Professional Documents
Culture Documents
Basic Capacity Definitions
Basic Capacity Definitions
Impacted by:
Product specification
Product mix
Methods used to make product
Pace of work
Finding Capacity Available
Back scheduling (the typical approach) – Start with the due date, use
lead time to find the proper start date for each operation
Forward scheduling – Launch the order into the first (gateway) work
center, then use the lead times to find when the order will be completed
at each work center
Managing the Plan – Adjusting Capacity
Master
Planning Production
Scheduling
Material
Requirements
Planning
Input/
Output
Implement
Production Control
and
Purchasing Activity
Control
Control
Operation
Figure 6.1
Sequencing
Priority planning and production activity control
Scheduling
Move
Move
Queue Setup Run Wait
Example Problem
= 34 hours, 45 minutes
Scheduling Techniques
Forward Scheduling
Material 1st 2nd 3rd
Ordered Operation Operation Operation
Backward Scheduling
Capacity
Capacity Underload
Figure 6.5 Infinite load profile
Forward and Backward Scheduling:
Finite Load
Order Recieved Due Date
1 2 3 4 5 6 7 8 9
Forward Scheduling
Material 1st 2nd 3rd
Ordered Operation Operation Operation
Backward Scheduling
Capacity
Smoothed Load
Part A
OP 10 OP 20
X
Part B Assembly
OP 10
85 90 95 100
Working Days
Operation Overlapping
The next operation is allowed to begin before the entire
lot is completed
Reduces the manufacturing lead time
Order is divided into at least two transfer lots
Operartion A
SU Lot 1 Lot 2
T T Transfer Time
SU Lot 1 Lot 2
Operation B
Operation Overlapping
Costs involved:
Handling costs between work centers
May increase queue and wait for other orders
Idle time if the second batch doesn’t arrive in time
Size of the Transfer Batch
SUA = Set up time operation A
SUB = Set up time operation B
RTA = Run time per piece operation A
RTB = Run time per piece operation B
QT = Total order size
T1 = size of the first transfer batch
T1 = QT x RTA - SUB T2 = QT - T1
RTA + RTB
Size of the Transfer Batch
If the second operation is slower than the first make the first transfer
batch small
i.e. get the slower machine started early
If the second machine is faster than the first make the first transfer batch
large
i.e. the second machine will be able to catch up
Example Problem
Operation A
0 30 730 1,000 (Minutes)
30 70 x 10 = 700 30 x 10 = 300
T T Transfer Time
1,010
One Machine
SU Run
SU Run
Load Report
Tells PAC the current and upcoming load on a work center
Based on standard hours of operation for each order
Load Report
Work Center: 10 Available Time: 120 Hours per week
Description: Lathes Efficiency: 115%
Number of Machines: 3 Utilization 80%
Rated Capacity: 110 standard hours / wk
Week 18 19 20 21 22 23 Total
Released
80 30 0 0 315
Load 105 100
60 80 130 80 350
Planned Load
Total Load 105 100 140 110 130 80 665
Rated
110 110 110 110 110 110 660
Capacity
(Over) /
Under 5 10 (30) 0 (20) 30 (5)
Capacity
Bottlenecks
“a facility, function, department, or resource whose capacity is equal to or less
than the demand put upon it.”
APICs Dictionary 11th Edition
Throughput
Control the work going into and out of a work center: Input/output
control
Queue
(Load, WIP)
Output Rate
Control
Figure 6.13
Input/output control
Work Center: 201
Capacity per period: 40 standard hours
Period 1 2 3 4 5 Total
Planned Input 38 32 36 40 44 190
Actual Input 34 32 32 42 40 180
Cumulative Variance -4 -4 -8 -6 -10 -10
Planned Backlog 32 30 22 18 18 22
Actual Backlog 32 34 30 18 16 20
The difference between the total planned for a given period and the
actual total for that period
Cumulative variance
= previous cumulative variance + actual
- planned
Work Center: 201
Capacity per period: 40 standard hours
Period 1 2 3 4 5 Total
Planned Input 38 32 36 40 44 190
Actual Input 34 32 32 42 40 180
Cumulative Variance -4 -4 -8 -6 -10 -10
Planned Backlog 32 30 22 18 18 22
Actual Backlog 32 34 30 18 16 20
Planned Input 45 40
Actual Input 42 46
Cumulative Variance
Planned Output 40 40
Actual Output 42 44
Cumulative Variance
Planned Backlog 30
Actual Backlog 30
Operations Sequencing
CR=1 On Schedule
= actual time remaining
lead time remaining CR>1 Ahead of
Schedule
on-hand on-order
job status shortages
scrap material shortages
Production Activity Control Summary