatic & Pneumatic Test
Hydro Testing: Safety instruction
27
8/29/20 27
Hydrostatic & Pneumatic Test
Hydro Testing: Safety instruction
SAFETY REQUIREMENTS
28
8/29/20 28
Hydrostatic & Pneumatic Test
Hydro Testing: Safety instruction
8/29/20 29
Hydrostatic & Pneumatic Test
Hydro Testing: Safety instruction
SAFETY ACTIVITIES
CTS for the hydrotest has to carry out the following activities:
a) suspend all activities inside the barricaded area when the activity is being
executed
b) verify, prior to filling columns/drums/vessels or overhead piping systems
with water, if those items and their foundations/supports to withstand full
water weight
c) verify that all people involved in the activity wear appropriate Personal
Protective Equipments (PPE)
d) in addition to PPE required to the normal activity inside the plant it is
mandatory use the following personal protections
e) the persons directly involved at the discharge point shall use proper goggles
and gloves
8/29/20 30
Hydrostatic & Pneumatic Test
Hydro Testing: Safety instruction
f) if the hydrotest is used the operator must use an overall rubber protection,
face shield, gloves and rubber boots
i) make sure that the water to be discharged has the quality parameters
complied with standard fixed by Client
8/29/20 31
Hydrostatic & Pneumatic Test
Hydro Testing: check list
Check List:
Hydrostatic test pressure and temperature standard are already clearly
2. defined in the related document. Supported documents such as P&ID and
isometric drawing are available and conform to as built facilities at the field.
Pressure test planning has to be distributed to all relevant sections in the
3. site at least 24 Hrs before the execution date.
All test equipments and tools shall be inspected for wear and damage.
4. Pressure gauges used in the test have enough capacity and properly
calibrated.
Pressure gauges must be installed at a proper location so that it can be
5. easily read and do not create additional hazards to the hydrostatic test or
expose personnel to the vessel being tested.
All the temporary tools (such as valve, fitting, hoses, flanges, blind plate,
6. etc) have to be rated more than the maximum hydrostatic pressure
Isolate other equipments and pipe lines that do not include in the
7. hydrostatic test
Vents are available and installed the high points to vent air Check the vent
8. line before testing and make sure it is not blocked.
Choose drain valve at the lowest point in order to completely empty the
9. vessel and pipe
Safety relief valve is already installed. Safety relief valve setting is 1.5
10. times maximum allowable working pressure
Isolate the test area and surround it with safety line. Put appropriate safety
11. sign at that area
Make sure that all pipe and vessel supports are in good condition and have
12. been inspected.
32
8/29/20 32
Hydrostatic & Pneumatic Test
Hydro Testing: check list
Safety relief valve is already installed. Safety relief valve setting is 1.5 times
10. maximum allowable working pressure
Isolate the test area and surround it with safety line. Put appropriate safety
11. sign at that area
Make sure that all pipe and vessel supports are in good condition and have
12. been inspected.
Remove all air from the vessel and pipe line by water through vent line
16.
After completing the test ,open the lowest drain point to completely remove
18. water from the vessel / pipeline.
33
8/29/20 33
Hydrostatic & Pneumatic Test
Requirements for pneumatic & high-pressure hydrostatic
tests
the requirements above described are not applicable to pneumatic tests and
high-pressure hydraulic tests
these tests require to prepare a dedicated procedure for the project that
includes all of the special safety requirements and ASME B31.1 or ASME
B31.3 rules (as applicable)
34
8/29/20 34
Corporate Criteria: Pneumatic test
this philosophy defines the requirements for pneumatic pressure testing (or
pneumatic leak testing) of above ground systems (applicable to piping and
piping systems within the scope of ASME B31.3, “Process Piping”)
this document covers the application, preparation and procedure for
pneumatic testing in the field
Considering the high risks for pneumatic test execution following instruction
must be strictly respected!
35
8/29/20 35
Hydrostatic & Pneumatic Test
Pneumatic Testing: Roles and Responsibilities
36
8/29/20 36
Hydrostatic & Pneumatic Test
Pneumatic Testing: Documentation
37
8/29/20 37
Hydrostatic & Pneumatic Test
Pneumatic Testing: Documentation
38
8/29/20 38
Hydrostatic & Pneumatic Test
Pneumatic Testing: Documentation
the pneumatic test on any test assembly may not proceed until the
possession of the authorization form for that assembly, signed by PM-C and
FHSEM
39
8/29/20 39
Hydrostatic & Pneumatic Test
Pneumatic Testing: Equipment and materials
– pressure gauges
– temperature measuring devices
– recording instruments
– valves
– pipe work
– hoses
for each test
All the above items must be properly tested, calibrated and certified!
40
8/29/20 40
Hydrostatic & Pneumatic Test
Pneumatic Testing: Safety Concern/Exclusion Zone
Contractor shall:
41
8/29/20 41
Hydrostatic & Pneumatic Test
Pneumatic Testing: Safety Concern/Exclusion Zone
Exclusion zones shall be considered here as the minimum distance beyond which:
42
8/29/20 42
Hydrostatic & Pneumatic Test
Pneumatic Testing: Safety Concern/Exclusion Zone
Outside the exclusion zones, minor injuries can still occur to personnel
43
8/29/20 43
Hydrostatic & Pneumatic Test
Pneumatic Testing: Mitigation/Protection Measures
–test operators must wear appropriate PPE (eye and ear protection)
–resistant shelter
–protective shield
44
8/29/20 44
Hydrostatic & Pneumatic Test
Pneumatic Testing: Mitigation/Protection Measures
45
8/29/20 45
Hydrostatic & Pneumatic Test
Pneumatic Testing: Test Procedure
Testing shall not be undertaken when the weather conditions may give rise to large temperature fluctuation in a short
time; temperature of metal shall be taken to ensure that it is warmer that the minimum temperature allowed; after
evacuation of all personnel from the test area, air shall be slowly admitted to the test assembly until the pressure
attains the lesser of one-half of the required test pressure or 1.5 bar
46
8/29/20 46
Hydrostatic & Pneumatic Test
Pneumatic Testing: Test Procedure
all joints, flanges and welds shall therefore be tested by applying the soapy water
if any leak is found, the test shall be aborted and the leaks
repaired before recommencing the test
47
8/29/20 47
Hydrostatic & Pneumatic Test
Pneumatic Testing: Test Procedure
personnel performing tightening operations (if required) shall remain clear of the gasket plane
projection
48
8/29/20 48
Hydrostatic & Pneumatic Test
Pneumatic Testing: Test Procedure
this visual inspection shall be witnessed by the owner’s inspection or his delegated inspector
49
8/29/20 49
Hydrostatic & Pneumatic Test
Pneumatic Testing: Test Procedure
care shall be taken to avoid metal temperatures falling below minimum metal temperature (or 0°C), particularly near
fracture
50
8/29/20 50
Hydrostatic & Pneumatic Test
Pneumatic Testing: Repairs
if any leaks are found in a welded joint, they shall be repaired (after
depressurization) using an approved weld repair procedure and proved acceptable
by radiographic testing prior to repeating the pneumatic test
51
8/29/20 51
Hydrostatic & Pneumatic Test
Pneumatic Testing: Certification
Following successful test, the “Subcontractor execution responsible/Contractor Discipline SPT”
shall provide a test certificate for each test assembly
52
8/29/20 52
Hydrostatic & Pneumatic Test
Pneumatic Testing: Training and Communication
A dedicated training for pneumatic test will be held to all personnel involved
53
8/29/20 53
Hydrostatic & Pneumatic Test
Pneumatic Testing: Check list
S.No CHECKLIST YES NO
Subcontractor Responsible
1. Is there a method statement, risk assessment carried and permit to work system
carried out for the task?
5. All necessary piping and valves are correctly fitted between the air source and the
test assembly, and that depressurizing and relief facilities are in place.
6. All personnel not involved in the pneumatic test must leave the restricted area.
7.
All involved personnel must wear PPE
Are pneumatic and hydraulic hoses on power operated tools checked regularly for
8. deterioration or damage?
9. Pneumatic test planning has to be distributed to all relevant sections in the site at
least 24 Hrs before the execution date.
10. Make sure that all pipe supports are in good condition and have been inspected to
carry out the test
54
8/29/20 54
Hydrostatic & Pneumatic Test
Safety feedback
safety feedback
55
8/29/20 55
Safety feedback 1: Filling of a vertical tank with water
56
8/29/20 56
Safety feedback 2: Piping Pneumatic test
What happened
the tank “lifted off”
Why
leakage of air from the pipe to the
tank through the valve block
Fault analysis
a blind flange was NOT installed to
isolate the tank
Causes
lack of knowledge, Procedure and
check list outdated (do not meet
the design changes)
Image appear by courtesy of Exxon Company
57
8/29/20 57
Safety feedback 3: Emptying of a vertical tank
What happened
tank collapse during emptying
depressurizing operation
Why?
a plastic was trapped in the vent; a
vacuum was created.
Fault analysis
after setting up the pipeline operators
have started the pumps by remote
control located approximately 500
meters away from the tanks
Causes
lack of knowledge, lack of surveillance,
failure to comply procedure, poor
housekeeping Image appear by courtesy of
TotalFinaElf
58
8/29/20 58
Safety feedback 4: Pressure test incident
What happened
technician struck by a thermowell ejected from
a ¾’’ NPT female tapping in a 5K choke
manifold during a pressure test.
Why?
when the NPT thread failed the stored energy
was released and propelled the thermowell at
a velocity of 42 metres/sec (94 MPH).
Fault analysis
the technician was in front of the thermowell
tapping during the test .
Causes
lack of knowledge, failure to comply procedure,
incorrect position of the technician.
59
8/29/20 59
Conclusions and clarifications
Any question?
60
8/29/20 60