Lec03 - Utilization Factor, Plant Capacity Factor - Number of Generating Units

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 15

Lecture 03

Plant Capacity Factor, Load Forecasting


and
Selection of Number of Units
Key Terminologies
• Plant Capacity Factor- Ratio of actual energy produced to
maximum possible energy that can be produced in a given time.
– Indication of reserve capacity of the plant
– Power station always have some reserve capacity to meet future
demands=>installed capacity is greater than maximum demand
– Reserve capacity = Plant capacity – Maximum Demand
• Plant Use Factor- Ratio of KWh generated to product of plant
capacity and the number of hours for which the plant was in
operation.
• Load Duration Curve-Plot of demand in descending order for
given time.
Representation of Different Parameters
Plant Capacity Factor

• Plant
  Capacity Factor
=
 If period considered is one year then
 Annual plant capacity factor =  
 Plant Capacity factor is an indication of the reserve capacity of
the plant
 A power station is so designed that it has some reserve
capacity for meeting the increased load demand in future

4
Reserve Capacity
 Reserve capacity = Plant capacity − Max. demand
 If the maximum demand on the plant is equal to the plant
capacity, then load factor and plant capacity factor will have
the same value
 In such a case, the plant will have no reserve capacity
 Plant Use Factor =
(Station output in KWh)/(Plant Capacity x Hours of use)

5
Utilization Factor
Summary of Definitions
Reasons for Electrical Load Growth
• New customer additions
− Load will increase if more customers are buying the utility's
product.
− New construction and a net population in-migration to the area will
add new customers and increase peak load.
• New uses of electricity
− Addition or replacing of device by existed customers.
− With every customer buying more electricity, the peak load and
annual energy sales will most likely increase.
Load Forecasting
• A technique used by power or energy-providing companies to predict the
power/energy needed to meet the demand and supply equilibrium.
• Systematic procedure for quantitatively defining future loads.
Classification depending on the time period:
• Short term
– 1-2 years for deciding operating procedures & preparing budget
estimates
• Medium-term
– 5-6 years for planning the size of stations.
• Long term
– 20-year period for bigger picture of energy supply problems
Factors Affecting Load Forecasting

• Time factors such as:


– Hours of the day (day/night)
– Day of the week (week day/weekend)
– Time of the year (season)
• Weather conditions (temperature and humidity)
• Class of customers (residential, commercial, industrial, agricultural, public, etc.)
• Special events (TV programmes, public holidays, etc.)
• Population
• Economic indicators (per capita income, Gross National Product (GNP), Gross
Domestic Product (GDP), etc.)
• Trends in using new technologies
• Electricity price
Methods of Load Forecasting

• Sectional Methods or Load Survey Methods


– Visit, enquiries from consumer, category-wise and area-wise.
• Methods of Extrapolation
– Collection of data from various sources & application of
statistical methods
– Handicapped if don’t consider unforeseen developments
• Mathematical Methods
– Use of past data & direct extrapolation (linear or exponential)
– Applicable where adequate statistical data available.
• Energonomics
– Consider economic factors
Choice of Size of Generating Units & Number of Units

•Predicted load curve => Nature of varying demand


•Poor load factor => Greater variation in demand
•Minimum capacity of generating plant must be sufficient to meet
maximum demand.
•Minimum units could be one.
– Variable load =>the prime move and generator would be working
on full load for a very small time => Generating set would not be
running at all the time, under conditions best suited for giving
maximum efficiency=> fuel cost would be greater =>
Uneconomical to run the set under low load conditions.
Choice of Size of Generating Units & Number of Units

• Essential for a power station to maintain continuity & reliability


• To satisfy this requirement, another set of equal capacity
must be installed, in case first set is out of order or being
opened up for repairs.
• => Use of only unit is neither practical nor economical.
• Solution: Choose Number of set to fit the load curve as closely
as possible.
• Reserve required would only be one unit of the largest size
chosen.
• Issues: More space required, Cost of building and maintenance,
More starting, stopping & parallel operation of equipment.
Operation Schedule of Generating Units
Effect of Variable Load on Power Plant Operation & Design

• Variation in load => generators & prime movers have to move


quick to take up or without causing variations in voltage or
frequency =>Control supply of fuel to prime mover through
governeor
• Increase in Load => Slow down rotor =>Reduction in
frequency
Þ Reduction in speed of prime mover => governor acts to take
more fuel => Control of governor is important
• Parallel operation of generators
• Operation of generators for economic dispatch

You might also like