Professional Documents
Culture Documents
Variance Analysis: Project Monitoring, Evaluation & Controlling Rehan Rashid, 0984205, MPM - 3A
Variance Analysis: Project Monitoring, Evaluation & Controlling Rehan Rashid, 0984205, MPM - 3A
SPI = EV/PV
CPI = EV/AC
COST SCHEDULE CONTROL
SCHEDULE PERFORMANCE
INDEX
The schedule performance index is a
measure of how close the project is to
performing work as it was actually
scheduled. If we are ahead of schedule, EV
will be greater than PV, and therefore the
SPI will be greater than 1.
Obviously, this is desirable. On the other
hand, an SPI below 1 would indicate that the
work performed was less than the work
scheduled. Not a good thing.
COST PERFORMANCE INDEX
The cost performance index is a measure of
how close the project is to spending on the
work performed to what was planned to have
been spent.
If you are spending less on the work
performed than was budgeted, the CPI will
be greater than 1.
If not, and you are spending more than was
budgeted for the work performed, then the
CPI will be less than 1.
THANK YOU