Professional Documents
Culture Documents
Standard Cost: Chapter Eleven
Standard Cost: Chapter Eleven
Chapter Eleven
10-2
Standard Costs
Standard Costs
Standard
Amount
Direct
Material
Direct Manufacturing
Labor Overhead
Engineer Managerial
Accountant
10-6
Learning Objective 1
Price Quantity
Standards Standards
Setting Standards
Six
Six Sigma
Sigma advocates
advocates have
have sought
sought to
to
eliminate
eliminate all
all defects
defects and
and waste,
waste, rather
rather than
than
continually
continually build
build them
them into
into standards.
standards.
As
As aa result
result allowances
allowances forfor waste
waste and
and
spoilage
spoilage that
that are
are built
built into
into standards
standards
should
should be
be reduced
reduced over
over time.
time.
10-9
Rate Time
Standards Standards
Rate Activity
Standards Standards
A B AxB
Standard Standard Standard
Quantity Price Cost
Inputs or Hours or Rate per Unit
Direct materials 3.0 lbs. $ 4.00 per lb. $ 12.00
Direct labor 2.5 hours 14.00 per hour 35.00
Variable mfg. overhead 2.5 hours 3.00 per hour 7.50
Total standard unit cost $ 54.50
10-12
The
The purchasing
purchasing manager
manager is is responsible
responsible for
for raw
raw
material
material purchase
purchase prices
prices andand the
the production
production
manager
manager isis responsible
responsible for
for the
the quantity
quantity of
of raw
raw
material
material used.
used.
The
The buying
buying and
and using
using activities
activities occur
occur at
at different
different
times.
times. Raw
Raw material
material purchases
purchases maymay be
be held
held in
in
inventory
inventory for
for aa period
period of
of time
time before
before being
being used
used in
in
production.
production.
10-14
Variance Analysis
Variance Analysis
Learning Objective 2
Material Variances
The
The standard
standard price
price is
is used
used to
to compute
compute the
the quantity
quantity variance
variance
so
so that
that the
the production
production manager
manager isis not
not held
held responsible
responsible for
for
the
the purchasing
purchasing manager’s
manager’s performance.
performance.
10-31
Hanson’s
Hanson’s material
material price
price variance
variance (MPV)
(MPV)
for
for the
the week
week was:
was:
a.
a. $170
$170 unfavorable.
unfavorable.
b.
b. $170
$170 favorable.
favorable.
c.
c. $800
$800 unfavorable.
unfavorable.
d.
d. $800
$800 favorable.
favorable.
10-34
Hanson’s
Hanson’s material
material price
price variance
variance (MPV)
(MPV)
for
for the
the week
week was:
was:
a.
a. $170
$170 unfavorable.
unfavorable.
b.
b. $170
$170 favorable.
favorable.
c.
c. $800
$800 unfavorable.
unfavorable.
d.
d. $800
$800 favorable.
favorable. MPV = AQ(AP - SP)
MPV = 1,700 lbs. × ($3.90 - 4.00)
MPV = $170 Favorable
10-35
Hanson’s
Hanson’s material
material quantity
quantity variance
variance (MQV)
(MQV)
for
for the
the week
week was:
was:
a.
a. $170
$170 unfavorable.
unfavorable.
b.
b. $170
$170 favorable.
favorable.
c.
c. $800
$800 unfavorable.
unfavorable.
d.
d. $800
$800 favorable.
favorable.
10-36
Hanson’s
Hanson’s material
material quantity
quantity variance
variance (MQV)
(MQV)
for
for the
the week
week was:
was:
a.
a. $170
$170 unfavorable.
unfavorable.
b.
b. $170
$170 favorable.
favorable.
c.
c. $800
$800 unfavorable.
unfavorable.
d.
d. $800
$800 favorable.
favorable.
Actual Quantity
Used Standard
Quantity
× - ×
Standard Price Standard Price
1,700 lbs. 1,500 lbs.
× ×
$4.00 per lb. $4.00 per lb.
= $6,800 = $6,000
Quantity variance is
unchanged because
actual and standard Quantity variance
quantities are $800 unfavorable
unchanged.
10-41
Learning Objective 3
Quality of production
supervision.
Quality of training
provided to
Production Manager employees.
10-48
Responsibility for
Labor Variances
Hanson’s
Hanson’s labor
labor rate
rate variance
variance (LRV)
(LRV) for
for the
the week
week
was:
was:
a.
a. $310
$310 unfavorable.
unfavorable.
b.
b. $310
$310 favorable.
favorable.
c.
c. $300
$300 unfavorable.
unfavorable.
d.
d. $300
$300 favorable.
favorable.
10-51
Hanson’s
Hanson’s labor
labor rate
rate variance
variance (LRV)
(LRV) for
for the
the week
week
was:
was:
a.
a. $310
$310 unfavorable.
unfavorable.
b.
b. $310
$310 favorable.
favorable.
c.
c. $300
$300 unfavorable.
unfavorable.
LRV = AH(AR - SR)
d. $300 favorable.
d. $300 favorable. LRV = 1,550 hrs($12.20 - $12.00)
LRV = $310 unfavorable
10-52
Hanson’s
Hanson’s labor
labor efficiency
efficiency variance
variance (LEV)
(LEV)
for
for the
the week
week was:
was:
a.
a. $590
$590 unfavorable.
unfavorable.
b.
b. $590
$590 favorable.
favorable.
c.
c. $600
$600 unfavorable.
unfavorable.
d.
d. $600
$600 favorable.
favorable.
10-53
Hanson’s
Hanson’s labor
labor efficiency
efficiency variance
variance (LEV)
(LEV)
for
for the
the week
week was:
was:
a.
a. $590
$590 unfavorable.
unfavorable.
b.
b. $590
$590 favorable.
favorable.
c.
c. $600
$600 unfavorable.
unfavorable.
d.
d. $600
$600 favorable.
favorable.
Learning Objective 4
Quick Check
Zippy
Quick Check
Zippy
Hanson’s
Hanson’s spending
spending variance
variance (VOSV)
(VOSV) for
for variable
variable
manufacturing
manufacturing overhead
overhead for
for
the
the week
week was:
was:
a.
a. $465
$465 unfavorable.
unfavorable.
b.
b. $400
$400 favorable.
favorable.
c.
c. $335
$335 unfavorable.
unfavorable.
d.
d. $300
$300 favorable.
favorable.
10-63
Quick Check
Zippy
Hanson’s
Hanson’s spending
spending variance
variance (VOSV)
(VOSV) for
for variable
variable
manufacturing
manufacturing overhead
overhead for
for
the
the week
week was:
was:
a.
a. $465
$465 unfavorable.
unfavorable.
b.
b. $400
$400 favorable.
favorable.
c.
c. $335
$335 unfavorable.
unfavorable.
d.
d. $300
$300 favorable.
favorable. VOSV = AH(AR - SR)
VOSV = 1,550 hrs($3.30 - $3.00)
VOSV = $465 unfavorable
10-64
Quick Check
Zippy
Hanson’s
Hanson’s efficiency
efficiency variance
variance (VOEV)
(VOEV) for
for variable
variable
manufacturing
manufacturing overhead
overhead for
for the
the week
week was:
was:
a.
a. $435
$435 unfavorable.
unfavorable.
b.
b. $435
$435 favorable.
favorable.
c.
c. $150
$150 unfavorable.
unfavorable.
d.
d. $150
$150 favorable.
favorable.
10-65
Quick Check
Zippy
Hanson’s
Hanson’s efficiency
efficiency variance
variance (VOEV)
(VOEV) for
for variable
variable
manufacturing
manufacturing overhead
overhead for
for the
the week
week was:
was:
a.
a. $435
$435 unfavorable.
unfavorable.
b.
b. $435
$435 favorable.
favorable.
c.
c. $150
$150 unfavorable.
unfavorable. 1,000 units × 1.5 hrs per unit
d.
d. $150
$150 favorable.
favorable.
Quick Check
Zippy
Larger variances,
How do I know in dollar amount
which variances or as a percentage
to investigate? of the standard,
are investigated
first.
10-68 Exhibit
10-9
A Statistical Control Chart
Favorable Limit
• •
• • •
Desired Value
• •
Unfavorable Limit •
•
1 2 3 4 5 6 7 8 9
Variance Measurements
10-69
Learning Objective 6
Throughput Time
Throughput Time
Quick Check
A
A TQM
TQM team
team at
at Narton
Narton Corp
Corp has
has recorded
recorded the
the following
following
average
average times
times for
for production:
production:
Wait
Wait 3.0
3.0 days
days Move
Move 0.5
0.5 days
days
Inspection
Inspection 0.4
0.4 days
days Queue
Queue 9.39.3 days
days
Process
Process 0.2
0.2 days
days
What
What is
is the
the throughput
throughput time?
time?
a.
a. 10.4
10.4 days
days
b.
b. 0.20.2 days
days
c.
c. 4.14.1 days
days
d.
d. 13.4
13.4 days
days
10-73
Quick Check
A
A TQM
TQM team
team at
at Narton
Narton Corp
Corp has
has recorded
recorded the
the following
following
average
average times
times for
for production:
production:
Wait
Wait 3.0
3.0 days
days Move
Move 0.5
0.5 days
days
Inspection
Inspection 0.4
0.4 days
days Queue
Queue 9.39.3 days
days
Process
Process 0.2
0.2 days
days
What
What is
is the
the throughput
throughput time?
time?
a.
a. 10.4
10.4 days
days
b.
b. 0.2
0.2 days
days
Throughput
c. time = Process + Inspection + Move + Queue
c. 4.1
4.1 days
days
= 0.2 days + 0.4 days + 0.5 days + 9.3 days
d.
d. 13.4
13.4 days
days = 10.4 days
10-74
Quick Check
A
A TQM
TQM team
team at
at Narton
Narton Corp
Corp has
has recorded
recorded the
the following
following
average
average times
times for
for production:
production:
Wait
Wait 3.0
3.0 days
days Move
Move 0.5
0.5 days
days
Inspection
Inspection 0.4
0.4 days
days Queue
Queue 9.39.3 days
days
Process
Process 0.2
0.2 days
days
What
What is
is the
the Manufacturing
Manufacturing Cycle
Cycle Efficiency?
Efficiency?
a.
a. 50.0%
50.0%
b.
b. 1.9%
1.9%
c.
c. 52.0%
52.0%
d.
d. 5.1%
5.1%
10-75
Quick Check
AA TQM
TQM team
team at
at Narton
Narton Corp
Corp has
has recorded
recorded the
the following
following
average
average times
times for
for production:
production:
Wait
Wait 3.0
3.0 days
days Move
Move 0.5
0.5 days
days
Inspection
Inspection 0.4
0.4 days
days Queue
Queue 9.39.3 days
days
Process
Process 0.2
0.2 days
days
What
What is
is the
the Manufacturing
Manufacturing Cycle
Cycle Efficiency?
Efficiency?
a.
a. 50.0%
50.0%
b.
b. 1.9%1.9% MCE = Value-added time ÷ Throughput time
c.
c. 52.0%
52.0% = Process time ÷ Throughput time
d.
d. 5.1%5.1% = 0.2 days ÷ 10.4 days
= 1.9%
10-76
Quick Check
A
A TQM
TQM team
team at
at Narton
Narton Corp
Corp has
has recorded
recorded the
the following
following
average
average times
times for
for production:
production:
Wait
Wait 3.0
3.0 days
days Move
Move 0.5
0.5 days
days
Inspection
Inspection 0.4
0.4 days
days Queue
Queue 9.39.3 days
days
Process
Process 0.2
0.2 days
days
What
What is
is the
the delivery
delivery cycle
cycle time?
time?
a.
a. 0.50.5 days
days
b.
b. 0.70.7 days
days
c.
c. 13.4
13.4 days
days
d.
d. 10.4
10.4 days
days
10-77
Quick
Delivery cycle time Check
= Wait time +
Throughput time
= 3.0 days + 10.4 days
= 13.4 days
A
A TQM
TQM team
team at
at Narton
Narton Corp
Corp has
has recorded
recorded the
the following
following
average
average times
times for
for production:
production:
Wait
Wait 3.0
3.0 days
days Move
Move 0.5
0.5 days
days
Inspection
Inspection 0.4
0.4 days
days Queue
Queue 9.39.3 days
days
Process
Process 0.2
0.2 days
days
What
What is
is the
the delivery
delivery cycle
cycle time?
time?
a.
a. 0.50.5 days
days
b.
b. 0.70.7 days
days
c.
c. 13.4
13.4 days
days
d.
d. 10.4
10.4 days
days
10-78
End of Chapter 10