Professional Documents
Culture Documents
17MSE003 PV Plant Devlopement
17MSE003 PV Plant Devlopement
plant development
Prepared by:- Manan Bhatt
17MSE003
outline
• Over view of project development.
• Different stages in project development.
• Site identification.
• Pre-feasibility study.
• Feasibility study.
What is project development.
From inception of the idea to the start of commercial
operation.
• Stages of the project development
Site identification/concept.
Pre-Feasibility
study.
Feasibility study.
Permitting, financing
and contracts.
Engineering, construction
and commercial operation.
Site identification
• Solar resource
• Local climate
• Available area
• Land use
• Topography
• Geotechnical
• Geopolitical
• Accessibility
• Grid connection
• Water availability
• Financial incentives
Pre-feasibility study
• The aim of a prefeasibility study is to develop a preliminary plant design
and investment requirements, which allow further assessment of the
financial viability of a project.
The project site and boundary area, ensuring access to the site is possible,
both legally and technically.
It is given conceptual design of the project giving different options of
technology.
Also The approximate costs for land, equipment, development,
construction and operation of the project, as well as predicted revenue.
A financial model to determine the commercial viability of the project for
further investment purposes.
Grid connection cost and likelihood of achieving a connection within the
required timeline.
Feasibility study:
• The feasibility phase will build on the work undertaken at the
prefeasibility stage by repeating the assessment in more detail using site-
specific data.
• The objective of the feasibility study is to provide more detailed
information on the potential project design, the investment requirements,
and to plan for financing and implementation.
Technical key point of the process enables optimisation
and typically takes into account.
• Module selection.
• Inverter selection.
• Shading angles.
• Operations and maintenance (O&M) requirements.
• Module cleaning strategy.
• Tilt angle, orientation, and tracking.
• Temperature and wind profiles of the site.
• Cable runs and electrical loss minimisation.
• Selection of Switchgear.
• Transformers.
• Substation.
• Earthing and surge protection devices etc.