Professional Documents
Culture Documents
Pert & CPM
Pert & CPM
Pert & CPM
NETWORKING
(TOTAL 21 PAGES) 1
Network Planning Methods
What is Network Analysis?
Important Terms
Event - An event is a specific instant of time which marks
the start and the end of an activity. It is represented by a
circle and the event number is written within the circle. Eg
: Start a motor or Equipment arrived at site
Activity - Every project consists of a number of job
operations or tasks which are called activities. An activity
is represented by an arrow and it begins and ends with a
event. The activity name is indicated below the arrow and
duration is represented above it. Eg : Equipment Erection,
Spool Erection
Network Planning Methods
They are further classified as
Critical activities - The activities which if delayed will
delay the project.
Non Critical activities - The activities which have some
margin, such that a delay over their estimated time does not
delay the project
Dummy activities - When two different activities start at
the same instant of time, the head events are joined by a
dotted line and this is called a dummy activity.
Critical Path - The path with the longest duration and having
no float is determined and is called Critical Path. The duration
of the critical path is called Project Duration
Network Planning Methods
Earliest Start time - It is the earliest possible time at
which an activity can start and is calculated by moving
from the first to the last event in a network diagram.
10 10
0 0 4 4 15 15 18 18
(4) (3)
1 A 2 5 6
F
8 12
NETWORK DIAGRAM
19 19
6 6 30 30
2 5
33 33
10 24 8
(6)
0 0
4
5 7 16 18
(11) Arrow Diagram
6 7
Total Slack
Activity Dur EST EFT LST LFT
TS = LST - EST
1-2 6 0 6 0 0 0
1-6 5 0 5 2 7 2
2-3 13 6 19 6 19 0
2-4 4 6 10 20 24 14
3-5 11 19 30 19 30 0
4-5 6 10 16 24 30 14
6-7 11 5 16 7 18 2
5-8 3 30 33 30 33 0
7-8 15 16 31 18 33 2
Notes :
1 Critical Path is 1-2-3-5-8 and is marked on the network diagram
2 The length of the critical path or the total project duration (Te) is the sum of the duration of each critical activity ie. 6+13+11+3 = 33 days
3 Variance of the critical path is the sum of the variance of each critical activity ie. 4 +16+4+1 = 25 days
4 The probability that the project will meet the scheduled or the due date is calculated from the following relation
CPM
Critical Path Method
It is applied where activity times are more or less
deterministic
It is used where precise time can be determined from
either past experience or time and motion study
In this method Float available on each activity is
determined.
The path with the longest duration and having no float is
determined and is called Critical Path
PERT & CPM
Steps in CPM
CPM
PERT
Deterministic modeluncertainty
Probabilistic model with knowninactivity
activityduration
duration
Duration is computed based on past experience
from multiple time estimates
Activity oriented
Event oriented
Dummy activityactivity
Use of dummy not used
Used for repetitive jobs jobs
non repetitive
Used forfor
Applied construction Programme
planning and schedulingand business
It deals with
usually doescost
notofconsider
the project
costand their minimization
THANK YOU